Forwards Safety Evaluation Re Resolution of Unresolved Items from Fire Protection Insp Rept 50-309/84-11 Per 831213 Task Interface Agreement 83-122.Items Should Be Considered Closed,Pending Region I Confirmation
ML20133G284
Person / Time
Site: Maine Yankee
Issue date: 07/31/1985
From: Thompson H
Office of Nuclear Reactor Regulation
To: Partlow J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
Shared Package
ML20133G286 List:
References
NUDOCS 8508080623
Download: ML20133G284 (3)


See also: IR 05000309/1984011

Text

July 31, 1985

Docket No. 50-309

MEMORANDUM FOR: James G. Partlow, Director

Office of Inspection and Enforcement

FROM: Hugh L. Thompson, Jr., Director

Division of Licensing, NRR

SUBJECT: FIRE PROTECTION INSPECTION ASSISTANCE (TASK INTERFACE

AGREEMENT (TIA)83-122)

In accordance with the TIA dated December 13, 1983, we are forwarding the

enclosed Safety Evaluation (SE). That SE addresses the resolution of In-

spection Findings at Maine Yankee.

.

Between October 22-26, 1984, we provided assistance in conducting an Appendix R

inspection at Maine Yankee. On January 17, 1985, Inspection Report No. 50-309/84-11

was issued pertaining to that inspection. The following items were left

unresolved pending NRR evaluation:

Item 84-15-03), Unsealed openings in fire barriers

Item 84-15-06), Structural Improvements to fire doors

Item 84-11-04), Non-fire-related seismic gap

Item (84-11-07),011 Collection System for Reactor Coolant Pumps.

By letters dated March 20, 1985 and May 15, 1985, the licensee submitted

additional information, including commitments to improve the level of fire

safety in certain areas and to install an oil collection system for the RCPs.

The enclosed SE addresses those submittals. Therefore, the unresolved items

mentioned'above should be considered closed, pending Region I confirmation.

Tirag'lic/for

Hugh L. Thompson, Jr., Director

Division of Licensing, NRR

Enclosure: DISTRIBUTION:

As stated W EE FILE PKreutzer

NRC'PDR EJButcher

cc: V. Benaroya L PDR TWambach

S. Ebneter, Region I ORB #3 Rdg Glainas

A. Krasapoulos, Region I PSears HThompson

R. Starostecki, Region I

C. Holden, Region I

D. Kubicki

CONTACT:

P. Sears

X27458

  • See previous white for concurrences

ORB #3:DL* ORB #3:DL* ORB #5:DL* ORB #3:DL* AD:0R*

PKreutzer PSears:dd JStang EJButcher Glainas on

7/23/85 7/23/85 7/23/85 7/26/85 7/26/85 / 85

8508080623 850731

PDR ADOCK 05000309

G PDR

,~

F

-

.

.

Docket No. 50-309

MEMORANDUM FOR: James M. Taylor, Director

Office of Inspection and Enforcement

FROM: Hugh L. Thompson, Jr., Director

Division of Licensing, NRP,

SUBJECT: FIRE PROTECTION INSPECTION ASSISTANCE (TASK INTERFACE

AGREEMENT (TIA)83-122)

In accordance with the TIA dated December 13, 1983, we are forwarding the

enclosed Safety Evaluation (SE). That SE addresses the resolution of in-

spection Findings at Maine Yankee.

Between October 22-26, 1984, we provided assistance in conducting an Appendix R

inspection at Maine Yankee. On January 17, 1985, Inspection Report No. 50-309/84-11

was issued pertaining to that inspection. The following items were left

unresolved pending NRR evaluation:

Item (84-15-03), Unsealed openings in fire barriers

Item (84-15-06), Structural Improvements to fire doors

Item (84-11-04), Non-fire-related seismic gap

Item (84-11-07), Oil Collection System for Reactor Coolant Pumps.

By letters dated March 20, 1985 and May 15, 1985, the licensee submitted

additional information, including comitments to improve the level of fire

safety in certain areas and to install an oil collection system for the RCPs.

The enclosed SE addresses those submittals. Therefore, the unresolved items

mentioned above should be considered closed, pending Region I confirmation.

Hugh L. Thompson, Jr., Director

Division of Licensing, NRR

Enclosure: DISTRIBUTION:

As stated NOTKET FILE PKreutzer

NRC PDR EJButcher

cc: V. Benaroya L PDR TWambach

S. Ebneter, Region I ORB #3 Rdg Glainas

A. Krasapoulos, Region I PSears HThompson

R. Starostecki, Region I

C. Holden, Region I

D. Kubicki

CONTACT:

P. Sears

X27458

ORB #5:DL* 0 0 D:DL

ORB #3:DL* ORB #3:DL* L

PKreutzer PSears:dd JStang EQ cher  % HThompson

7/23/85 7/23/85' 7/23/85 r; /g/85 hs / /85

I I

. .

MEMORANDUM FOR
James M. Taylor, Director

i

Office of Inspection and

Enforcement

'

FROM: Hugh L. Thompson, Jr., Director

Division of Licensing, NRR

SUBJECT: FIRE PROTECTION INSPECTION ASSISTANCE (TASK INTERFACE

AGREEMENT (TIA)83-122)

In accordance with the TIA dated December 13, 1983, we are forwarding the

enclosed Safety Evaluation (SE). That SE addresses the resolution of In-

spection Findings at Maine Yankee.

Between October 22-26, 1984, we provided assistance in conducting an Appendix R

inspection at Maine Yankee. On January 17, 1985, Inspection Report No. 50-309/84-11

was issued pertaining to that inspection. The following items were left

unresolved pending NRR evaluation:

Item (84-15-03 , unsealed openings in fire barriers

Item (84-15-06 , Structural Improvements to fire doors

Item (84-11-04 , Non-fire-related seismic gap

Item (84-11-07), Oil Collection System for Reactor Coolant Pumps.

By letters dated March 20, 1985 and May 15, 1985, the licensee submitted

additional information, including commitments to improve the level of fire

safety in certain areas and to install an oil collection system for the RCPs.

The enclosed SE addresses those submittals. Therefore, the unresolved items

mentioned above should be considered closed.

Hugh L. Thompson, Jr., Director

Division of Licensing, NRR

Enclosure: DISTRIBUTION:

As stated DOCKET FILE PKreutzer

NRC PDR EJButcher

cc: V. Benaroya L POR TWambach

S. Ebneter, Region I ORB #3 Rdg Glainas

A. Krasapoulos, Region I PSears' HThoapson

R. Starostecki, Region I

C. Holden, Region I

.

D. Kubicki

CONTACT:

P. Sears