Advises That Written Summary Rept Will Be Submitted to NRC Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions within 120 Days
ML20134E388
Person / Time
Site: Waterford Entergy icon.png
Issue date: 10/30/1996
From: James Fisicaro
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-96-06, GL-96-6, W3F1-96-0194, W3F1-96-194, NUDOCS 9611010149
Download: ML20134E388 (4)


Text

s '

y Entergy Oper tlins,Inc.

  • Killona. LA 70066 Tel 504 739 6242 m a J.Fisicaro

%?%"s'*

W3F1-96-0194 A4.05 PR October 30,1996 U.S. Nuclear Regulatory Commission  :

ATTN: Document Control Desk I Washington, D.C. 20555  !

Subject:

Waterford 3 SES  ;

Docket No. 50-382 License No. NPF-38 Generic Letter 96-06, Assurance Of Equipment Operability and Containment Integrity During-Design Basis Accident Conditions Gentlemen:

The NRC on September 30,1996 issued Generic Letter 96-06," Assurance Of Equipment Operability And Containment Integrity During Design-Basis Accident Conditions." The purpose of the Generic Letter is the following:

(1) notify addressees about the safety-significant issues that could affect )

containment integrity and equipment operability during accident conditions, (2) request that all addressees submit certain information relative to the issues that have been identified and implement actions as appropriate to address these l issues, and (3) require that all addressees submit a written response to the NRC relative to implementation of the requested actions.

hD92 ' ,

9611010149 961030 PDR ADOCK 05000382 P PDR 010 m

=

Generic Letter 96-06, Assurance Of Equipment Operability and Containment Integrity During Design Basis Accident Conditions W3F1-96-0194 Page 2 October 30,1996 The requested actions are the following:

(1) . determine if containment air cooler cooling water systems are susceptible to either waterhammer or two-phase flow conditions during postulated accident conditions; (2) determine if piping systems that penetrate the containment are susceptible to l thermal expansion of fluid so that overpressurization of piping could occur.

Further, the Generic Letter requests that items one and two should be reviewed with respect to the scenarios referenced in the Generic Letter.

The subject Generic Letter requests that within 30 days of the date of the Generic Letter a response be provided indicating: (1) whether or not the requented actions will be completed, (2) whether or not the requested information will be submitted, and ;

(3) whether or not the requested information will be submitted within the requested {

time period.

l i

Entergy, Waterford 3, will perform an evaluation of Waterford 3 consistent with the j guidance of Generic Letter 96-06 specifically to determine: l (1) If containment air cooler cooling water systems are susceptible to either waterhammer or two-phase flow conditions during postulated accident conditions; (2) If piping systems that penetrate the containment are susceptible to thermal expansion of fluid so that over pressurization of piping could occur.

Items one and two will be reviewed with respect to the scenarios referenced in the Generic Letter.

+

, e ,

~  ;

Generic Letter 96-06, Assurance Of Equipment Operability and Containment Integrity l During Design Basis Accident Conditions  !

W3F1-96-0194

Page 3 I October 30,1996

. A written summary report will be submitted to the NRC stating actions taken in response to the generic letter requested actions, conclusions reached relative to the susceptibility for waterhammer and two-phase flow in the containment air cooler 4 cooling water system and overpressurization of piping that penetrates containment,

! the basis for continued operation of affected systems and components, as applicable, and corrective actions, if any. We plan to submit the information within

120 days of the Generic Letter. However, should there be a valid reason determined j as a result of the ongoing evaluation to change the schedule, Waterford 3 would change this schedule, and we would apprise the NRC in writing of the reason and ,

revised schedule.-

Please contact me at (504) 739-6242 or Tim Gaudet (504) 739-6666 should there be -)

any questions regarding this letter. j l

l Very truly yours, i

'?&

James J. Fisicaro Director Nuclear Safety JJF/RJM/ssf cc: L.J. Callan, NRC Region IV C.P. Patel, NRC-NRR R.B. McGehee N.S. Reynolds NRC Resident inspectors Office

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the matter of )

) .

Entergy Operations, Incorporated ) Docket No. 50-382 Waterford 3 Steam Electric Station )

AFFIDAVIT James J. Fisicaro, being duly sworn, hereby deposes and says that he is Director, Nuclear Safety - Waterford 3 of Entergy Operations, incorporated; that he is duly authorized to sign and file with the Nuclear Regulatory Commission the attached Response to NRC Generic Letter 96-06; that he is familiar with the content thereof; and that the matters set forth therein are true and correct to the best of his knowledge, information and belief.

f>~w h JMes J. Fisidaro -

Director, Nuclear Safety - Waterford 3 STATE OF LOUISIANA )

) ss PARISH OF ST. CHARLES )

Subscribed and sworn to before me, a Notary Public in and for the Parish and State above named this lo' day of N oG JL .1996.

l 5 w kUc Notary Public

- My Commission expires Lv w ' ' e C .

i