Responds to GL 96-05, Periodic Verification of Design-Basis Capability of SR Movs. Gpu Intends to Complete Requested Actions & Submit Summary Description of MOV Periodic Verification Program by 970318 as Requested by Generic Ltr
ML20134M793
Person / Time
Site: Crane Constellation icon.png
Issue date: 11/15/1996
From: James Knubel
GENERAL PUBLIC UTILITIES CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
6710-96-2386, GL-96-05, GL-96-5, NUDOCS 9611260042
Download: ML20134M793 (1)


Text

~..

j

)

{

GPU Nuclear,Inc.

4 Route 441 South NUCLEAR Post Office Box 480 Middletown, PA 17057 0480 Tel 717-944 7621 i

November 15,1996 i

6710-96-2386 U. S. Nuclear 'Aegulatory Commission Attn.: Docun ent Control Desk Washington, DC 20555 Nr Sir:

Subject:

Three Mile Island Nuclear Station, Unit 1 (TMI-1)

Operating License No. DPR-50 Docket No. 50-289 Response to Generic Letter (GL) 96-05

Reference:

NRC Letter dated September 18,1996, GL 96-05, " Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves" Generic Letter (GL) 96-05 requested f hat licensees establish a program to verify on a periodic basis that safety-related Motor-Operated Valves (MOVs) continue to be capable of performing their safety functions within the current licensing bases of the facility. The program should ensure that changes in required performance resulting from degradation (such as those caused by age) can be properly identified and accounted for.

GPU Nuclear Inc. (GPUN) intends to complete the requested actions and submit a summary description of the MOV periodic verification program by March 18,1997 as requested by the GL.

Sincerel -

/

J. Knubel Vice President and Director, TMI

)

MRK I

((D cc:

NRC Project Manager f

Administrator, Region I j