l JOSEPH M. FARLEY NUCLEAR PLANT UNIT 2 NARRATIVE
SUMMARY
OF OPERATIONS APRIL, 1985 There were no unit shutdowns or significant power reductions during the month of April:
The following major safety-related maintenance was performed in the month of April:
1.
Miscellaneous corrective and preventive maintenance was performed on the diesel generators.
2.
Replacement of containment tendon field anchors is complete.
A total of 130 vertical and sevea horizontal tendon field anchors have been removed, inspected and replaced.
1 l
t I
i l
Fue:q.
g33j I
.m
_-._7-_--
4 n
1 'v OPERATING DATA REPORT DOCKET NO. 50-364 lI DATE May 3.
1985 COMPLETED BY J D. Woodard
~
)
TELEPHONE nos) a90-5156 OPERATING STATUS I
- 1. Unit Name:
b anh M-Niav - l'n i e ?
- 1) Cumulative data since I
- 2. Reporting Pened. Anril. 1985 7-30-81, date of commercial 2652 j
3, Licensed Theneel Power (MWt):
860
- 4. Namepiste Rating (Genes MWe):
i 029
$. Domes Electrical Rating (Net MWe):
850.Z
- 6. Maxiseum Dependable Capeaty (Gross MWe):
i 0
1
- 7. Maximuse Dependable Capacity (Net MWe):
I
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Tjuough 7) Since Last Report. Give Reasons:
i N/A N/A l
- 9. Power Level To Which Restricted. lf Any (Net MWe):
j
- 10. Rennens For Reetnctions. lf Any:
L'/A l
l
!O This Month Yr. to Dete Cuniulative I
719 2,879 32.904
!!. Hours la Reporting Pened 719*0 1.099.8 28,018.3
- 12. Nuneber Of Hours Reactor Was W O'O O*O 138 0 i
- 13. Reacter Reserve Shutdown Hours
- 14. Hours Generator On Line 719.0 I.055.0 z/,o33.i j
- 15. Unit Reestve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thennel Energy Generated (MWH) 1,861,582 2,470,023 69,322,77i 625,238 817,420 22,703,tuz j
- 17. Gross Electrieel Energy Generated (MWH) 3"'994 150,47Z 21.569.394 j
- 18. Net Electrieel Energy Generated (MWH) i
- 19. Unit Service Factor 100,0 36.6 g4,0 f
- 20. Unit Availability Facto, 100.0 36.6 84.o 1
- 21. Unit Capacity Factor (Using MDC Nt) 102.7 32.3 60.9 100.0 31.4 79,I i
- 22. Unit Capacity Factor (Using DER Nt) 0.0 2.6 5,4 i
- 23. Unit Forced Outage Rate
~
. Shutdowns Scheduled Over Next 6 Months (Type. Dete and Duration of Eachl:
24 4
N/A 1
1 i
- 25. If Shut Down At End Of Report Period. Estbnated Date of Startup:
N/A.
t
- 26. Units in Test Saatus (Prior to Commercial Operation):
Forecast Achieved
-i INITIAL CRITICALITY ns-nn_a1 05-08-R1 INITIAL ELECTRICITY 05-24-81 05-25-81 COMMERCIAL OPERATION 08-01-81 07-30-81
]
(9/77i
DOCXIT NO.
s n-an t, 2
un,r
[
DATT. M"V I*
I985 J. D. Woodard COMPLETED BY l
(205) 899-5156 TELEPHONE April, 1985 MONTl!
DAY AVERACE DAILY POWER LEVEL DAY AYERACE DAILY POWER LEVEL plWe Net)
OlWe Net) i g,
824 17 811 839 830 2
gg M 1 - -- -
_ -..... _ g 9 _
g30 3
831 830 4
791 830 3
21 6
827
, g, 828 838 824 7
g 842 827 g
- 4 9
845 23-827 10 Ala 26 A?R 833 828 gg g
810 12 23 821 828 824 g3 828 826 g4 30 15 83I 38 16 834 i
INSTRUCT.ONS On tids formst. fist the averste daily umt power icvet in MW'e Net for each day in the repoeting month. Campute to
, the nessert whole me;swait.
O O
O 30-364 UN4T StM11 DOWNS AND POWER REIMICIl0NS DOCKETNO. J. M. Farley - Unit.2 ggggyggg DATE May 3.
1985 COMPLETED sY 1 D. Woodard-REPORT MONfil Anrf1 14Rs TELEPl80NE (205) 899-5156 "t.
u
=
j~I 3s3 Evens
[i Acikas su
- EG ticasse E,
Cause & Casseceive No.
Ibse
[
f
-[
j;fgg Nepsw #
g p,,,,,,g,g,,,,,,
in U u
e-d THERE WERE NO UNI E SHUTD MNS OR SI ;NIFICANT POL ER R1 DUCTIONS DURING THE MONTH OF APRIL.
I 2
3 4
F: Fusced Meason:
MeshoJ:
Exhibit G. las suctions S: Selieduled A-Equipocas Failuse(Emplain) 1 -Manual for Psepasasstai of Dasa B-Maintenance of Test 2 Maamal Scram.
Entry sheets foe t.iccusee C-Refuehag 3 Automatic Scraen.
Event Rep wa (t.ER n file (NUREG-D Reguiassay Ress:ection 4 Osleet (Emplain) 0161)
E4hiesaior Ts46ains A license Esamination F-Adadaistsasive 5
G Ope asianial Essur (Eng.laisa)
Eshdait I Same Souue
('J/77) 11Othc (Explain) 1
I.
i t.
is a4
. Altbams Power Company 6C0 Norm 18th Street Post Office Box 2641 04rmingham. Alabama 35291 Telephone 205 78M090 R. P. McDoneed Senior Vice President Fhntndge Bwiding
/\\lilkX)[ll3lDWCf ry s w,-o e,cn z, 4-m May 13, 1985 Docket No. 50-364 Director, Office of Resource Management U. S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Sir:
RE: Joseph M. Farley Nuclear Plant Unit 2 Monthly Operating Data Report Attached are two (2) copies of the April 1985 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 2, required by.Section 6.9.1.10 of Appendix A of the Technical Specifications.
If you have any questions, please advise.
Yours very t ly,,
b R. P. Mcdonald RPM /KWM: sam Enclosures xc: Director, IE (10 copies)