ML20129A055

From kanterella
Jump to navigation Jump to search
Responds to FOIA Request for Plant Biennial Quality Audits for 1978,1980 & 1982 & Idvp for 1982.No Biennial Quality Audits Performed.Evaluation Rept by Util & Other Documents Listed in App Available in PDR
ML20129A055
Person / Time
Site: Midland
Issue date: 06/05/1985
From: Felton J
NRC OFFICE OF ADMINISTRATION (ADM)
To: Butler N
SMITH, HAUGHEY, RICE & ROEGGE
References
FOIA-85-283 NUDOCS 8507270156
Download: ML20129A055 (2)


Text

'

,'o, UNITED STATES

/ o NUCLEAR REGULATORY COMMISSION h a wAssincrow. o. c. 20sss

]ib "s*..../

J18 0 5 1988 Ms. Nancy Butler Smith, Haughey, Rice & Roegge 200 Calder Plaza Building IN RESPONSE REFER Grand Rapids, MI 49503 TO F01A-85-283

Dear Ms. Butler:

This is in reply to your letter of April 16, 1985, in which you requested, pursuant to the Freedom of Information Act (FOIA), copies of Biennial Quality Audits for 1978, 1980, and 1982, and an Independent Design Verification of 1982 for the Midland nuclear power plant.

Our technical staff has informed us that NRC did not require the performance of any biennial quality audits. However, we do have a copy of an evaluation report which Consumers Power Company sent to the NRC, and which was previously placed in the NRC Public Document Room (PDR),1717 H Street, NW, Washington, DC 20555. The enclosed appendix lists this document (Item 3), as well as three other reports in the PDR, evaluations performed by TERA Corp. which may be the independent design verification documents you are seeking.

We are enclosing a notice that explains procedures and charges for obtaining documents from the PDR.

Si ely, M. Felton, Director D vision of Rules and Records Office of Administration

Enclosures:

As stated 8507270156 850605 PDR FOIA BUTLERBS-283 PDR

o Re: F01A-85-283 APPENDIX DATE POR ACCESSION SJBJECT NUMBER

1. 01/04/83 8408150741 Letter from H.A. Levin, TERA, to J.W.

(FOIA Rice Cook, CPC, and to NRC, attaching Midland 84-96) Independent Design and Construction Verification Program--Structural Evaluation of the Diesel Corp..) Generator dated 11/29/82 (45 Building)(TERA pages

2. 02/22/83 8303040015 Memo to Docket file from D. Hood, NRC, attaching copy of TERA Corporation's Project Quality Assurance Plan, Rev. 1, and Engineering Prog. Plan, Rev. 1, for the Independent Design and Construction Verification Program for Midland Plant, dated 2/9/83 (184 pages)
3. 03/02/83 8303300665 Construction Project Evaluation of Consumers Power Company--Midland Energy Center Project--Units 1 and 2--Evaluation Performed by Management Analysis Co.

(Rev. I to 1/31/83 Evaluation) (201 pages)

4. 07/18/84 8407240266 Letter from H.A. Levin, TERA, to J.W. Cook and to NRC, attaching draft report, Midland Independent Design and Construction Veriff-cation Program--Control Room HVAC System Performance Requirements--Midland Independent Design and Construction Verification Program.

(91pages)

-_ -.----- --