Provides Status of IE Bulletin 79-14 Program Re Seismic Analysis for as-built safety-related Piping Sys.Final Installation of Insulation Will Be Verified Compatible W/ Seismic Evaluations & Stress Analysis
ML20129C717
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 01/14/1985
From: Koester G
KANSAS GAS & ELECTRIC CO.
To: Denise R
NRC - WOLF CREEK TASK FORCE
References
IEB-79-14, KMLNRC-85-032, KMLNRC-85-32, NUDOCS 8507160307
Download: ML20129C717 (2)


Text

h/)l$

KANSAS GAS AN iRlC CO f

~ ~ ~ ' - ~

TFE ELECTAC COMPANY f j JAN 2 l 1985 F atenue nossTen vica earsom. ucteu h(dl %l

!),

January' D '985-Mr. R.P. Denise, Director Wolf Creek Task Force U.S. Nuclear Regulatory Commission, Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 KMLNRC 85-032 Re: Docket No. STN 50-482 Ref: SLNRC 79-18, dated November 1, 1979 KLMNRC 84-209, dated December 1,1984 Subj: IE BULLETIN 79-14: SEISMIC ANALYSIS FOR AS-BUILT SAFETY-RELATED PIPING SYSTEMS AT WOLF CREEK GENERATING STATION

Dear Mr. Denise:

The referenced letter SLNRC 79-18 provided the SNUPPS response to the subject IE Bulletin. The purpose of this letter is to provide the status of j our IE Bulletin 79-14 program.

Bechtel Power Corporation was contracted by Kansas Gas and Electric Company-(KG&E) to conduct the required walkdowns and reviews, Becthel has completed I the initial walkdown of all piping and hangers within the scope of IE Bulletin 79-14 and has issued punch lists of findings identified during this process.

The Bechtel findings were grouped as follows: Group 1 includes all items which pertain to the physical installation of piping and hangers. Group 2 includes items pertaining to installation of insulation, coping of insula- l tion at interferences and verification of penetration closure installation.

All items in Group 1 will be closed with completion of ASME Code N-5 data reports. Close-out of Group 2 items is coordinated with the completion of insulation. The referenced letters indicated that our IE Bulletin 79-14 ,

program would be completed by fuel load. Although the program is nearly l complete, final installation of insulation wi?1 keep the 79-14 program from being finished before fuel load.

8507160307 850114 PDR l

ADOCK 05000482 '

G PDR l6ll N 201 N. Market - Wichita, Kansas - Mail Address: RO. Box 208 I wichita, Kansas 67201 - Telephone: Area Code (316) 261-6451

Mr. R.P. Denise Page 2 We will verify that final installation of insulation is compatible with seismic evaluations and stress analysis. However, the very nature of this work, coupled with our plans for final installation, should preclude any effect on the validity of seismic and stress analyses. Items which are more likely to have an effect, i.e., the physical installation of piping and hangers, will be completed prior to fuel load. It is KG&E's judgement that completion of 79-14 items which do not impact piping or hanger configuration will not compromise plant safety and can be completed subsequent to fuel load.

Yours very truly, fd v Y Glenn L. Koester Vice President - Nuclear GLK: dab xc: P0'Connor HBundy WGuldemond RCDeYoung