Notification of 851107 Meeting W/Util in Perry,Oh to Determine Readiness for Low Power Ol.Simulator Exercise Planned for 851106.Agenda Encl
ML20133N624
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 10/22/1985
From: Stefano J
Office of Nuclear Reactor Regulation
To: Youngblood B
Office of Nuclear Reactor Regulation
References
NUDOCS 8510290628
Download: ML20133N624 (4)


Text

. -

Docket No.: 50-440 OCT 2 21985 MEMORANDUM FOR: B. J. Youngblood, Chief Licensing Branch No. 1 Division of Licensing FROM: John J. Stefano, Project Manager Licensing Branch No. 1 Division of Licensing

SUBJECT:

FORTHCOMING NRC MANAGEMENT VISIT TO THE PERRY NUCLEAR POWER PLANT SITE DATE & TIME: Thursday, November 7, 1985 9:00 a.m. - 4:00 p.m.

LOCATION: Perry Plant Site Perry, Ohio PURPOSE: To determine the readiness of Perry Unit 1 for a low-power operating license (Agenda enclosed) Note: a simulator exercise is planned for the evening of Wednesday, November 6; time indicated in the enclosed agenda.

PARTICIPANTS: NRC CEI lE M. Bernero M. R. Edelman, et. al J. G. Partlow B. J. Youngblood R. W. Houston D. L. Ziemann J. J. Stefano John J. Stefano, Project Manager Licensing Branch No.1 Division of Licensing

Enclosure:

As stated cc: See next page f

  1. 1/DL LBA t I

JStefano/mac BJiob Mlood l pp/3//85

/h/g /85 8510290628 851022 PDR ADOCK O 4j0

ENCLOSURE AGENDA FOR MANAGEMENT SITE VISIT PERRY NUCLEAR POWER PLANT UNIT 1 Tuesday, November 6, 1985 6:30 p.m. CEI/NRC Management Introduction 7:00 p.m. Simulator Exercise (NRC staff will coordinate the exercise with CEI just prior to the site visit) 8:00 p.m. Simulator Exercise Completed Wednesday, November 7, 1985 9:00 a.m.

Planttourgnddiscussionswithoperatingandmaintenance personnel 12:00 p.m. Lunch S/

a 1:00 p.m. Meeting Discussions Discuss simulator exercise of previous evening Organization, staffing, training Operational experience / personnel qualifications Operational readiness / procedures Lessons learned from other operating plant experiences Preoperational Testing /Startup Testing Technical Specifications certification status Qusiity Assurance operation program implementation 3:30 p.m. Concluding remarks by NRC and CEI 1/

4:00 p.m. Meeting adjourned i

1/ The tour will consist of several groups inspecting various areas of the plant.

CEI should plan to provide an escort for each group. Specific groups will be determined prior to the tour.

El CEI is requested to provide a room to enable the NRC staff to conduct a private working meeting during lunch. I El If time permits, the NRC will entertain questions from the public at the conclusion of NRC/CEI remarks.

_ 1 _ . , . , _ . _ _ .. .

i ..- .

h Mr. Murray R. Edelman Perry Nuciear Power Plant i The Cleveland Electric Units 1 and 2 Illuminating Company

. cc: '

! Jay Silberg, Esq. Mr. Larry 0. Beck Shaw, Pittman, & Trowbridge The Cleveland Electric lj 1800 M Street, N. W. Illuminating Company 1

Washington, D. C. 20006 P. O. Box 97 E-210 Perry, Ohio 44081 Donald H. Hauser, Esq.

The Cleveland Electric Illuminating Company i P. O. Box 5000 Cleveland, Ohio 44101 a ' Resident Inspector's Office 1 U. S. Nuclear Regulatory Commission l Parmly at Center Road l Perry, Ohio 44081 i

Regional Administrator, Region III U. S. Nuclear Regulatory Commission  ;

799 Roosevelt Road Glen Ellyn, Illinois 60137 j Donald T. Ezzone..Esq.

i Assistant Prosecuting Attorney i 105 Main Street

, Lake County Administration Center Painesvil'e, Ohio 44077 i Ms. Sue Hiant  ;

{ 0CRE Interim Representative 8275 Munson Mentor, Ohio 44060-Terry J. Lodge, Esq.

618 N. Michigan Street Suite 105 j Toledo, Ohio 43624 1

1 John G. Cardinal, Esq.

] Prosecuting Attorney Ashtabula County Courthouse

Jefferson, Ohio 44047 f

i i

i t!

l'  ;

i o _ . . . _ . , _ - - . _ _ . , _ ~ - , _ _ _ _ . _ . . . _ . . . _ _ . . . . . _ . . , _ _ . _ . . . . , . _ - . _ , - _ _ _ _ , _ , . ~ . , _ _ _ _ _ , . .

MEETING NOTICE DISTRIBUTION  :

Docket File M NRC Participants R

D R. H. Bernero NSIC .1. G. Partlow '

PRC System B. J. Youngblood LB#1 Reading File R. W. Houston M. Rushbrook D. L. Zeimann ,

Project Manager-' John Stefano J. J. Stefano H. Denton/D. Eisenhut H. Thompson /F. Miraglia T. Novak .

+

W. Butler G. Knighton E. Adensam C. Thomas

  • M. Virgilio J. Zwolinski C. Grimes G. Holahan G. Lainas-S. Varga D. Vassallo E. Butcher, Acting bec: Applicant & Service List J. Stolz T. Speis F. Schroede'r-F. Rowsome Acting Director /DE J. P. Knight W. Johnston R. Bernero W. Houston i

L. Rubenstein i -D. Muller

! Acting Director /DHFS l W. Russell i J. Partlow' j

B. Grimes E. Jordan F. Ingram ACRS (16)-

Attorney, OELD i

Receptionist

(IfmtgisheldinBethesda)

! J. G. Keppler, Region III C. E. Norelius, Region III

, C. J. Paperiello, Region III l

L l.

l

--