Company of Colorado 2420 W. 26th Avenue, Suite 1000, Denver, Colorado 80211 October 8, 1985 Fort St. Vrain Unit No. 1 P-85354 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555 Attention:
Mr. E. J. Butcher, Jr.
Acting Chief Operating Reactors Branch No. 3 Docket No. 50-267
SUBJECT:
Technical Specification Upgrade Program Request for Extended Draft Submittal Date
REFERENCE:
(1) PSC Letter, Brey to Johnson, dated July 3, 1985 (P-85229)
(2) NRC Letter, Martin to Lee, dated July 19, 1985 (G-85288)
(3) NRC Letter. Hunter to Lee, dated August 22, 1985 (G-85354)
(4) NRC Letter, Hunter to Lee, dated August 27, 1985 (G-85361)
Dear Mr. Butcher:
The purpose of this letter is to request NRC approval to extend the i
submittal date for the final draft of the Fort St.
Vrain upgraded Technical Specifications, from October 15, 1985, to November 30, 1985.
8510160075 851000 g
DR ADOCK 05 g7 D
\\
J
As noted in Reference 1, PSC intended to submit a final draft of the Fort St. Vrain (FSV) upgraded Technical Specifications to the NRC by i
October 15, 1985. Also, this commitment was noted in Reference 2 as a consideration in the NRC's authorization to restart Fort St. Vrain.
One of the essential elements of the final draft Technical Specification submittal is a review by FSV operations personnel, as required by PSC Action Item 16 in Reference 3.
However, recent FSV activities associated with plant restart up to 8%
- power, environmental qualification of electrical equipment, and inservice inspection program revisions in response to NRC comments (Reference 4), are requiring a large degree of operations personnel involvement.
This has not permitted a review of the revised Technical Specifications that would support an October 15 submittal.
During discussions with Mr. G. L. Plumlee III (NRC) on September 30, 1985, it was agreed that a delayed submittal that included a review l
by operations personnel was preferable to an October 15, 1985, submittal that did not include such a review.
In light of this, PSC proposes to subnit the final draft Technical Specifications to the NRC by November 30, 1985. NRC approval of this schedule change is hereby requested, as required by Reference 2.
If you have any questions or comments, please contact Mr. M. H.
Holmes at (303) 571-8409.
Very truly yours, Wir H. L. Brey, Manager Nuclear Licensing and Fuels Division cc:
G. L. Plumlee III, NRC HLB /5WC/ljb i
{
.