Documents 850117 Meeting W/Util Response Team in Bethesda,Md Re Draft Revs to Rev 0 Issue, Specific Action Plans. Required Actions Will Be Included in Sser 7
ML20134F922
Person / Time
Site: Comanche Peak 
Issue date: 01/25/1985
From: Keimig R
NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM)
To: Noonan V
NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM)
References
NUDOCS 8508220031
Download: ML20134F922 (1)


Text

,

JAN 2 51985 l

Docket No. 50-445-MEMORANDUM FOR:

Vincent S. Noonan, Project Director, Comanche Peak Technical Review Team FROM:

Richard R. Keimig, Comanche Peak Technical Review Team, Test Programs Group I.eader

SUBJECT:

DOCUMEhTATION OF MEETING WITH TUEC CONTRACTOR After the scheduled NRC meeting with TUEC in Bethesda, Maryland, on January 17, 1985, I met briefly with Mr. M. J. Wise, T' EC's Comanche Peak Response J

Team - Testing Programs Leader.

(Mr. Wise had called me on January 14 to inquire if I would be at the scheduled meeting and if we could meet briefly thereafter.

I responded in the affirmative.)

At our meeting Mr. Wise provided me with draft revisions to the Revision 0 Issue - Specific Action Plans in the Test Program area which were included in TUEC's submission to NRC on October 8, 1984. Mr. Wise requested that I review action plans for completeness of TUEC's coverage of our concerns and advise him of the results of my review when completed.

I agreed to Mr. Wise's request, but cautioned him that the results of my review would not represent a final NRC position on the action plans. Mr. Wise stated that he understood.

I also asked Mr. Wise to provide a copy of the draft revised action plans to Mr. Ward F. Smith, NRC Resident Inspector - Comanche Peak, for his review. He agreed.

I took the opportunity of this meeting with Mr. Wise to advise him that the TRT's Test Program Group had determined that an additional action was required by TUEC as a result of a finding identified by TRT's QA/QC Group. That finding related to numerous document control problems which existed between September 1981 and April 1984.

I explained to Mr. Wise that while the TRT's Test Program Group did not identify any adverse affects on the Comanche Peak testing program as a result of document control-problems, because of the nature and number of problems identified by the TRT's QA/QC Group, TUEC would have to investigate -further the potential for those problems to have affected the testing program and provide NRC with the results of that investigation.

I informed Mr. Wise that this ad.tional required action had not been brought to the attention of TUEC previously because the QA/QC Group's effort had not yet been completed when the Test Program Group developed their findings and required actions.

I also informed him that the required action would be included on Supplement 7 to Safety Evaluation Report which would be issued in a short period. Mr. Wise said that he would pass this information on to TUEC management.

This meeting took place between 1:20 p.m. and 2:00 p.m. on the previously stated date.

Richard R. Keimig RSS 9

2 W/85 0FFICIAL RECORD COPY