ML20133J771

From kanterella
Jump to navigation Jump to search
Revises Response to Violations Noted in Insp Rept 50-155/85-03.Change to Radiation Safety Plan Surveillance Program Does Not Change Commitment,Per Conversation W/P Lovendale
ML20133J771
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 09/23/1985
From: Johnson B
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NUDOCS 8510210079
Download: ML20133J771 (2)


Text

1 j)pl/3 O30mpany Consumers power General off.ces: 1945 West Parnall Road, Jackson. MI 49201 e (517F 788-0550 September 23, 1985 James G Keppler, Administrater Region III US Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137 DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT -

INSPECTION REPORT 85-03 RESPONSE - INFORMATIONAL UPDATE Consumers Power Company submittal dated April 1, 1985 and entitled " Inspection Report 85-03 Response" provided our response to a deviation from a previous commitment (50-155/85-03). As part of.our reply, we stated the following:

"We are currently in the process of revising the Radiation Safety Plan and intend to maintain a surveillance program as part of the plan.

Although the program will not involve the Corporate Office, the major parts of the program will still exist and involve a cooperative effort between Palisades and Big Rock Point."

In the revision process of the Radiation Safety Plan,Section X (Surveillance Program), was deleted in its entirety and the following was added to Section II, Item 2.2.C:

" Audits and surveillances of the Radiation Safety Program shall be carried out in accordance with NODS-QO2. The Corporate Health Physicist may be utilized as the technical expert member of the audit or surveillance team, as needed. Additionally, the Corporate Health Physicist and plant health physics personnel shall respond at the request of anoths* plant's health' physics staff to provide program reviews and advice relating to the requestor's Radiation Safety Program."

.ne question of whether or not this change to our Surveillance Program of the Ra<8tation Safety Plan constituted a change to our commitment prompted us to 8510210079 850923 PDR ADOCK 050 g5

.SEP 2 C 1995ggg OC0985-0009B-NLO2 h

o-

,. n JGKeppler, Administrator 2

Big Rock Point IEIR 85-03 Response September 23, 1985 communicate with Mr. Paul Lovendale of the Region III Staff. Based on our conversation with Mr. Lovendale, it was decided that this was not a-change in commitment but an' informational letter would be appropriate explaining the change.

ym~

Brian D Johnson Staff Licensing Engineer CC Director, Office of Nuclear Reactor Regulation Director, Office of Inspection.and Enforcement NRC Resident Inspector - Big Rock Point 4