Person / Time | |
---|---|
Issue date: | 08/06/1985 |
From: | Obrien J Office of Nuclear Reactor Regulation |
To: | Philips J NRC OFFICE OF ADMINISTRATION (ADM) |
References | |
FRN-50FR27006, RULE-PR-50 AB76-1, NUDOCS 8508090405 | |
Download: ML20133H583 (3) | |
Text
-
- .s ..
[ i UNITED STATES i( I NUCLEAR REGULATORY COMMISSION
%, s...../ WASHINGTON, D.C. 20555 AB76-1 M
Note to: John Philips Rules and Procedures Branch From: John O'Brien Mechanical Structural Engineering Branch Attached please find the index of documents for the regulatory history on the Rulemaking _to modify GDC 4.
John O'Brien
~
.. . .m cc:: Do'cument Control- Desk.
August 6,1985 kDj809405850806 85080hokO5 PDR
-. , c .
AB76-1 POR INDEX FOR MODIFICATIONS OF GENERAL DESIGN CRITERION 4 REQUIREMENTS FOR PROTECTION AGAINST DYNAMIC EFFECTS OF POSTULATED PIPE RUPTURES 10 CFR Part 50 50 FR 27006 July 1, 1985
- 1. Accession number 8407180024 USNRC Memorandum Denton to Minogue, June 29, 1984, " Request For Initiation of Rulemaking Regarding Alternatives to Postulation of Pipe Breaks and Protection Against Associated Dynamic Effects"
- 2. Accession number 8508050485 USNRC Memorandum Arlotto to Speis, August 7, 1984, " Initiation of Rulemaking on GDC 4 Requirements For Protection Against Postulated Pipe Ruptures"
- 3. Accession number 8412270009 USNRC Memorandum Minogue to Dircks, December 4, 1984, " Control of NRC Rulemaking: RES Review to Begin RES Sponsored Rulemaking"
- 4. Accession number 8412270115 USNRC Memorandum Dircks to Minogue, December 12, 1984, " Control of NRC Rulemaking"
- 5. Accession number 8306280124 ACRS Memorandum Ray to Dircks, June 14, 1983, " Fracture Mechanics Approach to Pipe Failures"
- 6. Accession number 8311140312 USNRC Memorandum Stello to Dircks, October 14, 1983, " Minutes of CRGR Meeting Number 47"
- 7. Accession number 8402010410 Generic Letter 84-04, February 1,1984, "Saf ety Evaluation of Westinghouse Topical Reports Dealing With Elimianation of Postulated Fipe Breaks In PWR Primary Main Loops"
- 8. Accession number 8508050497 USNRC Memorandum Speis to Denton, October 15, 1984,
" Leak-Before-Break-Rule" 1
.1
e s . s AB76-1 PDR
- 9. Accession number 8508050474 USNRC Memorandum Chilk to Dircks, June 18, 1985, "SECY-85-108 - Proposed Rule to Modify General Design Criterion 4; Interim Schedular Exemptions"
- 10. Accession number 8508050473 Environmental Assessment For Proposed Regulation to Modify General Design Criterion 4
- 11. Accession number 8504050347 SECY 85-108 Dircks to Con 11ssioners, March 26, 1985, " Proposed Rule to Modify General Design Criterion 4; Interim Schedular Execeptions"
- 12. Accession number 8505290243 Transcript of ACRS Subcommittee Meeting of May 23, 1985, Combined Subcommittees on Metal Components and Structural Engineering (sic)
- 13. Accession number 8505300344 Transcript of ACRS Subcommittee Meeting of May 24, 1985, Combined Subcommittees on Metal Components and Structural Engineering (sic)
- 14. Accession numbers 8110080617, 8109240008, 8108200455 8109240004, 8108200456, 8109240010 8110080042, 8110130007, 8108200450 NUREG/CR-2189, in nine volumes, "Probabilility of Pipe Fracture in the Primary Coolant Loop of a PWR Plant" by Lawrence Livermore National Laboratory.
- 15. Accession number 8412100188 NUREG-1061, Volume 3, " Evaluation of Potential for Pipe Breaks" Report of the USNRC Piping Review Committee
- 16. Accession number 8107010438 WCAP-9558, May 1981, " Mechanistic Fracture Evaluation of Reactor Coolant Pipe Containing Postulated Circumferential Throughwall Crack"
- 17. Accession number 8107010430 WCAP-9787, May 1981, " Tensile and Toughness Properties of Primary Piping Weld Metal For Use In Mechanistic Fracture Evaluation" L _ _ ;