Requests Clarification of OL Condition for Electrical & Instrumentation & Control as-built Drawing Program.Revised Paragraph Listed for Possible Incorporation Into License NPF-33
ML20128Q122
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 05/27/1985
From: Agost F
DETROIT EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NE-85-0713, NE-85-713, NUDOCS 8506040094
Download: ML20128Q122 (2)


Text

<

g p'O

D"de"a#

NudearOperanons -

. Fermi-2 Edison"REEN a:n;.

-May 27, 1985 NE-85-0713 FRIORity RoutitlG Mr.. James G.-Keppler og\\

NK Regional' Administrator g

Region III p(ggg U. S.-Nuclear 1 Regulatory Commission

- jg

-799 Roosevelt Road Glen Ellyn,: Illinois 60137

Dear Mr. Keppler:

Reference:

(1)

Fermi 2 NRC Docket No. 50-341 (2)

Fermi 2 Facility Operating License, License No. NPF-33

Subject:

Fermi 2 Facility Operating License Condition for Electrical and'IEC As-built Drawina Proaram The' purpose of this letter is to request the assistance of NRC,-Region III, in acquiring a clarification'to the Fermi 2 Facility Operating License.

Detroit Edison is addressing this request to Region III because'it is related to the Electrical and I&C As-built Program which is under the purview ~of the Region.

The' license, Attachtent 1, paragraph B.3.ar states:

" Correct all remaining drawing deviations (not completed prior ~to fuel load or addressed in

' Item 2.a'above) identified during walkdowns associated with the resolution of 10CFR50.55(e),

Item No. 143, " Deviations of As-built Plant from Design Dor:uments".

Demonstrate'that all design documents; reflect the as-built configuration of the. plant."

To assure this requirement is understood to apply.to the nuclear safety-related electrical and IEC plant configura-tion and that some flexibility'is allowed in the manner of

~

final' engineering disposition of Category C deviations, the

-revised paragraph.below is proposed for incorporation into the. Fermi 2 full power license:

MAY 311985 hDOCk$

/

DR 0

g

I Mr. James G. Keppler May 27, 1985 NE-85-0713 Page 2

" Correct all remaining drawing deviations (not completed prior to fuel load or addressed in Item 2.a above) identified during walkdowns associated with the resolution of 10CFR50.55(e),

Item No. 143, " Deviations of As-built Plant from Design Documents".. Demonstrate that all design documents related to the subject 50.55(e) Item No. 143 are reconciled to the as-built configur-ation of the plant."

The flexibility referred to above for Category C engineering dispositions includes, as an example, the acceptability of the drawing configuration shown below:

Terminal Terminal Strip Strip 1

1 3

3 T

T 3

T T

T Field Drawing Minor. pictorial differences as shown above which are electrically and functionally equivalent, may be acceptable as-is and so documented without requiring a revision to a drawing.

Please direct any questions to Mr. Lewis Bregni at (313)586-5083.