Responds to 940804 Memo & Informs That Plant Coordinating Group Being Reassembled to Expeditiously Review,Analyze & Formulate Position on Adequacy of Responses by Gpc
ML20128Q046
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 08/15/1994
From: Russell W
Office of Nuclear Reactor Regulation
To: Milhoan J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
NUDOCS 9408230110
Download: ML20128Q046 (5)


Text

_ __ _

w atu p

4 UNITED STATES g

j NUCLEAR REGULATORY COMMISSION t

WASHINGTON, D.C. 20086 0001

\\

,o#

August 15, 1994 I

MLANDUMFOR:

James L. Milhoan Deputy Executive Director j

for Nuclear Reactor Regulation l

Regional Operations and Research FROM:

William T. Russell, Director j

Office of Nuclear Reactor Regulation i

SUBJECT:

NRC STAFF ANALYSIS AND POSITION ON GEORGIA POWER 4

COMPANY'S RESPONSE TO ENFORCEMENT ACTION, V0GTLE l

ELECTRIC GENERATING PLANT, UNITS 1 AND 2 Your memorandum of August 4, 1994, requested that the NRC's Vogtle Coordinating Group (Group) be reassembled to expeditiously review, analyze, and formulate a position on the adequacy of responses by Georgia Power Company (GPC) and specific GPC individuals to the NRC's May 9,1994, proposed enforcement action and demands for information. As a separate matter, you requested that 01 review and analyze GPC's response and provide OI's views on whether that response affects any of the conclusions that 01 has previously provided in this case and whether 01 agrees.or disagrees with GPC's statements and characterizations of the facts. You requested that the Group and 01 i

provide an estimate as to when the analyses and recommendations can be completed.

The Vogtle Coordinating Group is being reassembled. Members of the group are listed in the enclosure.

Effective Monday, August 15, 1994, the group will begin their review with the goal of completing the requested analysis and providing recommendations to you by October 31, 1994.

I have also been advised that OI will complete its review no later than October 15, 1994. This schedule for the Group's analysis provides for evaluation of additional evidence, including several transcripts of taped conversations, relied upon by GPC and not included in the Group's previous analysis.

If a meeting is held with GPC, as recommended in GPC's cover letter of July 31, 1994, the schedule assumes that it will be held early in the process to allow consideration of any new or different information provided.

William T. Russell, Director Office of Nuclear Reactor Regulation

Enclosure:

As stated cc w/ enclosure:

J. Taylor, EDO S. Burns, OGC H. Thompson, DEDS L. Chandler, OGC K. Cyr, OGC J. Lieberman, OE S. Ebneter, RII J. Fitzgerald, 01 l

Q p.

Y h

b !

'5 9

l ENCLOSURE 4

4 4

VOGTLE COORDINATING GROUP NAME ORGANIZATION David Matthews (Chair)

NRR Duke Wheeler (Vice Chair)

NRR

~

Darl Hood NRR Pierce Skinner Ril Renee Pedersen OE Legal Advisors

)