Monthly Operating Repts for Jan 1993 for Calvert Cliffs Nuclear Power Plant Units 1 & 2
ML20128K740
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 01/31/1993
From: Cruse C, Shanley L
BALTIMORE GAS & ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9302180286
Download: ML20128K740 (11)


Text

_ _ _ _ _ _ _ _ _ _ _ _

S ALTlMORE GAS AND ELECTRIC CALVERT CLIFFS NUCLEAR POWER PLANT 1650 CALVERT CLIFFS PARKWAY

  • LUSBY, MARYLAND 20657 4702 CHARLES H CRUSE PLANT GENERAL MANAGER CALVERT CLIFFS February 12,1993

~

U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:

Document Control Desk

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2: Docket Nos. 50-317 & 50-318 January 1993 Operatine Data Reports Gentlemen:

The subject reports are being sent to you as required by Technical Specification 6.9.1.6.

Should you have any questions, please contact Mr. Bruce Mrowca at (410) 260-3989.

Very truly yours, l.!

/

y r

a-CHC/LBS/bjd

,, /

Attachments cc:

D. A. Brune, Esquire J. E. Silberg, Es.luire R. A. Capra, NRC D. G. Mcdonald, Jr., NRC T. T. Martin, NRC P. R. Wilson, NRC R. I. McLean, DNR J. H. Walter, PSC R. A. Hartfield, NRC P. Lewis, INPO K. Larson, ANI 4

Ob d

1R 1o' 9302180286 930131 A

PDR ADOCK 0S000317

/f

'R PDR

/

}

Ill

  • o**************************************************************************

UNIT 1 OPERATING DATA REPORT Docket No. 50-317 February 12, 1993 Prepared by Leo Shanley Telephone : (410) 2 60-6744 OPERATING STATUS 1.

UNIT NAME Calvert Cliffs Unit 1 2.

REPORTING PERIOD JANUARY 1993 3.

LICENSED THERMAL POWER (MWT) 2700 4.

NAMEPLATE RATING (GPOSS MWe) 918 5.

DESIGN ELECTRICAL RATING (NET MWe) 845 6.

MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 860 7.

MAXIMUM DEPENDABLE CAP'Y (NET MWe) 825 8.

CHANGE IN CAPACITY RATINGS NONE 9.

POWER LEVEL TO WHICH RESTRICTED N/A

10. REASONS FOR RESTRICTIONS N/A Cumulative This month Year-to-Date to Date
11. HOURS IN REPORTING PERIOD 744 744 155,485
12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 744.0 109,094.0
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 3,019.4
14. HOURS GENERATOR ON LINE 744.0 744.0 106,722.9
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
16. GROSS THERMAL ENERGY GENERATED (MWH) 2,004,526 2,004,526 269,283,377
17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 673,316 673,316 89,500,850
18. NET ELECTRICAL ENERGY GENERATED (MWH) 647,026 647,026 85,116,412
19. UNIT SERVICE FACTOR 100.0 100.0 68.6
20. UNIT AVAILABILITY FACTOR 100.0 100.0 68.6
21. UNIT CAPACITY FACTOR (USING MDC NET) 105.4 105.4 66.4
22. UNIT CAPACITY FACTOR (USING DER NET) 102.9 102.9 64.8
23. UNIT FORCED OUTAGE RATE 0.0 0.0 9.2
24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):

N/A

25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:

N/A

UNIT SIIUTDOWNS AND POWER REDUCTIONS

' ~

DOCKETNO.

50-317 UNTTNAME Calvert Giffs-U1 i

DATE February 12.1993.

-I COMPLETED BY Leo Shan!cy TELEPHONE (4101260 4744 l

REPORT MONTil January 1993 ME1110D OF S!!UT11NG IJCENSEE CAUSE & CORRECITVE DURATION DOWN EVD4T SYS111M COMPONENT ACI10NTO d

CODE 5 PREVDE RECURRENCE NO.

DATE TYPEI (liOURS)

REASON 2 REACTOR 3 REPORT #

CODE

'Ihere were no significant power reductions j

this month.

l I:

4 IEEE Standard 805-1984 3 Method:

1 F: Forced 2 ' Reason:

S: Scheduled..

A-Equipment Failure 1 - Mar B -Maintenance or Test 2 - Mat cas C-Refueling -

3 - Automatic Scram.

5 IEEE Standard 803A-19tG

. D.- Regulatory Restriction -

4-Continued E - Operator Training & License Examination 5 - Reduced Load F-Administrative 9-Other G - Operational Error H - Other

AVERAGE DAILY UNIT POWER LEVEL Docket No. 50-317 Calvert Cliffs Unit No. 1 February 12, 1993 Prepared by Leo Shanley Telephone: (410) 260-6744 JANUARY 1993

                      • c***

Average Daily Power Level Average Daily Power Level Day (MWe-Net)

Day (MWe-Net) 1 870 17 869 2

870 18 869 3

869 19 871 4

869 20 874 5

870 21 874 6

870 22 875 7

867 23 876 8

868 24 876 9

818 25 875 10 868 26 875 11 869 27 875 12 869 28 875 13 868 29 875 14 869 30 874 15 868 31 874 16 869 1

o

9 DOCKET NO.50 317 CALVERT CLIFFS. UNIT 1 February 12,1993 i

SUMMARY

OF OPERATING EXPERIENCE l

JanuafYl'MJ f

TN unit began the month at 100% (870 MWe).

i Power was reduced from 0015 to 2125 on January 9 to clean Main Condenser waterboxes and test Main Turbine valves.

J The unit ended the month at 100% (875 MWe).

4 i

i I

l

l_

{

l i

February 3, 1993 l

REFUELING INFORNATION REQUEST i

e i

4 l

1.

Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No.1.

i 2.

Scheduled date for next refueling shutdown: Narch 5, 1994.

3.

Scheduled date for restart following refueling:

l' None identified at this time, f

4. -

Will refueling or resumption _of operation thereafter require a Technical Specification change or other license amendment?

None identified at this time.

j 5.

Scheduled date(s) for submitting-proposed licensing action and j

supporting information.

b December 1993 for UIC12.

l 6.

Important licensing considerations associated with the refueling.

None identified at this time.

ti.

7.

The number of fuel assemblies (a) in the core and (b). in the spent fuel I

storage pool.

(a) 217.

(b) 1410.

i Spent fuel pools are common to Units 1 and 2.

J 8.

(a) The present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned,:in_ number of fuel assemblics.

1 (a)- 4710. (NOTE 1)

(b) 0.*

i 9.

The projected date.of the last refueling that can be discharged to the i

Spent Fuel Pool assuming the present licensed capacity and maintaining i

space for one full; core off-load.

L i

March 2014*

3 I

  • Eritry changed since last reported.
I NOTE 1
4710 total licensed-site storage capacity.

1 (1830 pool + 2880 Isp31) i

,.-._.a._

o**********=****************************************************************

UNIT 2 OPERATING DATA REPORT Docket No. 50-318 February 12, 1993 Prepared by Leo Shanley Telephone:(410)260-6744 OPERATING STATUS 1.

UNIT NAME Calvert Cliffs Unit 2 2.

REPORTING PERIOD JANUARY 1993 3.

LICENSED THERMAL POWER (MWT) 2700 4.

NAMEPLATE RATING (GROSS MWe) 911 5.

DESIGN ELECTRICAL RATING (NET MWe) 845 6.

MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 860 7.

MAXIMUM DEPENDABLE CAP'Y (NET MWe) 825 8.

CHANGE IN CAPACITY RATINGS NONE 9.

POWER LEVEL TO WHICH RESTRICTED N/A

10. REASONS FOR RESTRICTIONS N/A Cumulative This month Year-to-Date to Date
11. HOURS IN REPORTING PERIOD 744 744 138,840
12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 744.0 100,708.4
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 1,296.6
14. HOURS GENERATOR ON LINE 744,0 744.0 99,325.8
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
16. GROSS THERMAL ENERGY GENERATED (MWH) 1,993,650 1,993,650 253,138,442
17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 664,358 664,358 83,623,136
18. NET ELECTRICAL ENERGY GENERATED (MWH) 637,560 637,560 79,905,989
19. UNIT SERVICE FACTOR 100.0 100.0 71.5
20. UNIT AVAILABILITY FACTOR 100.0 100.0 71.5
21. UNIT CAPACITY FACTOR (USING MDC NET) 103.9 103.9 69.8
22. UNIT CAPACITY FACTOR (USING DER NET) 101.4 101.4 68.1
23. UNIT FORCED OUTAGE RATE 0.0 0.0 5.9
24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):

Refueling, February 19, 1993 for 105 days.

25. IF UNIT IS SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:

N/A l

l

UNIT SIIUTDOWNS AND POWER REDUCTIONS DOCKET NO.50-31R UNITNAME Calvert Cliffs-U2 DATE Februarv12.1 W3.

COMPLETED BY Leo Shanley TELEPHONE (410)26fL6744 REPORT MONTIi Jannary 1993 ME1110D OF I

SIIUTTING LICENSEE CAUSE & CORRECITVE DURNDON DOWN EVLNT SYSTEM COMPONENT ACDONTO (IIOURS)

REASON 2 REACIOR3 REPORT #

CODE 4 CODES PREVENT RECURRENCE N O.

DNIE TYPEI There were no significant power reductions this month.

1 1 F: Forced 2 Rea+on:

3 Method:

4 IEEE Standard 805-1984 S: Scheduled A-Equipment Failure 1 - Manual B-Maintenance or Test 2 - Manual Scram.

C-Refueling 3 - Automatic Scram.

5 IEEE Standard 803A-1981 D-Regulatory Restriction 4 - Continued E - Operator Training & License Examination.

5 - Reduced lead F-Administrative 9 - Other G Operational Error H - Other s_

4 AVERAGE DAILY UNIT POWER LEVEL co*********************************************ww***********************

Docket No. 50-318 Calvert Cliffs Unit No. 2 February 12, 1993 Prepared by Leo Shanley Telephone: (410) 260-6744 JANUARY 1993

                            • e i

Average Daily Power Level Average Daily Power Level Day (MWe-Net)

Day (MWe-Net) 1 861 17 852 2

860 18 860 3

860 19 861 4

860 20 860 5

861 21 860 6

860 22 860 7

860 23 861 8

860 24 860 9

858 25 860 4.

10 859 26 860 11 860 27 860 12 860 28 860 13 860 29 861

~14 860 30 860 15 859 31 859 16 773 J

4 l

-e

=

d 4

DOCKET NO. 50 318 CALVERTCLIFFS UNIT 2 February 12,1993

SUMMARY

OF OPERAT1NG EXPERIENCE January 19J9 j

The unit began the month at 100% (860 MWe).

Power was reduced to less than 90% at 0300 on January 16 to clean Main Condenser waterboxes and test Main Turbine valves. The unit was returned to 100% (860 MWe) at 0415 on January 17.

j The unit ended the month at 100% (860 MWe),

d 4

a e

c 0

n i

February 5, 1993 BIEELING INFORMATION RIQUEST 1.

Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No. 2 2.

Scheduled date for next refueling shutdown:

February 19, 1993.

3.

Scheduled date for restart following refueling:

June 4, 1993.-

4.

Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?.

4 No.

5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

None required.

6.

Important licensing considerations associated with the refueling.

None identified at this time.

7.

The number of fuel assemblies-(a) in' the core and (b) in the spent fuel storage pool.

(a) 217.

-(b) 1410.

Spent fuel pools are connon to Units 1 and 't.

8.

(a)-The present licensed spent fuel pool storage capacity, and (b,) the size of any increase-in licensed storage capacity that has been requested or is planned, in number of fuel assemblies.

(a) 4710-(NOTE.1)-

(b) 0*

9.-

The projected date of the last refueling that can be-discharged to-the Spent Fuel Pool assuming the present licensed capacity and maintaining space for one full core off load.

March 2016.*

  • Entry has changed since last reported.

NOTE 1: 4710 total licensed site storage capacity.-

(1830. pool + 2880 IspSI)