Forwards Responses to O Rothberg & Miner 850725 Requests for Info Re Util Actions Resulting from Problem w/Davis-Besse CRD Mechanism Locking Spring
ML20134D042
Person / Time
Site: Rancho Seco
Issue date: 08/12/1985
From: Reinaldo Rodriguez
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Thompson H
Office of Nuclear Reactor Regulation
References
RJR-85-399, NUDOCS 8508190029
Download: ML20134D042 (2)


Text

'

e

$SMUD SACRAMENTO MUNICIPAL UTluTY DISTRICT O 6201 S Street, P.O. Box 15830, Sacramento CA 95852-1830.(916) 452-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA RJR 85-399 August 12, 1985 DIRECTOR OF NUCLEAR REACTOR REGULATION ATTENTION HUGH L. THOMPSON, JR.

DIRECTOR DIVISION OF LICENSING U S NUCLEAR REGULATORY COMMISSION WASHINGTON D C 20555 DOCKET 50-312 RANCHO SECO NUCLEAR GENERATING STATION UNIT NO 1 DISTRICT REVIEW OF DAVIS BESSE CRDil LOCKING SPRING PROBLEM In a telephone conversation on July 25, 1985, Mssrs. Owen Rothberg and Sydney Miner of your staff requested information on the District's actions resulting from the CRDM locking spring problem at Davis Besse. Attached is the District's response to their questions.

If you have any questions, please call Robert Roehler of my staff at (916) 452-32L, extension 4905.

A t

R.

. R0 RIGUEZ ASSISTANT GENERAL \\ ANAGER, NUCLEAR Attachment BgRo8190029 850812

\\

g ADOCK 05000312

'00-PDR

r-o 4

ATT5CHMENT RESPONSE TO NRC QUESTIONS ON DISTRICT'S ACTIONS RESULTING FROM DAVIS BESSE CRDM LOCKING SPRING PROBLEM s

.1.

Have there been any long drop times recorded during control rod drop tests at Rancho Seco?

RESPONSE: The District reviewed the results of past drop time tests and all times are within Technical Specification limits.

2.

Are there any records of long drop times for all reactor trips?

RESPONSE: The District does not record drop times for reactor trips.

3.

Are there any drop times from this outage? Do they compare with previous times?

RESPONSE: A drop time test was performed on June 12, 1985. The results of this test are comparable with previous tests.

4.

Did the District verify that the springs were engaged?

RESPONSE: The District performed a visual inspection of the locking springs. Two springs were found to be disengaged. The springs were re-engaged and exercised to verify they were not damaged.

5.

Is the District considering any followup checks of the springs?

RESPONSE: The District considers this to be a one time occurrence and is not planning any additional inspections. Because of procedure changes, the spring is no longer disengaged from its locked position.

Based on this, there is no mechanism for the spring to become disengaged.

6.

Is the District participating in any B&W Owners Group (B&WOG) efforts?

RESPONSE: The B&WOG is currently considering actions to followup this problem. The District will actively participate in any B&WOG programs related to this.