|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217P3791999-10-21021 October 1999 Forwards NRC Form 396 & NRC Form 398 for Renewal of Licenses SOP-20607-1 & SOP-20610-1.Without Encls ML20217N2521999-10-20020 October 1999 Provides Supplemental Info Re 990405 Containment Insp Program Requests for Relief RR-L-1 & RR-L-2,in Response to 991013 Telcon with NRC ML20217K7541999-10-15015 October 1999 Forwards Rev 1 to Unit 1,Cycle 9 & Unit 2 Cycle 7 Colrs,Iaw Requirements of TS 5.6.5.Figure 5, Axial Flux Difference Limits as Function of Percent of Rated Thermal Power for RAOC, Was Revised for Both Units ML20217G6751999-10-13013 October 1999 Requests Withholding of Proprietary Info Contained in Application for Amend to OLs to Implement Relaxations Allowed by WCAP-14333-P-A,rev 1 ML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20216J9041999-10-0101 October 1999 Forwards Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20216J9161999-10-0101 October 1999 Forwards Response to NRC 990723 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20212E8751999-09-20020 September 1999 Forwards Response to NRC GL 99-02, Lab Testing of Nuclear Grade Activated Charcoal. Description of Methods Used to Comply with Std Along with Most Recent Test Results Encl ML20212E7481999-09-20020 September 1999 Requests Approval Per 10CFR50.55a to Use Alternative Method for Determining Qualified Life of Certain BOP Diaphragm Valves than That Specified in Code Case N-31.Proposed Alternative,Encl ML20212C2191999-09-16016 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, Which Is Current Need for NRC Operator Licensing Exams for Years 2000 Through 2003 of Plant Vogtle,Per Administrative Ltr 99-03 ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20211J5291999-08-30030 August 1999 Forwards Snoc Copyright Notice Dtd 990825,re Production of Engineering Drawings Ref in VEGP UFSAR ML20211J5251999-08-30030 August 1999 Forwards Response to NRC 990727 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20211J7381999-08-27027 August 1999 Informs That Licensee Vessel Data Is Different than NRC Database Based on Listed Info,Per 990722 Request to Review Rvid ML20211E9251999-08-23023 August 1999 Forwards fitness-for-duty Performance Data for Jan-June 1999,as Required by 10CFR26.71(d).Data Reflected in Rept Covers Employees at Vogtle Electric Generating Plant ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210L2181999-08-0202 August 1999 Forwards NRC Form 396 & Form 398 for Renewal of Listed Licenses,Iaw 10CFR55.57.Without Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210C8011999-07-21021 July 1999 Provides Response to NRC AL 99-02,which Requests That Addressees Submit Info Pertaining to Estimates of Number of Licensing Actions That Will Be Submitted for NRC Review for Upcoming Fy 2000 & 2001 ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20209H3881999-07-14014 July 1999 Forwards Revs 1 & 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Unit 1 & 2 ML20209C4041999-07-0101 July 1999 Forwards Rev 29 to VEGP Units 1 & 2 Emergency Plan.Rev 29 Incorporates Design Change Associated with Consolidation of Er Facilities Computer & Protues Computer.Justifications for Changes & Insertion Instructions Are Encl ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20212J2521999-06-21021 June 1999 Responds to NRC RAI Re Yr 2000 Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701 ML20196F9171999-06-21021 June 1999 Forwards Owner Rept for ISI for Vogtle Electric Generating Plant,Unit 1 Eighth Maint/Refueling Outage. Separate Submittal Will Not Be Made to NRC on SG Tubes Inspected During Subj Outage ML20195F8031999-06-11011 June 1999 Forwards Changes to VEGP Unit 1 Emergency Response Data Sys (ERDS) Data Point Library.Changes Were Completed on 990308 While Unit 1 Was SD for Refueling Outage ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 05000424/LER-1998-006, Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Exi1999-05-10010 May 1999 Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Existed ML20206D6411999-04-29029 April 1999 Forwards Vogtle Electric Generating Plant Radiological Environ Operating Rept for 1998 & Vogtle Electric Generating Plant Units 1 & 2 1998 Annual Rept Annual Radioactive Effluent Release Rept ML20206D5881999-04-29029 April 1999 Forwards Rept Which Summarizes Effects of Changes & Errors in ECCS Evaluation Models on PCT for 1998,per Requirements of 10CFR50.46(a)(3)(ii).Rept Results Will Be Incorporated Into Next FSAR Update ML20206D6951999-04-28028 April 1999 Provides Update of Plans for VEGP MOV Periodic Verification Program Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs ML20206C2241999-04-21021 April 1999 Forwards Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2.Page E2-2 Was Iandvertently Omitted from Previously Submitted Rept on 990413 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20209A3741999-04-0505 April 1999 Submits Several Requests for Relief for Plant from Code Requirements Pursuant to 10CFR50.55a(a)(3) & (g)(5)(iii).NRC Is Respectfully Requested to Approve Requests Prior to Jan 1,2000 ML20205H3481999-03-31031 March 1999 Forwards Georgia Power Co,Oglethorpe Power Corp,Municipal Electric Authority of Ga & City of Dalton,Ga Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81 ML20205F9091999-03-29029 March 1999 Submits Rept of Number of SG Tubes Plugged During Plant Eighth Maintenance/Refueling Outage (1R8).Inservice Insps Were Completed on SGs 1 & 4 on 990315.No Tubes Were Plugged ML20205G0761999-03-26026 March 1999 Provides Results of Individual Monitoring for 1998.Encl Media Contains All Info Required by Form NRC 5.Without Encl 1999-09-20
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML20217P3791999-10-21021 October 1999 Forwards NRC Form 396 & NRC Form 398 for Renewal of Licenses SOP-20607-1 & SOP-20610-1.Without Encls ML20217N2521999-10-20020 October 1999 Provides Supplemental Info Re 990405 Containment Insp Program Requests for Relief RR-L-1 & RR-L-2,in Response to 991013 Telcon with NRC ML20217K7541999-10-15015 October 1999 Forwards Rev 1 to Unit 1,Cycle 9 & Unit 2 Cycle 7 Colrs,Iaw Requirements of TS 5.6.5.Figure 5, Axial Flux Difference Limits as Function of Percent of Rated Thermal Power for RAOC, Was Revised for Both Units ML20217G6751999-10-13013 October 1999 Requests Withholding of Proprietary Info Contained in Application for Amend to OLs to Implement Relaxations Allowed by WCAP-14333-P-A,rev 1 ML20216J9161999-10-0101 October 1999 Forwards Response to NRC 990723 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20216J9041999-10-0101 October 1999 Forwards Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20212E7481999-09-20020 September 1999 Requests Approval Per 10CFR50.55a to Use Alternative Method for Determining Qualified Life of Certain BOP Diaphragm Valves than That Specified in Code Case N-31.Proposed Alternative,Encl ML20212E8751999-09-20020 September 1999 Forwards Response to NRC GL 99-02, Lab Testing of Nuclear Grade Activated Charcoal. Description of Methods Used to Comply with Std Along with Most Recent Test Results Encl ML20212C2191999-09-16016 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, Which Is Current Need for NRC Operator Licensing Exams for Years 2000 Through 2003 of Plant Vogtle,Per Administrative Ltr 99-03 ML20211J5291999-08-30030 August 1999 Forwards Snoc Copyright Notice Dtd 990825,re Production of Engineering Drawings Ref in VEGP UFSAR ML20211J5251999-08-30030 August 1999 Forwards Response to NRC 990727 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20211J7381999-08-27027 August 1999 Informs That Licensee Vessel Data Is Different than NRC Database Based on Listed Info,Per 990722 Request to Review Rvid ML20211E9251999-08-23023 August 1999 Forwards fitness-for-duty Performance Data for Jan-June 1999,as Required by 10CFR26.71(d).Data Reflected in Rept Covers Employees at Vogtle Electric Generating Plant ML20210L2181999-08-0202 August 1999 Forwards NRC Form 396 & Form 398 for Renewal of Listed Licenses,Iaw 10CFR55.57.Without Encl ML20210C8011999-07-21021 July 1999 Provides Response to NRC AL 99-02,which Requests That Addressees Submit Info Pertaining to Estimates of Number of Licensing Actions That Will Be Submitted for NRC Review for Upcoming Fy 2000 & 2001 ML20209H3881999-07-14014 July 1999 Forwards Revs 1 & 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Unit 1 & 2 ML20209C4041999-07-0101 July 1999 Forwards Rev 29 to VEGP Units 1 & 2 Emergency Plan.Rev 29 Incorporates Design Change Associated with Consolidation of Er Facilities Computer & Protues Computer.Justifications for Changes & Insertion Instructions Are Encl ML20196F9171999-06-21021 June 1999 Forwards Owner Rept for ISI for Vogtle Electric Generating Plant,Unit 1 Eighth Maint/Refueling Outage. Separate Submittal Will Not Be Made to NRC on SG Tubes Inspected During Subj Outage ML20212J2521999-06-21021 June 1999 Responds to NRC RAI Re Yr 2000 Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701 ML20195F8031999-06-11011 June 1999 Forwards Changes to VEGP Unit 1 Emergency Response Data Sys (ERDS) Data Point Library.Changes Were Completed on 990308 While Unit 1 Was SD for Refueling Outage 05000424/LER-1998-006, Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Exi1999-05-10010 May 1999 Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Existed ML20206D5881999-04-29029 April 1999 Forwards Rept Which Summarizes Effects of Changes & Errors in ECCS Evaluation Models on PCT for 1998,per Requirements of 10CFR50.46(a)(3)(ii).Rept Results Will Be Incorporated Into Next FSAR Update ML20206D6411999-04-29029 April 1999 Forwards Vogtle Electric Generating Plant Radiological Environ Operating Rept for 1998 & Vogtle Electric Generating Plant Units 1 & 2 1998 Annual Rept Annual Radioactive Effluent Release Rept ML20206D6951999-04-28028 April 1999 Provides Update of Plans for VEGP MOV Periodic Verification Program Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs ML20206C2241999-04-21021 April 1999 Forwards Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2.Page E2-2 Was Iandvertently Omitted from Previously Submitted Rept on 990413 ML20209A3741999-04-0505 April 1999 Submits Several Requests for Relief for Plant from Code Requirements Pursuant to 10CFR50.55a(a)(3) & (g)(5)(iii).NRC Is Respectfully Requested to Approve Requests Prior to Jan 1,2000 ML20205H3481999-03-31031 March 1999 Forwards Georgia Power Co,Oglethorpe Power Corp,Municipal Electric Authority of Ga & City of Dalton,Ga Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81 ML20205F9091999-03-29029 March 1999 Submits Rept of Number of SG Tubes Plugged During Plant Eighth Maintenance/Refueling Outage (1R8).Inservice Insps Were Completed on SGs 1 & 4 on 990315.No Tubes Were Plugged ML20205G0761999-03-26026 March 1999 Provides Results of Individual Monitoring for 1998.Encl Media Contains All Info Required by Form NRC 5.Without Encl ML20205H4051999-03-25025 March 1999 Forwards Info on Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81,as Requested IAW 10CFR50.75(f)(1) ML20205H3891999-03-25025 March 1999 Forwards Info on Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81,as Requested IAW 10CFR50.75(f)(1).Page 2 in Third Amend Power Sales Contract of Incoming Submittal Not Included ML20205A9441999-03-25025 March 1999 Forwards VEGP Unit 1 Cycle 9 Colr,Per TS 5.6.5.d ML20205H3811999-03-24024 March 1999 Forwards Info on Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81,as Requested IAW 10CFR50.75(f)(1) ML20205H3621999-03-22022 March 1999 Forwards Info on Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81, as Requested IAW 10CFR50.75(f)(1) ML20204G4361999-03-18018 March 1999 Forwards Summary Rept of Present Level & Source of on-site Property Damage Insurance Coverage for Vegp,Iaw Requirements of 10CFR50.54(w)(3) ML20204C0591999-03-17017 March 1999 Forwards Rev 0 to WCAP-15160, Evaluation of Pressurized Thermal Shock for Vegp,Unit 2 & Rev 0 to WCAP-15159, Analysis of Capsule X from Vegp,Unit 2 Reactor Vessel Radiation Surveillance Program ML20207K9551999-03-11011 March 1999 Forwards Response to Rai,Pertaining to Positive Alcohol Test of Licensed Operator.Encl Info Provided for NRC Use in Evaluation of Fitness for Duty Occurrence.Encl Withheld,Per 10CFR2.790(a)(6) ML20207L9721999-03-10010 March 1999 Forwards Rev 15 to EPIP 91104-C of Manual Set 6 of Vogtle Epips.Without Encl ML20207B0191999-02-25025 February 1999 Forwards Fitness for Duty Performance Data for six-month Reporting Period 980701-1231,IAW 10CFR26.71(d) 05000424/LER-1998-009, Forwards LER 98-009-00 Re Event in Which Improper Testing Method Resulted in Inadequate Surveillances on 9812291999-01-27027 January 1999 Forwards LER 98-009-00 Re Event in Which Improper Testing Method Resulted in Inadequate Surveillances on 981229 ML20199F7701999-01-13013 January 1999 Submits Revised Response to RAI Re Licensee 980713 Proposed Amend to Ts,Eliminating Periodic Response Time Testing Requirements on Selected Sensors & Protection Channels. Corrected Copy of Table,Encl ML20199F7981999-01-13013 January 1999 Forwards Corrected Pages to VEGP-2 ISI Summary Rept for Spring 1998 Maint/Refueling Outage. Change Bar in Margin of Affected Pages Denotes Changes to Rept ML20199G1381999-01-13013 January 1999 Forwards Copy of Permit Renewal Application Package for NPDES Permit Number GA0026786,per Section 3.2 of VP Environ Protection Plan 05000424/LER-1998-007, Forwards LER 98-007-00,re Inadequate Surveillances Due to Improperly Performed Response Time Testing,On 981215,IAW 10CFR50.731999-01-13013 January 1999 Forwards LER 98-007-00,re Inadequate Surveillances Due to Improperly Performed Response Time Testing,On 981215,IAW 10CFR50.73 ML20198F6131998-12-18018 December 1998 Forwards Revised Certification of Medical Exam Form for License SOP-21147.Licensee Being Treated for Hypertension. Util Requests That Individual License Be Amended to Reflect Change in Status ML20198L6631998-12-18018 December 1998 Forwards Amend 37 to Physical Security & Contingency Plan. Encl 1 Provides Description & Justification for Changes & Encl 2 Contains Actual Amend 37 Pages.Amend Withheld,Per 10CFR73.21 ML20198D9291998-12-16016 December 1998 Forwards Requested Info Re Request to Revise TSs Elimination of Periodic Pressure Sensor Response Time Tests & Elimination of Periodic Protection Channel Response Time Tests ML20198D9991998-12-16016 December 1998 Forwards Responses to 980916 RAI Re Response to GL 97-01, Degradation of Control Rod Drive Mechanism Nozzle & Other Vessel Closure Head Penetrations ML20198D8171998-12-14014 December 1998 Forwards NRC Form 396 & Form 398 for Renewal of License OP-20993.Without Encls ML20206N3051998-12-0808 December 1998 Submits RAI Re Replacement of Nuclear Instrument Sys Source & Intermediate Range Channels & post-accident Neutron Flux Monitoring Sys 1999-09-20
[Table view] Category:UTILITY TO NRC
MONTHYEARELV-02056, Forwards Operator Exam Schedule for Facility,Per Generic Ltr 90-07 Request,Including Number of Candidates to Be Examined During NRC Site Visits,Requalification Schedules & Number of Candidates to Participate in Generic Fundamentals Exam1990-09-0606 September 1990 Forwards Operator Exam Schedule for Facility,Per Generic Ltr 90-07 Request,Including Number of Candidates to Be Examined During NRC Site Visits,Requalification Schedules & Number of Candidates to Participate in Generic Fundamentals Exam ELV-01599, Discusses Mods to HED-1114 Re Plant Dcrdr,Per . Amber Monitor Light Covers Installed for Spare Pumps to Make Status of Pumps Readily Apparent to Operator1990-09-0404 September 1990 Discusses Mods to HED-1114 Re Plant Dcrdr,Per . Amber Monitor Light Covers Installed for Spare Pumps to Make Status of Pumps Readily Apparent to Operator ELV-02059, Clarifies 900409 Response to 900323 Confirmation of Action Ltr.Util Made 31 Successful Start Attempts for Diesel Generator (DG) 1A & 29 Successful Start Attempts for DG 1B1990-08-30030 August 1990 Clarifies 900409 Response to 900323 Confirmation of Action Ltr.Util Made 31 Successful Start Attempts for Diesel Generator (DG) 1A & 29 Successful Start Attempts for DG 1B ELV-01956, Forwards Listed Documents in Response to Request for Addl Info Re Settlement Monitoring Program,Per 900614 Request1990-08-30030 August 1990 Forwards Listed Documents in Response to Request for Addl Info Re Settlement Monitoring Program,Per 900614 Request ELV-02050, Responds to Violations Noted in Insp Repts 50-424/90-08 & 50-425/90-08.Corrective Actions:Administrative Procedures Controlling Verification & Validation of Emergency Operating Procedures Will Be Evaluated & Revised as Required1990-08-30030 August 1990 Responds to Violations Noted in Insp Repts 50-424/90-08 & 50-425/90-08.Corrective Actions:Administrative Procedures Controlling Verification & Validation of Emergency Operating Procedures Will Be Evaluated & Revised as Required ELV-02028, Forwards Fitness for Duty Performance Data for First Six Month Period,Per 10CFR26.71(d)1990-08-22022 August 1990 Forwards Fitness for Duty Performance Data for First Six Month Period,Per 10CFR26.71(d) ELV-02022, Forwards Revised LER Re Apparent Personnel Error Leading to Unsecured Safeguards Info.Ler Withheld1990-08-22022 August 1990 Forwards Revised LER Re Apparent Personnel Error Leading to Unsecured Safeguards Info.Ler Withheld ELV-02027, Forwards Rev 0 to Core Operating Limits Rept, for Cycle 3, Per Amends 32 & 12 to Licenses NPF-68 & NPF-79,respectively1990-08-20020 August 1990 Forwards Rev 0 to Core Operating Limits Rept, for Cycle 3, Per Amends 32 & 12 to Licenses NPF-68 & NPF-79,respectively ELV-01973, Submits Rept Re Results of Leakage Exams Conducted During Spring 1990 Refueling Outage,Per TMI Item III.D.1.1.None of Identified Leakage Considered Excessive.Work Orders Issued in Effort to Reduce Leakage to Level as Low Practical1990-08-14014 August 1990 Submits Rept Re Results of Leakage Exams Conducted During Spring 1990 Refueling Outage,Per TMI Item III.D.1.1.None of Identified Leakage Considered Excessive.Work Orders Issued in Effort to Reduce Leakage to Level as Low Practical ELV-01918, Responds to NRC 900612 Request for Comments & Suggestions on Draft risk-based Insp Guide.Util Conducting Individual Plant Exam & Will Withhold Comment on risk-based Insp Guide Until Completion1990-08-0303 August 1990 Responds to NRC 900612 Request for Comments & Suggestions on Draft risk-based Insp Guide.Util Conducting Individual Plant Exam & Will Withhold Comment on risk-based Insp Guide Until Completion ELV-01943, Responds to Violation & Proposed Imposition of Civil Penalty in Insp Repts 50-424/90-11 & 50-425/90-11.Corrective Action: Complete Audit of Contents of Safeguards Info Container Performed & Unassigned Safeguards Info Dispositioned1990-07-27027 July 1990 Responds to Violation & Proposed Imposition of Civil Penalty in Insp Repts 50-424/90-11 & 50-425/90-11.Corrective Action: Complete Audit of Contents of Safeguards Info Container Performed & Unassigned Safeguards Info Dispositioned ELV-01949, Forwards Info Re Status of Pen Branch Fault Investigation. Investigations Conducted So Far Still Indicate That Pen Branch Fault Not Capable1990-07-26026 July 1990 Forwards Info Re Status of Pen Branch Fault Investigation. Investigations Conducted So Far Still Indicate That Pen Branch Fault Not Capable ELV-01500, Forwards Nuclear Decommissioning Funding Plan for Plant.Info Provides Assurance That NRC Prescribed Min Funding Will Be Available to Decommission Facilities1990-07-25025 July 1990 Forwards Nuclear Decommissioning Funding Plan for Plant.Info Provides Assurance That NRC Prescribed Min Funding Will Be Available to Decommission Facilities ML20055H6441990-07-23023 July 1990 Submits Summary of Snubber Types & Sample Plans for Functional Testing to Be Performed During Sept 1990 Outage ML20044B0311990-07-13013 July 1990 Forwards Vogtle Electric Generating Plant Unit 1 Reactor Containment Bldg 1990 Integrated Leakage Rate Test Final Rept. ML20044B1541990-07-12012 July 1990 Responds to NRC 900612 Ltr Re Violations Noted in Insp Repts 50-424/90-08 & 50-425/90-08.Corrective Actions:Eop Step Deviation Documents to Be Upgraded,Adding More Justification & Temporary Change Issued to Correct EOP Deficiencies ELV-01867, Responds to Violations Noted in Insp Repts 50-424/90-10 & 50-425/90-10.Corrective Action:Level Indication Error Corrected After Discrepancy Discovered1990-07-12012 July 1990 Responds to Violations Noted in Insp Repts 50-424/90-10 & 50-425/90-10.Corrective Action:Level Indication Error Corrected After Discrepancy Discovered ML20055F1651990-07-0909 July 1990 Forwards Comments Re NUREG-1410 ELV-01858, Advises That Full Compliance W/Violation Will Not Be Achieved Until Nov 1990,when Evaluation of VP-2693 Complete1990-07-0606 July 1990 Advises That Full Compliance W/Violation Will Not Be Achieved Until Nov 1990,when Evaluation of VP-2693 Complete ML20044A8851990-07-0606 July 1990 Forwards Response to NRC Question on Steam Generator Level Instrumentation Setpoints,Per Revised Instrument Line Tap Locations.Tap Location Will Be Changed from Above Transition Cone to Below Transition Cone ELV-01834, Forwards Response & Comments to Regulatory Effectiveness Review Rept.Encl Withheld (Ref 10CFR73.21)1990-06-28028 June 1990 Forwards Response & Comments to Regulatory Effectiveness Review Rept.Encl Withheld (Ref 10CFR73.21) ML20044A2791990-06-25025 June 1990 Responds to Generic Ltr 90-04, Request for Info on Status of Licensee Implementation of Generic Safety Issues Resolved W/Imposition of Requirements or Corrective Actions. Table Indicating Status of Each Generic Safety Issue Encl ML20043J0171990-06-22022 June 1990 Discusses Corrective Actions for Plant Site Area Emergency, Per 900514 Ltr.Jacket Water High Temp Switches Calibr for Diesel Generators,Using Revised Calibr Procedure ML20043H3061990-06-15015 June 1990 Forwards Rev 3 to ISI-P-014, Inservice Insp Program, for Review & Approval,Per Tech Spec 4.0.5 Re Surveillance Requirements.Rev Includes Withdrawal of Relief Requests RR-45,47,48 & 54 ML20043G2071990-06-12012 June 1990 Forwards Amend 18 to Physical Security & Contingency Plan. Amend Withheld (Ref 10CFR73.21) ML20043G1021990-06-0606 June 1990 Requests Temporary Waiver of Compliance from Requirements of Action Statement 27 of Tech Spec 3.3.2 for Period of 6 H When Two Operating Control Room Emergency Filtration Sys Trains Shut Down for Required Testing ML20043E6901990-06-0505 June 1990 Forwards Rev 12 to Emergency Plan & Detailed Description & Justification of Changes.W/O Rev ML20043G7651990-06-0505 June 1990 Forwards Rev 13 to Emergency Plan & Description & Justification of Changes ML20043B5991990-05-25025 May 1990 Forwards Scope & Objectives Re 1990 Annual Emergency Preparedness Exercise to Be Conducted on 900801 ML20043B5981990-05-24024 May 1990 Responds to Violations Noted in Insp Rept 50-424/90-05 on 900217-0330.Corrective Actions:Locked Valve Procedure Revised to Eliminate Utilization of Hold Tag on Valves Required by Tech Specs to Be Secured in Position ML20043B6291990-05-22022 May 1990 Forwards Rev 5 to ISI-P-008, Inservice Testing Program, Per Tech Specs 4.0.5 Re Surveillance Requirements & Generic Ltr 89-04 ML20043B6351990-05-22022 May 1990 Forwards Rev 2 to ISI-P-016, Inservice Testing Program, Per Generic Ltr 89-04, Guidance on Developing Acceptable Inservice Testing Programs. ML20042H0601990-05-14014 May 1990 Forwards Summary of Corrective Actions for 900320 Site Area Emergency Due to Loss of Offsite Power Concurrent W/Loss of Onsite Emergency Diesel Generator Capability.Truck Driver Disciplined for Lack of Attention ML20042G7301990-05-11011 May 1990 Forwards Revised Pages for May 1989,Jan & Mar 1990 Monthly Operating Repts for Vogtle Electric Generating Plant,Units 1 & 2.Revs Necessary Due to Errors Discovered in Ref Repts ML20042E2911990-04-18018 April 1990 Forwards Amend 17 to Security Plan.Amend Withheld (Ref 10CFR2.790) ML20042E7481990-04-0909 April 1990 Requests Approval to Return Facility to Mode 2 & Subsequent Power Operation,Per 900320 Event Re Loss of Offsite Power Concurrent W/Loss of Onsite Emergency Diesel Generator Capability ML20012E9001990-03-28028 March 1990 Provides Supplemental Response to Station Blackout Rule,Per NUMARC 900104 Request.Mods & Associated Procedure Changes Identified in Sections B & C W/Exception of Mods to Seals Will Be Completed 1 Yr from Acceptance of Analysis ML20012E8581990-03-28028 March 1990 Suppls Response to NRC Bulletin 88-010,Suppl 1 Re Traceability Reviews on Molded Case Circuit Breakers Installed in safety-related Applications.All Breakers Procured & Installed in Class 1E Equipment Reviewed ML20012E9761990-03-27027 March 1990 Requests Withdrawal of Inservice Insp Relief Requests RR-45, RR-47,RR-48 & Conditional Withdrawal of RR-54 Based on Reasons Discussed in Encl,Per 900206 Conference Call ML20012D8561990-03-22022 March 1990 Submits Special Rept 1-90-02 Re Number of Steam Generator Tubes Plugged During 1R2.One of Four Tubes Exceeded Plugging Limit & Required Plugging.Remaining Three Tubes Plugged as Precautionary Measure.No Defective Tubes Detected ML20012D6641990-03-22022 March 1990 Provides Followup Written Request for Waiver of Compliance to Make Tech Spec 3.04 Inapplicable to Tech Spec 3.8.1.2 to Permit Entry Into Mode 5 W/Operability of Diesel Generator a & Associated Load Sequencer Unverified ML20012D3681990-03-19019 March 1990 Forwards Proprietary & Nonproprietary Suppl 2 to WCAP-12218 & WCAP-12219, Supplementary Assessment of Leak-Before-Break for Pressurizer Surge Lines of Vogtle Units 1 & 2, Per 900226 Request.Proprietary Rept Withheld (Ref 10CFR2.790) ML20012D3401990-03-19019 March 1990 Submits Response to 891121 Request for Addl Info Re Settlement Monitoring Program.Current Surveying Procedures Used by Plant to Monitor Settlement of Major Structures Outlined in Procedure 84301-C.W/41 Oversize Drawings ML20012D6631990-03-15015 March 1990 Responds to Generic Ltr 89-19 Re Resolution of USI A-47 on Safety Implications of Control Sys in Lwrs.Overfill Protection Sys Sufficiently Separate from Control Portion of Main Feedwater Control Sys & Not Powered from Same Source ML20012C4681990-03-0606 March 1990 Provides Summary Rept of Property Damage Insurance Levels, Per 10CFR50.54(w)(1) ML20012B2891990-03-0606 March 1990 Forwards Plant Pipe Break Isometrics,Vols 1 & 2 & Advises That Encl Figures Have Been Revised to Be Consistent W/Pipe Analysis in Effect at Time That Unit 2 Received Ol,Including Revs Through 890930.W/309 Oversize Figures ML20012B2421990-03-0606 March 1990 Forwards Cycle 3 Radial Peaking Factor Limit Rept & Elevation Dependent Peaking Factor Vs Core Height Graph ML20011F5291990-02-26026 February 1990 Withdraws 881107 Proposed Amend to Tech Spec 3.8.1.1, Revising Action Requirements for Inoperable Diesel Generator to Clarify Acceptability of Air Roll Tests on Remaining Operable Diesel Generator ML20011F5261990-02-26026 February 1990 Forwards 1989 Annual Rept - Part 1. Part 2 Will Be Submitted by 900501 ML20011E8911990-02-12012 February 1990 Advises That Hh Butterworth No Longer Employed by Util 1990-09-06
[Table view] |
Text
o '
Georg:a Pcwer Company Route 2 802 299A Waynesboro. Georgta 30830 Telephone 404 554-9961 404 724-8114 Soutnem Corrpany Services. Inc Post Off<ce Boi 2625 B rmingnam Atabama 35202 b
reeononcos 8m60" Vogtle Project October 22, 1985 Director of Nuclear Reactor Regulation File: X7T02.6 Attention: Ms. Elinor G. Adensam, Chief Log: GN-721 Licensing Branch #4 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555 NRC DOCKET NUMBERS 50-424 AND 50-425 CONSTRUCTION PERMIT NUMBERS CPPR-108 AND CPPR-109 V0GTLE ELECTRIC GENERATING PLANT - UNITS 1 AND 2 INFORMATION CONCERNING ARCHAE 0 LOGICAL AND HISTORICAL RESOURCES EXEMPT FROM PUBLIC DISCLOSURE
Dear Mr. Denton:
By D. O. Foster's letter of August 3,1984 (File X7T02.6, Log: Gh-400),
Georgia Power Company provided consultant's reports and Cultural Resource Management Plans (CRM) delineating historical and archaeological properties along certain transmission line rights-of-way associated with the Vogtle project. As noted in that letter, additional reports and CRM plans were being developed and would be submitted as they became available.
Enclosed are 10 copies of the Consultant's reports and submittal letters to the Historic Preservation Section (HPS) for the Vogtle-Scherer Transmission Li ne. These reports include the: Resource Inventory and Assessment Studies (Resource Inventory I and II), Tentative Resodrce Treatment Plan, Resource Evaluation and Data Recovery Planning final report on properties GP-BL-01 and GP-J0-05. Also included is the HPS's review of this last report.
This information is being provided with the understanding that it will not be subject to public disclosure. Withholding this information from public disclosure is necessary to protect these resources and ensure their preservation. The basis for withholding from public disclosure were stated in D. O. Foster's letter of August 3,1984.
Additional reports and CRM plans are being developed for submittal to the HPS for the transmission lines associated with the Vogtle Electric Generating Pl ant. Such reports will be submitted to you under the same conditions noted a herein as they become available.
h i y Okt$ TG C ' f' N go 0300 4 AC#3 D *
$h" ,
a mommee d* ' l i
.~ .
1 I
i Director of Nuclear Reactor Regulation
- October 22, 1985
} Page 2
+
If you have any questions concerning the enclosed information please :
- contact us. I
- i
! Yours very truly, 1
i
) i' j J. A. Bailey i JAB /DHW/sro Enclosures cc w/o enclosures:
D. O. Foster M. A. Miller B. A. Jones
- G. Bockhold, Jr.
B. W. Churchill, Esquire l !
L. T. Gucwa i
J. E. Joiner, Esquire R. A. Thomas
) W. C. Ramsey l L. Fowler j T. Johnson !
- D. C. Teper
! Vogtle Project File '
I f
1 t
I i
I i
i i
t i
f
\
?
! t I !
{
i i i i
- Gec ; a Pcaer Cemeamy 260 Pea:atree Stree At.aa:a Ge:r; a 303:3 Te eracre 404 526 65:6 Ma'a; AO 'e5S '
P s: C'? Ce 5 = '545 At.aata Ge:'; a 303:0 M Georgia Power
'*f 517'e'" e PCT'f 5,0ff
- Ronald C. Kester V Ce E'eS Cea!-La*O August 21, 1985 FILE NO. 10-38
SUBJECT:
PLANT V0GTLE PROJECT RE: CRM/V0GTLE-SCHERER TRANSMISSION LINE WALLACE DAM-PLANT SCHERER SECTION GP-BL-01 AND GP-J0-05 Dr. Elizabeth A. Lyon, Chief Historic Preservation Section Department of Natural Resources His:oric Preservation Section 270 Washing cn Street, S. W., Room.704 Atlanta, Georgia 30334 A::ention: Mr. Joe McCannon i
Environ = ental Review Coordinator
Dear Dr. Lyon:
In accordance with the Tentative Resource Treatment Plan (tentative plan) for cultural resources on the cactioned proj ect, Effects Negation-Stage 1 studies have been undertaken for the two properties captioned above, by the firm of Garrow & Associates, Incorporated. A copy of their final report is enclosed for your review and cor= lent. Our views regarding these studies and our intentions with regard to resource managenent strategies for each of the above-captioned properties are discussed below.
GP-BL-01 In accordance with the tentative plan, a Designated Work Area (DWA) has been established at this property for the construc-tion of line tower # 522 (see attached map) . All line construction activities will be confined within this DWA. This DWA has been established primarily in light of our discovery of an historic cemetery within the line corridor at GP-BL-01. That portion of this property lying outside of the DWA will be subj ect to the construction restrictions detailed in Part IV.A (avoidance alterna-tive) of the tentative plan. Therefore, the remainder of this
Dr. Elizabeth A. Lyon (
August 21,_1985 l Page Two i i
discussion relates most specifically to the DWA portion of GP-BL-01.
As discussed in the enclosed report, Garrow & Associates have recom= ended that additional archaeological testing studies should be undertaken in order to more fully determine if sufficient research potential exists to warrant data recovery prior to line tower construction. They propose to combine this additional testing with any warranted data recovery, in order to meet our critical scheduling requirements. All such work would be confined by Georgia Power Co=pany to within the DWA for construction of line tower # 522.
Georgia Power Company does not concur with the recommendation by Garrow & Associates that additional archaeological testing and/or data recovery is required within the DWA. Based upon our review of the data presented in Chapter II of the enclosed report, we believe it highly improbable that intact cultural remains (in the form of occupation-related features) are present within the DWA. We base this upon the considerations that:
(1) soil stratigraphy exhibits no " clear-cut cultural stratigraphy" and that vertical distributions of cultural materials " suggests there is poor vertical separation" of those materials (enclosed report:
p . 24) ;
(2) there are no "particularly striking" patterns in the horizontal distributions of cultural materials (enclosed report: p. 34);
(3) the highest counts of artifacts recovered in test-ing were recovered most often in the general Level 2 soil zone, described by Garrow & Associates as a
"... probable... plow one..." (enclosed report:
see Tables 1-8 and p.19); and (4) no cultural features were found in the excavation of 10, two x two meter (40 square meters) units within the DWA (enclosed report: Figure 2 and pp.
17-18; see also the attached map).
It is also important to note that in all of the 11, two x two meter tests (44 square meters) excavated outside of the DWA, only five soil anomalies were encountered; that upon. excavation, only two of these anomalies were identifiable as cultural features; and that no features of " definite prehistoric" origins were encountered at all (enclosed report: pp. 17-18 and p. 36). While the research questions posited by Garrow & Associates (enclosed report: p. 36) are pertinent to the study of Late Woodland prehis-toric occupations of the Georgia Piedmont, addressing these
i l
l l
Dr. Elizabeth A. Lyon August 21, 1985 l Page Three guestions would be largely dependent upon the occurrence of intact
.eatures related to such a Late Woodland occupation at GP-BL-01.
We believe that the evidence does not suggest that such features are extant inside the DWA (or probably outside) , and that addition-al work would not reverse this finding. Therefore, at this time we are not authorizing Garrow & Associates to proceed with any work.
We are requesting a thorough review by your office of the data presented in the enclosed report. However, the scheduling of line tower construction of this critical proj ect is such that we need to release this property (with adequate and appropriate restrictions upon construction) on or before September 16, 1985.
Given this short time frame, we have determined that if it is finally determined that sufficient research potential is present
- within the DWA to warrant data recovery (based upon the present evidence), or if additional testing work is deemed appropriate, then we will proceed with construction of line tower # 522 under the following strategy. A wooden working platform would be constructed by hand within the DNA at this property. From this platform, would be conducted all construction activities essential to the construction of line tower # 522. The construction of foundations for this tower would not adversely affect any signifi-cant resource values. Test units C, D, E and F (see attached map) were excavated at the locations of these foundations, by Garrow &
Associates, in order to confirm that no historic interments were present. No such interments were determined to be present. As noted above, no prehistoric cultural features were located in either of these four test units. The soils removed in the borings for foundation construction would be spoiled off of the working platform, outside of cultural property GP-BL-01. After completion of all line construction activities , the wooden working platform would be removed by hand and, as necessary, a cover crop of grasses planted without surface scarification, in order to maintain adequate ground Cover.
GP-JO-05.
In accordance with the tentative plan, Georgia Power Company l
has established a Designated Work Area (DWA) for the construction i of line tower # 528 at this historic archaeological property (see attached map). All line construction activities will be confined within this DWA and/or within " Area I" of this: property (Garrow &
Associates has reco== ended no data recovery in this area - see enclosed report, Figure 13 and p. 77) . We are proceeding with j archaeological data recovery (under the research design proposed in I the enclosed report) within the DWA for the construction of line tower # 528. Included in these studies is the reco= mended historical L J
Dr. Elisabeth A. Lyon August 21, 1985 Page Four documentary research for property GP-J0-05 as a whole. In accor-dance with the tentative plan, only the DWA would be released for construction af ter completion of on-site, archaeological data recovery field work therein.
Georgia Power Company has considered the resources identified in the studies reported by the enclosed report, the apparent signifi-cance of those resources, and the long-term management needs of this property as a whole. It is our opinion that in-place conservationin of that portion of this property lying outside of the DWA is not the best interests of the resources represented at GP-J0-05. We believe this is so in consideration of the apparent significance of the resources, and that recovery of resources within the DWA would be essentially meaningless without at least a usable sample of the
- resources outside of the DWA.
Therefore, af ter completion of necessary line construction we would cause to be conducted, archaeological data recovery studies on that portion of GP-J0-05 lying outside of the DWA for construc-tion of line tower # 528. Such studies would be conducted within the parameters of a research design applicable to GP-J0-05 as a whole. Further, the scope of such studies would be directed at recovering a usable sa=ple of resources sufficient to allow the deletion of GP-J0-05 from future (post-construction) management considerations, as detailed in Part V o f the tentative plan. Prior to co=mencing any such data recovery. outside of the DNA, we will consult with your office regarding the appropriateness of the final specifics of scope for such studies. One scope of work we are considering is included in the enclosed report.
Overall, the designation of a two-phase data recovery strategy is consistent with our obj ectives regarding the negation of potential adverse eff ects , prior to both critical proj ect construction and post-construction activities. It is therefore consistent with Part IV.B of the tentative plan.
In summnry, then, we are seeking the following specific consultations at this time. In general, we seek your overall Also, we seek your overall co==ents upon the enclosed report.
co=ments regarding the resource treatment alternatives we have included in this submittal. As regards GP-BL-01, we do not concur with the Garrow & Associates recommendation, and we seek your co==ents regarding any demonstrable research p'otential and/or the need for additional studies within the DWA for construction of line tower # 522. As noted above, if necessitated by scheduling constraints, we will adopt a protective strategy (wooden working platform) for work inside the DWA for construction of line tower
- 522. As regards GP-J0-05, we are proceeding with data recovery
\
1 Dr. Elizabeth A. Lyon August 21, 1985 Page Five inside the DWA for construction of line tower # 528. We propose to conduct additional data recovery outside of this DWA, after completion of essential construction. We seek your comments regarding appropriate data recovery and this overall =anagement strategy.
In order to meet critical construction schedules, we will need to release property GP-BL-01 (with restrictions as may be necessary) on or before September 16, 1985. As noted above, tower construction (tower # 528) will proceed within the DWA at GP-J0-05 as soon as data recovery field work within the DWA is completed.
Therefore, we need to receive your written comments on these matters on or before September 6, 1985. That portion of GP-J0-05 lying outside of the DWA will not be released until we have completed the necessary consultations with your office regarding the scope of data recovery, and until necessary data recovery field work is co=pleted. Your written coc=ents should be addressed and sent to:
James J. Shive, Senior Archaeologist, Land Department 260-2nd Floor, P. O. Box 4545, Atlanta, Georgia, 30302. We will be available at your discretion for any discussion of these matters with you or your staff.
We appreciate this opportunity to work with you in the responsible management of Georgia's nonrenewable cultural resources.
Sincerely, ,f ,
,s' , 's W . ,
James J. Shive Senior Archaeologist JJS:mes Enclosures xc: Mr. R. C. Kester Mr. A. L. Lightsey Mr. R. E. Gentry Mr. J. E. McGuffey Mr. H. H. E::ard Mr. H. D. Brooks '
Mr. A. L. Smith, Jr.
Mr. M. H. Thompson, Jr.
Mr. D. H. Jones Mr. S. G. Powner Mr. W. L. Bowers L ,
Georgio Department of Natural Resources 270 Washington Street, S.W., Hoom 704, Atlanta, Georgia 30334 J. Leonard Ledtwtter, Commissioner
@ Cothren. til, Director September 13, 1985 kFf'j 5
'2[y"on 'j,"
k 404/656 2840 nry Mr. James J. Shive Senior Archaeologist Land Department 260-2nd Floor Post Office Box 4545 Atlanta, Georgia 30302 RE: Resource Evaluation and Data Recovery Planning Plant Vogtle l Burke County, Georgia HP 850822-003
Dear Mr. Shive:
The Historic Preservation Section has reviewed the documen-tation in your letter of August 21, 1985 concerning the Phase II survey of GP-BL-01. Based on the information contained in this report, it is our opinion that this site is not eligible for listing in the National Register of Historic Places for the following reasons:
- 1. The site lacks demonstrated vertical integrity.
- 2. Horizontal integrity is undemonstrated for the site.
- 3. No potential was demonstrated for the occurrence of intact features which pertain to the Late Woodland Period, and identified as the " candidate for data recovery".
Without an eligible site, the management of this resource is the option of Georgia Power. Section 106 compliance respon-sibilities are considered complete as far as these sites are concerned.
If we may be of further assistance, please contact Joe McCannon, Environmental Review Coordinator, at (404) 656-2840.
Sincerely,
?
Eliza th A. Lyon, Chief Historic Preservation Section
, Deputy State Historic Preservation Officer I
l t
r
. o Gect; a Pcwer Ccecaw *
- 260 Peacr:ree Street At;a^ta Geor; a 30303 Te ecrc e 404 526 65:6 Ma trg Acrest Pcs: Ct! ce Scs 4':45 Ara-:3. Gecr; a 30302 M Georgia Power
- e Gr* ts, - g c 5. s ter" Ronald C. Koster V ce 'es ceat-La-d July 1, 1985 FILE NO. 10-38 SUBJECT : PLANT V0GTLE PROJECT RE: CRM/V0GTLE-SCHERER TRANSMISSION LINE Dr. Elizabeth A. Lyon, Chief Historic Preservation Section Department of Natural Resources 27D Washington Street, S. W. - Room 704 Atlanta, Georgia 30334 Attention: Mr. Joe McCannon Environmental Review Coordinator
Dear Dr. Lyon:
Georgia Power Company is conducting cultural resource management planning actions for a transmission line presently under construction between the Vogtle Electric Generating Plant (Burke County, Georgia) and the Robert W. Scherer Electric Generating Plant (Monroe County, Georgia). Garrow & Associates, Inc., has completed a cultural resource inventory and assessment study for a 53.6-mile section of this line, known as the Wallace Dam to Plant Scherer Section. A copy of their final report is enclosed.
Garrow & Associates has identified thirty-three (33) cultural properties on the referenced line section which they recommend as eligible for inclusion in the National Register of Historic Places. All 33 of these properties were recommended as eligible for the National Register in consideration of their potential to contribute archaeological data important in the study of prehistory or history.
Georgia Power Company has assessed resource treatment alternatives for the 33 properties recommended by Garrow & Associ-ates as eligible for National Register listing. A copy of a tentative resource treatment plan for these properties is also l
1 l
l l
L __
s
.= , , ,
Dr. Elizabeth A. Lyon July 1, 1985 Page Two enclosed. This plan discusses cultural resource management planning actions taken to date, and sets out Georgia Power Company s intentions with regard to the management of the 33 properties referenced above.
Georgia Power Company solicits your review and comments upon these planning actions. Specifically, we are seeking your co= cents regarding the National Register cligibility of the properties reco== ended as eligible by Garrow & Associates, as well as the treatcent ceasures proposed in the enclosed tentative treatment plan. Your comments should be addressed and forwarded to: Ja=es J. Shive, Senior Archaeologist, Georgia Power Company, Land Department 260/2nd, P. O. Box 4545, Atlanta, Georgia 30302.
Due to the critical scheduling of construction and resource management activities on this project, we need to receive your comments on or before July 31, 1985.
We appreciate this opportunity to work with you in the canage=ent of Georgia's nonrenewable cultural resources. Please feel free to contact me if any further information is required.
Sincerely, -
f/
W "-
James J. Shive Senior Archaeologist JJS:=cs Enclosures xc: Mr. A. L. Lightsey Mr. R. E. Gentry Mr. J. E. McGuffey Mr. H. D. Brooks Mr. H. H. Ezzard Mr. M. H. Thompson, Jr.
Mr . A . L . Smir ' . , J r .
Mr. D. H. Jones Mr. R. O. Holton Mr. W. L. Bowers