Notifies of Change of Facility Organization.Level 2 Mgt Responsibilities Previously Assigned to LL Reed Assumed by Gw Titus,Manager,Engineering & Support Svcs,Effective 850701
ML20132G709
Person / Time
Site: Vallecitos Nuclear Center
Issue date: 07/29/1985
From: Darmitzel R
GENERAL ELECTRIC CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
GEC-85005, NUDOCS 8508050117
Download: ML20132G709 (1)


Text

I GENER AL $ ELECTRIC NUCLEAR ENERGY BuslNEss OPERATIONS GENERAL ELECTRIC COMPANY e VALLECTOs NUCLEAR CENTER

  • PLEAsANTON, CAUFORNIA 94566 GEC-85005 July 29, 1985 Dr. H. R. Denton, Director Office of Nuclear Reactor Regulation U S Nuclear Regulatory Commission Washington D.C. 20555

REFERENCE:

1) Licenser-33, Docket 50-73
2) General Electric Nuclear Test Reactor Safety Analysis Report, NED0-12727, April, 1981

Dear Dr. Denton:

Pursuant to Technical Specification 6.5.2(b)(1) c,r License R-33 General Electric wishes to notify you of a change in the facility organization for the General Electric Nuclear Test Reactor (NTR).

Effective July 1, 1985, Level 2 management responsibilities for the NTR were assumed by the Manager, Engineering and Support Services (G. W. Titus). They had previously been assigned to the Manager, Advanced Nuclear Applications (L. L. Reed). No other management changes were made, and the facility organization shown in Table 6.1 of the Technical Specifications remain accurate.

Sincerely, R. W. Darmitzel, Manager Irradiation Processing Operation RWD:sl 8500050117 850729 PDR ADOCK 05000073 H PDR