Notifies That Control Air Sys Drawings for Unit 3 Discussed in Re Insp Rept 84-15 Issued on 850619.Drawings for Units 1 & 2 Will Be Issued Before Restart
ML20128G228
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 06/21/1985
From: Domer J
TENNESSEE VALLEY AUTHORITY
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20128G213 List:
References
NUDOCS 8507090111
Download: ML20128G228 (1)


Text

.

e TENNESSEE VALLEY AUTHORITY CH ATTANOOGA, TENNESSEE 374o1 400 Chestnut Street Tower II June 21, 1985 U.S. Nuclear Regulatory Commission Region II ATTN: Dr. J. Nelson Grace, Regional Administrator 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323

Dear Dr. Grace:

Please refer to my letter to you dated May 29, 1985, regarding Inspection Report 84-15 for our Browns Ferry Nuclear Plant. In that letter we indicated "as-constructed" control air system drawings for unit 3 would be issued by June 1, 1985. However, it has taken longer than we anticipated to complete these drawings. They were issued June 19, 1985 for unit 3 and will be issued before restart for units 1 and 2. This was discussed between Floyd Cantrell of your staff and myself on May 31, 1985.

If you have any questions, please get in touch with R. E. Alsup at FTS 858-2725.

To the best of my knowledge, I declare the statements contained herein are complete and true.

Very truly yours, TENNESSEE VALLEY AUTHORITY BY!llt

  • J. A. Domer, Chief Nuclear Licensing Branch cc: Mr. James Taylor, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20555 l

l t

1 0507090111 850620 1 PDR ADOCK 05000259 l G PDR l