Requests 850412 Amend to License DPR-35,increasing k-effective Limit for Spent Fuel Storage Pool for Normal Operation from 0.90 to 0.95 & Any Evaluation Re Amend
ML20128L360
Person / Time
Site: Pilgrim
Issue date: 07/08/1985
From: Doherty J
DOHERTY, J.F.
To: Vassallo D
NRC
References
NUDOCS 8507110330
Download: ML20128L360 (1)


Text

~. ~

July 8,1985 318 Summit Ave. #3 Brighton, Mass. 02135 Mr. Domenic B. Vassallo Chief Reactor Branch No. 2 Division of Licensing U. S. Nuclear Regulatory Commission Washington D. C. 20555 Dear Mr. Vassallo I have recently filed a Petition with regard to a licensing amendment for the Pilgrim Nuclear Power Station, Plymouth, Massachusetts.

The amendment would increase the K-effective limit for the scent fuel storage pool for normal operation for O.90 to 0.95 The Federal Regisber announcement states the request for the amendment was dated Anril 12, 1985 I would aopreciate it very much if you could send me La copy of the amendment request and any evaluation the NRC has done with regard to it. It would be a big helo to me in understanding why the Commission feels this step does not decrease a significant safety limit in the plant, which is its current conclusion.

Thank you very much for your attention to this re-uest..

Sincerely, John F. Doherty 00 $'

i o

~

8507110330 850700 PM ADOCK 05000293 P