Order Confirming Rulings Made During 850930 Telcon.Aslb Will Convene Hearing on Rorem Contention 1(a) on 851029.Based on Agreement of Parties,Aslb Authorizes Mailing of Emergency Planning Booklet in Present Form.Served on 851002
ML20133B182
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 10/01/1985
From: Grossman H
Atomic Safety and Licensing Board Panel
To:
COMMONWEALTH EDISON CO., NEINER, B. (BOB NEINER FARMS, INC.), NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
References
CON-#485-662 79-410-03-OL, 79-410-3-OL, OL, NUDOCS 8510030065
Download: ML20133B182 (2)


Text

-

] .

UNITED STATES OF AMERICA Uk{IC0 C NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD -2 A10:14 Before Administrative Judges:

N${ Tk3dh[L RVlU IA" Herbert Grossman, Chaiman Dr. A. Dixon Callihan Dr. Richard F. Cole SERVED 007 -21985 In the Matter of Docket Nos. 50-456

) 50-457 COMMONWEALTH EDIS0N COMPANY

) ASLBP No. 79-410-03-0L

)

(Braidwood Nuclear Power Station, )

Units 1 and 2) ) October 1, 1985

)

i ORDER (Confirming Rulings Made During Telephone Conference of September 30,1985) m

)

During a telephonic conference call on Sept 6mber 30, 1985, in which the Board and parties participated, the following rulings were made by the Board and confirmed in this written order:

1. With the agreement of the parties, the Board will convene the hearing on Rorem Contention 1(a) on October 29, 1985, if hearing room space is available; prefiled testimony is due by October 11, 1985; motions to strike testimony are due by October 18, 1985; goo 30065851001 o ADocK 05000456 PDR 3Co2- \