Forwards Amend 17 to Fire Protection Rept Which Provides Changes to Facilities & Procedures in Effect as of 960616 & Detailed Change Log
ML20132C965
Person / Time
Site: Byron, Braidwood  Constellation icon.png
Issue date: 12/16/1996
From: Stanley G
COMMONWEALTH EDISON CO.
To:
NRC (Affiliation Not Assigned), NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20132C971 List:
References
NUDOCS 9612190082
Download: ML20132C965 (2)


Text

__

[N Commonwealth Edison

('

) Braidwood Nuclear Power Stron

\\._ / Route #1, Box B4

\\,_/

Braceville, Ilknois 60407 Telephone 815/458-2801 December 16,1996 Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 j

Attention:

Document Control Desk l

Subject:

Amendment 17 to the Fire Protection Report Byron Nuclear Power Station, Units 1 and 2 FPF-37/66: NRC Docket Nos. STN 50-454/455 Braidwood Nuclear Power Station, Units 1 and 2 NPF-72/77: NRC Docket N FN 50-456/457 1

References:

1.

December 16,1994 letter, H.D. Pontious (Comed) to Document Control Desk (NRC),

Fire Protection Report - Amendment 16 2.

June 15,1993 letter, J. B. Hickman (NRC) to D. L. Farrar (Comed), Commonwealth Edison Proposal for Updated Final Safety Analysis Report Revision Submittal Frequency (TAC Nos.

M86432, M86457, M86458, M86459, M86460, M86461, M86462, M86463, M86464, M86465, M86466, and M86467)

In Reference (1) Commonwealth Edision Company (Comed) provided the Nuclear Regulatory commission (NRC) Staff with Amendment 16 to the Byron /Braidwood Stations Fire Protection Report (FPR). Previously, Title 10, Code of Federal Regulations, Part 50, Section 71, Paragraph (b) Subparagraph (4)

[10 CFR 50.71(b)(4)] was revised in response to a federal government initiative to reduce the unnecessary burden of go. ernment regulation by extending the interval between updates oflicensee Final Safety Analysis Reports (FSARs). In Reference (2)

'the Staff agreed with Comed's proposal to provide updates to the Byron /Braidwood Stations Updated Final Safety Analysis Report (UFSAR) to the NRC no later than 24 calendar months from the submittal date of the previous revision. Since the Byron /Braidwood Stations FPR is incorporated by reference into the Byron /Braidwood Stations UFSAR, Chapter 9.5, it is also being updated on a frequency of 24 calendar months from the submittal date of the previous revision.

\\p DR I

17U110 s9 J

I i

f Document Control Desk December 16,1996 j

Page 2 Accordingly, Amendment 17 to the Byron /Braidwood Stations FPR is enclosed. The i

changes included in Amendment 17 are changes to the facilities and procedures that l

were in effect as of June 16,1996. These changes do not represent a decrease in the level of fire protection which would require prior NRC approval in accordance with the following:-

1. Condition 2.C.6 of the Byron Unit 1 Facility Operating License, NPF-37,
2. Condition 2.E of the Byron Unit 2 Facility Operating License, NPF-66,
3. Condition 2.E of the Braidwood Unit 1 Facility Operating License, NPF-72, and
4. Condition 2.E of the Braidwood Unit 2 Facility Operating License, NPF-77.

Attached to this letter is a detailed change log which identifies and explains all changes from Amendment 16 of the Byron /Braidwood Stations FPR. This is being provided as an aid to the Staff to assist in the review of the changes made.

[

i Pursuant to 10 CFR 50.4(b)(6), one (1) signed original and ten (10) copies are being provided to the Document Control Desk, plus one (1) copy to the NRC Region III l

j office and one (1) copy each to the Byron and Braidwood Resident Inspectors offices.

[

Please address any questions or comments regarding this submittal to Harold Pontious,

{

Nuclear Licensing Administrator, at (630) 663-7205.

Very truly yours, l

l tan ey l

ite Vice President l

Braidwood Nuclear Power Station l

GS/EO/grv j

Attachment:

cc:

A. B. Beach, Regional Administrator - Region III G. F. Dick Jr., Byron Project Manager - NRR R. R. Assa, Braidwood Project Manager - NRR l

S. D. Gurgess, Senior Re.sident Inspector - Byron C. Phillips, Senior Resident Inspector - Braidwood Office of Nuclear Facility Safety - IDNS H. D. Pontious - OPUS l-T. Simpkin - Braidwood

.