Text
--
Commonwecith Edison Cmnpany 1400 Opus Place Downe.o Grove, IL 60515 5701 February 11,1997 U. S. Nuclear Regulatory Commission Attn.: Document Control Desk Washington,DC 20555
Subject:
Commonwealth Edison Company Quality Assurance Program Topical Report CE-1-A, Revision 65d Byron Units I and 2 (NRC Docket Numbers 50-454 and 50-455) "
Braidwood Units I and 2 (NRC Docket Numbers 50-456 and 50-457)$
Zion Units 1 and 2 (NRC Docket Numbers 50-295 and 50-304) 2, Dresden Units 1,2, and 3 (NRC Docket Numbers 30-10,50-237 and 50-249)
Quad Cities Units I and 2 (NRC Docket Numbers 50-25 t and 50-265) I LaSalle Units I and 2 (NRC Docket Numbers 50-373 and 50-374)2 Attached for your information and use is a copy of Revision 65d to the Commonwealth Edison Company (Comed) Quality Assurance Program Topical Report, CE-1-A, dated February 10,1997.
Revision 65d expands and updates the organizational description section to reflect recent organizational changes; revises sclert position descriptions to clarify responsibilities; and editorially revises select verbiage to improve readability, it is Comed's position that the changes do not reduce commitment and do not require approval by the NRC prior to implementation. Comed will implement the changes immediately.
Sincerely.
)
Lon H. Waldinger Nuclear Oversight Manager i
g/qapolicy/ letters /feblir97(l l)/sms QS97-044 9702180255 970211 PDR ADOCK 05000010 Attachments W
PDR 3 cc:
A. Beach, Regional Administrator - Rill
\\ h R. A. Capra, Director of Directorate III-2, NRR R. R. Assa, Braidwood Project Manager - NRR
~
O G. F. Dick Jr., Byron Project Manager - NRR J T1 Stang, Jr., Dresden Project Manager - NRR qh Q D 1 Skay, LaSalle County Project Manager - NRR R. M. Pulsifer, Quad Cities project Manager - NRR C. Y. Shiraki, Zion Project Manager - NRR C. J. Phillips, Senior Resident Inspector - Braidwood S. D. Burgess, Senior Resident Inspector - Byron C. L. Vanderniet Senior Resident inspector - Dresden M. P. Huber, Senior Rsident inspector - LaSalle County 180061 C. a. Miner. Senior Resident inspecior - Quad Cities R. A. Westberg. Acting Senior Resident inspector - Zion Office of Nuclear Facility Safety - IDNS File A Unicom Company