Confirms That All Parties Granted Further Extension of Time Until 851011 to File Motions Re ASLB 850918 Memorandum Concerning Water Recirculation Problems Caused by Paint,Per 851003 Telcon W/Pb Bloch
ML20133E903
Person / Time
Site: Comanche Peak  
Issue date: 10/03/1985
From: Bachmann R
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
To: Bloch P, Johnson E, Mccollom K
Atomic Safety and Licensing Board Panel
References
CON-#485-680 OL, NUDOCS 8510100057
Download: ML20133E903 (1)


Text

/

'o 8

~,,

UNITED STATES NUCLEAR REGULATORY COMMISSION n

7; E

WASHtNGTON, D. C. 20555 Y

p 65 cc7 -8 M0:02 October 3, 1985 i 'b: r I

Peter B. Bloch, Esq., Chairman Dr. Kenneth A. McCollom Administrative Judge Administrative Judge Atomic Safety and Licensing Board Dean, Division of Engineering, U.S. Nuclear Regulatory Commission Architecture and Technology Washington, DC 20555 Oklahoma State University Stillwater, OK 74078 Elizabeth B. Johnson Administrative Judge Dr. Walter H. Jordan Oak Ridge National Laboratory Administrative Judge P. O. Box, Building 3500 881 W. Outer Drive N

Oak Ridge TN 37830 Oak Ridge, TN 37830 In the Matter of Texas Utilities Electric Company, et al.

(Comanche Peak Steam Electric Station, Uiiits 1 and 2)

Docket Nos. 50-445 and 50-446' "o L_

Dear Administrative Judges:

This letter memorializes my telephone conversation with Chairman Bloch on October 3, 1985. With no objection from any of the parties, a further extension of time has been granted to all parties until October 11, 1985 to file, if deemed appropriate, motions regarding the Licensing Board's Memorandum (Water Recirculation Problems Caused by l

Paint) dated September 18, 1985.

Sincerely, Richard G. Bachmann Counsel for NRC Staff cc:

Service List 8510100057 851003 PDR ADOCK 05000445 O