Text
_
.r December 20,1996 Mr. James E. Cross President - Generation Group Duquesne Light Company Post Office Box 4 Shippingport, PA 15077 i
SUBJECT:
PLANT PERFORMANCE REVIEW (PPR)- BEAVER VALLEY
Dear Mr. Cross:
1 On November 6,1996, the NRC staff completed the semiannual Plant Performance Review i
(PPR) of Beaver Valley Power Station. The staff conducts these reviews for all operating i
nuclear power plants to develop an integrated understanding of safety performance. The results are used by NRC management to facilitate planning and allocation of inspection resources. The PPR for Beaver Valley involved the participation of all technical divisions in evaluating inspection results and safety performance information for the period March 28, 1996, to November 6,1996. PPRs provide NRC management with a current summary of licensee performance and serve as inputs to the NRC Systematic Assessment of Licensee Performance (SALP) and senior management meeting (SMM) reviews.
This letter advises you of our planned inspection effort resulting from the Beaver Valley PPR review. It is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. The enclosure details our inspection plan for the next six months. The rationale or basis for each inspection outside the core inspection program is provided so that you are aware of the reason for emphasis in these program areas. Resident inspections are not listed due to their ongoing and continuous nature.
We willinform you of any changes to the inspection plan. If you have any questions, please contact me (610) 337-5234.
Sincerely, Original Signed By:
Peter W. Eselgroth, Chief Projects Branch 7 9612300040 961220 Division of Reactor Projects PDR ADOCK 05000334 G
PDR Docket No. 50-334; 50-412 l
Enclosure:
Inspection Plan j
Mr. James E. Cross 2
cc w/ encl:
Sushil C. Jain, Vice President, Nuclear Services T. P. Noonan, Vice President, Nuclear Operations L. R. Freeland, Manager, Nuclear Engineering Department B. Tuite, General Manager, Nuclear Operations Unit K. L. Ostrowski, Manager, Quality Services Unit R. Brosi, Manager, Nuclear Safety Department M. Clancy, Mayor Commonwealth of Pennsylvania State of Ohio Distribution w/ encl:
Region 1 Docket Room (with concurrences)
PUBLIC Nuclear Safety Information Center (NSIC)
NRC Resident inspector DRS Director, Region l DRS Deputy Director, Region i DRS Branch Chiefs, Region i DRP Director, Region 1 3
DRP Deputy Director, Regioni I
DRP Branch Chiefs, Region i 1
D. Haverkamp, DRP J
B. Welling, DRP C. O'Daniell, DRP 1
Distribution w/enci (VIA E-MAIL):
J. Stolz, NRR D. Brinkman, NRR
]
W. Dean, OEDO Inspection Program Branch, NRR (IPAS) i i
i l
DOCUMENT NAME: G:\\ BRANCH 7\\BV\\BVPPR12.96 l
To receive e copy of this document. Indicate in the bos: "C" = Copy without ettechment/ enclosure "E'
Copy with attechmentlenclosure "N" = No copy OFFICE DRP\\RI 6
DRP\\RI j
l BWelling [At PEselgrog l
/
- utischt, 127I4/ft f
i
.,eie+dw=..f l
Enclosure 6 MONTH INSPECTION PLAN FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 IP - Inspection Procedure l
Ti - Temporary Instruction j'
CO - Core Inspection l
SI - Safety issue inspection l
RI - Regional Initiative inspection t
I i
l INSPECTION TITLE / PROGRAM AREA START TYPE OF INSPECTION DATE COMMENTS l
IP 40500 Effectiveness of Licensee Controls in 3/31/97 Rl, Review recent changes to identifying, Resolving, and Preventing licensee oversight committees.
Problems
{
IP 37550 Engineering - Visit 1 3/31/97 CO, Focus on system engineering, work management and prioritization, and engineering efforts to validate the current licensing basis.
IP 81700 Physical Security - Visit 1 5/12/97 CO i
l lP 83750 Occupational Radiation Exposure 5/12/97 CO, Focus on high rad area (Radcon) access control and rad worker l
practices.
i lP 84750 Environmental Monitoring 6/2/97 CO IP 71001 Licensed Operator Requal Program TBD CO IP 93801 Design Basis Review TBD Si lP 62706 Maintenance Rule inspection Team TBD Special Review on Maintenance Rule Program. Delayed from 11/96 at licensee request.