ML20129B528

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Rept 50-267/85-12.Corrective Actions:Responsibility Placed on Contractor Superintendent to Ensure Needed Signatures Obtained
ML20129B528
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 06/05/1985
From: Gahm J
PUBLIC SERVICE CO. OF COLORADO
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20129B476 List:
References
P-85189, NUDOCS 8507290180
Download: ML20129B528 (2)


Text

_ - - - - -

S eubiicservice 16805 WCR 19 1/2, Platteville, Colorado 80651

  • "* " Y ' " '

June 5, 1985 Fort St. Vrain Unit No. 1 P-85189 Regional Administrator Attn: Mr. E. H. Johnson

<<P!

U"~~~z.

'nW_

Region IV D - AG}

0i U. S. Nuclear Regulatory Commission  ;* \

JJNI I 611 Ryan Plaza Drive, Suite 1000 3 Arlington, Texas 76011 Docket No. 50-267

SUBJECT:

I&E Inspection Report 85-12

REFERENCE:

NRC Letter, Johnson to Lee, dated 05/07/85 (G-85174)

Dear Mr. Johnson:

This letter is in response to the Notice of Violation received as a result of inspections conducted at Fort St. Vrain during the period April 15-19, 1985. The following response to the items contained in the Notice of Violation is hereby submitted:

10 CFR 50, Appendix B, Criterion V, requires that activities affecting quality shall be prescribed by, and accomplished in accordance with documented procedures. This requirement is implemented, in part, by Administrative Procedure G-2, which requires compliance with authorized procedures or initiation of action to obtain changes if compliance is not possible.

Contrary to 'ie

.. above, the Authorization Sheet to Rework Task 1 of FHPWP-100-11 had not been filled out or signed by the shift manager and health physics prior to starting work. Step 11.0 of that Rework Task also was not signed by health physics.

Task 42 of FHPWP-100-39 was completed without the health physics notification signature required in Step 42.0.

8507290180 850723 PDR ADOCK 05000267 G PDR h

> .~

s, Task 15 of FHPWP-100-39 was signed out at 5:00 a.m. on April 17, 1985, and not signed in by the end of the shift as required by that procedure.

This is a Severity Level V Violation. (Supplement I)

(267/8512-01)

(1)The. corrective steps which have been taken and the results achieved:

Discussions were held with all CR00A Refurbishment Program Shift Managers and- contractor superintendents emphasizing the importance of the administrative procedure controls sited as having been violated. Since the responsibility for ensuring that such signatures were obtained had not been specifically assigned previously, the responsibility was placed on the contractor superintendent. Additionally, a practice of keeping the contractor superintendent and lead QC representative over to verify that all paperwork associated with their assigned shift's work was properly signed-off was established. This practice has proven very effective in precluding procedure violations of this nature.

(2) Corrective steps which will be taken to avoid further violations:

No further corrective actions are anticipated.

(3) The date when full compliance will be achieved:

May 15, 1985.

Should you have any further questions, please contact Mr. Frank J. Novachek, (303) 571-7436, ext. 201.

Sincerely, J. W. Gahm Manager, Nuclear Production Fort St. Vrain Nuclear Generating Station JWG/djc