November 18, 1996 Mr. D. M. Smith, President PECO Nuclear.

- Nuclear Group Headquarters-Correspondence Control Desk P.- O. Box.195 Wayne, PA 19087-0195

SUBJECT:

PLANT PERFORMANCE REVIEW.(PPR)- LIMERICK GENERATING STATION

Dear Mr. Smith:

On November 7,1996, the NRC staff completed the semiannual Plant Performance Review (PPR) of.the Limerick Generating Station. The staff conducts these reviews for all

. operating nuclear power plants to develop an integrated understanding of safety.

performance. The results are used by NRC management to facilitate planning.and allocation of inspection resources. - The PPR for Limerick involved the participation of all technical divisions in evaluating inspection results and safety performance information for the period May 1996 through October 1996.~ PPRs provide _ NRC management with a current summary of licensee performance and serve as inputs to the NRC Systematic Assessment of Licensee Performance (SALP) and senior management meeting (SMM) reviews.

This letter advises you of our planned inspection effort resulting from the Limerick PPR review.-~ lt is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite..The enclosure details our inspection plan for the next 6 months. The rationale or basis for each inspection outside the core inspection program is provided so that you are aware of the reason for emphash in these program areas. Resident inspections are not listed due to their ongoing and ccntinuous nature.

' We willinform you of any chanpas to the inspection plan. If you have any questions, please contact Walter J. Pascia at 610-337-5258.

ORIGINAL SIGNED BY:

Walter J. Pasciak, Chief Reactor Projects Branch 4 Division of Reactor Projects 1

Docket Nos. 50-352;50-353

Enclosure:

Inspection Plan Ih j{

l i

200017 9611260084 961118 L

PDR ADOCK 05000352 G

PDR n

Mr. D. M. Smith 2

cc w/ encl:

G. A. Hunger, Jr., Chairman, Nuclear Review Board and Director - Licensing W. MacFarland,'Vice President - Limerick Generating Station J. L. Kantner, Regulatory Engineer - Limerick Generating Station Secretary, Nuclear Committee of the Board Nuclear Safety Information Center (NSIC)'

Commonwealth of Pennsylvania t

i i

L i

1 i

Mr. D. M. Smith 3

Distribution w/ encl:

Region l Docket Room (with concurrences)

K. Gallagher, DRP l

D. Screnci, PAO M. Oprendek, DRP l

NRC Resident inspector PUBLIC Distribution w/ encl: (Via E-Mail)

W. Dean, OEDO F. Rinaldi, NRR -

J. Stolz, PDI-2, NRR inspection Program Branch, NRR (IPAS)

R. Correia, NRR R. Frahm, Jr., NRR i

DOCUMENT NAME:

ranch 4\\pprltr. lim T3 receive a copy of this do _

icate in the box: "C" = Copy without attachment / enclosure

  • E' = Copy with attachment / enclosure "N* = No copy l

OFFICE RI:Dg//f Rl:DRP NAME PSpipfarya WPasciak i

DATE 11/g/96 11/ /96 IV OFFICIAL RECORD COPY

o LIMERICK INSPECTION PLAN IP NUMBER '

TITLE DATE/ COMMENTS Effectiveness of Licensee Controls in Identifying, Resolving, and IP 40500 - CO January 1996 Preventing Problems N/A initial Operator Exams 1/20/97 le 37550 - CO Engineering TBD IP 73753 - CO Inservice inspection 2/10/97 IP 83750 - CO Occupational Radiation Exposure (Outage - Unit 2) 2/3/97 IP 81700 - CO Physical Security Program for Power Reactors 1/20/97 IP 82302 - CO Review of Exercise Objectives and Scenarios for Power Reactors 4/21/97 IP 82301 - CO Evaluation of Exercises for Power Reactors 6/23/97 IP 64704 - CO Fire Protection Program 3/3/97 IP - NRC Inspection Procedure CO - NRC Core inspection (NRC Program Requirement)