ML20132D045

From kanterella
Jump to navigation Jump to search
Informs That Util Has Received Notification That Cycle Length Calculations Have Been Finalized & Confirmed Results Submitted in
ML20132D045
Person / Time
Site: Byron Constellation icon.png
Issue date: 12/12/1996
From: Hosmer J
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9612190129
Download: ML20132D045 (1)


Text

-

Commonwealth Edison Company 14C3 Opus Place Downers Grove, IL 60515-5701 December 12,1996 1

i U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Attention: Document Control Desk j

Subject:

Additional Information Pertaining to Byron Cycle Length Submittal NRC Docket Number: 50-454 l

Reference:

J. Hosmer letter to the Nuclear Regulatory Commission dated December 2,1996, Transmitting Response to j

Additional Information for Byron Cycle Length i

The referenced document transmitted the Commonwealth Edison Company's i

(Comed) response to the Request for Additional Iriformation (RAI) which contained information which support 600 days of operation for Byron Unit 1. At that time, the cycle length calculation had not been finalized.

Subsequent to that submittal, Comed has received notification that the cycle length calculations have been finalized and confirmed the results submitted via the reference letter.

If you have any questions concerning this correspondence, please contact Denise Saccomando, Senior PWR Licensing Administrator at (630) 663-7283.

Sincerely, D

//#pA

/&

/

John B. Hosmer Engineering Vice President cc:

M. D. Lynch, Senior Project Manager - NRR G. Dick, Byron Project Manager - NRR S. Burgess, Senior Resident inspector - Byron A. B. Beach, Regional Administrator - Rlli Office of Nuclear Safety -lDNS 961219o129 961212 PDR ADOCK 0500o454 P

pyg k.Watyronvai 1

A Unicom Q)mpany j

d