Commonwealth Edison a

one First National Pfar, Chicago, lihnois Address Reply to: Post Office Box 767 Chicago, Illinois 60690 o

July 15, 1985 Mr. James G. Keppler Regional Administrator Region III U.

S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Il 60137

SUBJECT:

Braidwood Station Units 1 and 2 Supplemental Response to Inspection Reports Nos.

50-456/85-015 and 50-457/85-016 NRC Docket Nos. 50-456 and 50-457 REFERENCE (a):

W.

S. Little letter to Cordell Reed dated May 16, 1985.

(b):

D. L. Farrar lette-to James G. Keppler dated June 21, 1985.

Dear Mr. Keppler:

The enclosure to this letter supplements our Reference (b) response to the inspection conducted by Messrs. R. D. Schulz, W. J.

Kropp and R. N. Gardner on March 25 through May 3, 1985 of activities at Braidwood Station as identified in Reference (a).

If you have any further questions on this matter, please direct them to this office.

Very truly yours, 8507220259 850715 PDR ADOCK 05000456 j=_ c =,

- - - = ^ " -

O PDR D. L. Farrar Director of Nuclear Licensing

/klj

'r

, Enclosure cc:

NRC Resident Inspector Braidwood j

h 9(

0371K i

JUL 161985

Supplemental Response to Inspection Report 456/85-015 and 457/85-016 Item 456/85-015-06 In our Reference (b) response under Corrective Action Taken and Results Achieved the following statement was made.

"The NCR has been re-opened and a letter sent to Project Engineering requesting that the design status of all.

supports associated with NCR No. 600 be updated."

We wish to clarify this statement.

NCR No. 600 was reopened on June 21, 1985.

The letter to Project Engineering was transmitted on July 5, 1985.