ML20134M662

From kanterella
Jump to navigation Jump to search
Forwards Status Summary of Efforts to Date & Schedule for Completion of Thermo-Lag Fire Barrier Activities at BVPS Unit 2
ML20134M662
Person / Time
Site: Beaver Valley
Issue date: 02/14/1997
From: Jain S
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9702200344
Download: ML20134M662 (3)


Text

-.

/

g 8..

v.uy e., si.imn SNppingport.PA 150U-0004 oEn' vin..w.ni February 14, 1997 p.xl4i$ $$

=::=Ln l

U. S. Nuclear Regulatory Commission j

Attention: Document Control Desk Washington, DC 20555-0001

Subject:

Beaver Valley Power Station, Unit No. 2 Docket No. 50-412, License No. NPF-73 Schedule for Completion -

Thermo-Lag 330-1 Fire Barrier Issues i

Our previous submittal of December 27, 1996, identified that a schedule for completion of the Thermo-Lag fire barrier issues at Beaver Valley Power Station (BVPS) j Unit 2 would be provided by February 14,1997. Based on a telecon with NRC staff on January 14, 1997, a progress summary of our efforts to-date was also requested by the NRC. Enclosed as Attachment 1 is a status summary of our efforts to date and a schedule for completion of the Thermo-Lag fire barrier activities at BVPS Unit 2.

In summary, we project that the hardware modifications, utilizing additional Thermo-Lag material for upgrading the electrical conduit raceways required for post-fire safe shutdown capability, will be completed by August 29, 1997. The engineering I

analysis efforts and the ampacity evaluations associated with the Thermo-Lag installations vdll be completed by September 29,1997. If any unforeseen circumstances arise that recessitate a change in this schedule, we will notify you at that time.

j

/.s requested in Generic Letter 92-08, confirmation in writing will be provided upeu completion of the actions noted above. In the interim, fire watch patrols will be

)

mauntained for the affected areas until the Thermo-Lag fire barrier issues have been i

resolved. Should you have any questions concerning this matter, please contact Mr. Roy

[ 9 K. Brosi, Manager, Nuclear Safety at (412) 393-5210.

Sincerely, Y

j Sushil C. Jain c:

Mr. H. J. Miller, NRC Region I Administrator DEllVERING Mr. D. M. Kern, Sr. Resident inspector 0UALITY Mr. D. S. Brinkman, Sr. Project Manager ENERGV a

9702200344 970214 PDR ADOCK 05000412 P

PDR

l

)

/.

ATTACHMENT 1 I

Progress Summary of Thermo-Lag 330-1 Fire Barrier Issues at BVPS Unit 2 i

Thermo-Lag 330-1 fire barrier systems are utilized at BVPS Unit 2 for fire j

protection of safe shutdown circuits on electrical conduit raceways, boxed enclosures j

)

(electricaljunction boxes and pull boxes) and their associated supports. Thermo-Lag is

{

not used to protect cable trays at BVPS Unit 2. A different product, 3M Interam fire l

protection system, is used for protection of the cable trays.

Based on the results ofindustry testing, the boxed enclosures utilizing Thermo-Lag l

330-1 fire barrier systems were upgraded or justified to meet the required 1-hour fire resistance capability. These upgrades, utilizing additional Thermo-Lag trowel grade j

material and stress skin along the butted seams, were completed during the third quarter of1996.

Currently, the smaller size conduit raceways (< 3" in diameter) are being upgraded I

due to a change in methodology for compliance with the Thermo-Lag fire barriers issue.

i The upgrades, which utilize an additional layer of Thermo-Lag pre-formed half shells, 4

are being perfonned due to recent information from the industry and NRC that the use of fire modeling would not be an acceptable alternative for resolving the Thermo-Lag fire j

barrier issues. Approximately 400 feet of 1 1/2" and 2" diameter conduit raceways are being upgraded to meet the required 1-hour fire resistance capability. This effort is

}

}

approximately 65% complete at this time, and is expected to be completed by March 31, l

j 1997.

4 l

j Duquesne Light Company has been actively pursuing a resolution to the Thermo-i j

Lag fire barrier issues for BVPS Unit 2. As such, the larger size conduit raceways (3" to j

6" in diameter) encapsulated with Thermo-Lag 330-1 fire barrier systems were in the process of being evaluated by Duquesne Light Company in comparison to industry j

testing which had successfully qualified as c.1-hour fire rated assembly. One of the parameters previously assumed in the engineering evaluations was the installation i

i method of pre-buttering of the joints with trowel grade material vs. post-buttering after the assembly is configured. In December of 1996, during the upgrade project for small size conduits, a 2" diameter conduit was discovered to be void of the trowel grade material along the seam of the pre-formed half shell installation. Acceptable industry 2

testing on 3" diameter and larger sized conduits has been based on utilizing pre-buttered

~j joints. Industry testing of post-butteredjoints on smaller sized conduits (two tests of 2" diameter conduits) had mixed results. The discovery that post-buttering was used on certain installations at BVPS Unit 2 had a direct impact on the acceptability of the engineering analysis efforts that were being developed forjustification of the as-installed 3" to 6" diameter conduit Thenno-Lag configurations.

i A conservative management decision was made to assume worst case post-buttered j

assemblies and proceed to upgrade the remaining (3" to 6" in diameter) conduits j

encapsulated with Thermo-Lag 330-1 fire barrier systems which are credited for post-fire Page 1 of 2 4

/'

Progrets Summary of Thermo-Lag 330-1 Fire BarrierIssues at BVPS Unit 2 safe shutdown capability. This decision necessitated the need for a scope increase and an extension of the schedule for performing the necessary upgrades for the larger size conduits encapsulated with Thermo-Lag (approximately 900 feet). These upgrades are expected to be completed by August 29,1997. If unforeseen circumstances arise during the course of upgrading the Thermo-Lag installations which necessitate a change in our schedule, we will notify you at that time.

Our objective is to ensure a 1-hour fire rated barrier utilizing Thermo-Lag 330-1 fire barrier systems by bounding our installations at BVPS Unit 2 to a qualified, tested configuration.

Minor anomalies or differences with tested configurations will be evaluated and justification provided in supporting engineering analysis. Engineering analysis providing justification of the Thermo-Lag installations at BVPS Unit 2 including ampacity derating evaluations will be completed by September 29,1997.

l Page 2 of 2