Dove Morey Southern Nucleat t! ice Presdent Operating Company 6
.. IarleyProject P0. Box 1295 Birmingham. Alabama 35201 Tel 205.992.5131 k
SOUTHERN h February 7,1997 COMPANY Energy ro Serve YourWorld*
Docket No.:
50-348 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Joseph M. Farley Nuclear Plant - Unit i Elevated Tubesheet Sleeve Technical Snecification Amendment Ladies and Gentlemen:
By letter dated August 23,1996, Southern Nuclear requested a technical specification amendment for Farley Units 1 and 2 to allow the use of an elevated tubesheet sleeve. An interim amendment was approved for Unit 2 based on an agreement that Southern Nuclear would submit technical specification amendments for Farley Units 1 and 2 for all laser welded sleeves follow ~mg the completion of the Unit 2 outage.
The laser welded sleeve amendment for Farley Units I and 2 was submitted by letter dated January 10,1997. Consequently, approval of the Unit I submittal dated August 23,1996,is no longer required and is withdrawn.
If there are any questions, please advise.
Respectfully submitted, f,0) 71wel/
Q Dave Morey REM:LWSFNPl. DOC h{[!
cc:
Mr. L A. Reyes, Region 11 Administrator
/
Mr. J.1. Zimmerman, NRR Project Manager Mr. T. M. Ross, Plant Sr. Resident inspector Dr. D. E. Williamson, State Department of Public Health 9702120266 970207 PDR ADOCK 05000348 P