Forwards Safety Evaluation Granting Util 920824 Request for Authorization to Use Portion of Section XI of 1986 Edition of ASME Code Re Visual Exams VT-3 & VT-4 to Be Combined Into Single VT-3
ML20128E277
Person / Time
Site: Millstone, Haddam Neck  File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 02/04/1993
From: Stolz J
Office of Nuclear Reactor Regulation
To: Opeka J
CONNECTICUT YANKEE ATOMIC POWER CO.
Shared Package
ML20128E280 List:
References
TAC-M84392, TAC-M84393, TAC-M84394, NUDOCS 9302100368
Download: ML20128E277 (3)


Text

. _ _ - _ _ _ _ _ - _ _ _ _ - _ _

e February 4, 1993 Docket Hos. 50-243, 50-336 Dist ribu11pm and 50-423 Docket . file: J. Strosnider-  !

NRC & Local PDRs TMcLellan i Hr. John F. Opeka PD l-4 Plant AWang l Executive Vice President, Nuclear SVarga VRooney  ;

Connecticut Yankee Atomic Power Company JCalvo Northeast Nuclear Energy Company SNorris l Post Office Box 270 G5Vissing i Hartford, Connecticut 06141-0270 OGC  !

Dear Mr. Opeka:

ACRS LTDoerfle(10)in, RI  ;

SUBJECT:

HADDAM NECK PLANT AND HILLSTONE NUCLEAR POWER STATION, UNITS 2 AND 3 ,

REQUEST TO APPLY A PORTION OF SECTION XI 0F THE 1986 ASME CODE EDITION (TAC NOS. M84392, M84393 AND M84394)

By a letter dated August 24, 1992, Connecticut Yankee Atomic Power Company '

(CYAPCO) and Northeast Nuclear Energy Company (NNECO) submitted to the NRC a request for authorization to use a portion of Section XI of the 1986 Edition '

of the ASME Code pertaining to visual examinations for the Haddam Neck Plant and Hillstone Nuclear Power Station, Units 2 and 3. You requested, as an i

-alternative, to allow visual examinations VT-3 and VT-4 to be combined into a single VT-3 as the 1986 Code permits.

We have reviewed and evaluated the request and supporting information. Based on the information submitted and pursuant to 10 CFR 50.55a(g)(4)(iv), we  :'

hereby grant approval to use the 1986 Edition of the ASME Code Article IWA-2213, '".)sual Examination VT-3" as a subsequent Edition of the ASME Code, i

provided that all related requirements of the respective editions or addenda are met.

Sincerely, Original signed by John F. Stolz, Director Project Directorate 1-4 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation

Enclosure:

Safety Evaluation cc w/ enclosure:

See next~page 9302100368 930204 PDR ADOCK 05000213l P PDR OFFICE- LA:PDI PM: PD_l-4_ D:N4 OGCJ WE SNYrY GS k d g:cn JStolb /dbx,  :;

DME. l171/93 2 / /93- t /3 /93 i- / / )93 /- / y 0FFICIAL RECORD COPY - J' Document Name: G:\VISSING\M84392 ,

,, ~ ^

  • l ,

Mr. John F. Opeka Haddam Neck Plant & Millstone Nuclear Northeast Nuclear Energy Company Fower Station, Unit Nos. 2 & 3 CC:

Gerald Garfield, Esquire R. M. Kacich, Director Day, Berry and Howard Nuclear Licensing Counselors at Law Northeast Utilities Service Company City Place Post Office Box 270 Hartford, Connecticut 06103-3499 Hartford, Connecticut 06141-0270 W. D. Romberg, Vice President D. O. Nordquist.

Nuclear, Operations Services Director of Quality Lervices Northeast Utilities Service Company Northeast Utilities Service Company Post Office Box 270 Post Office Box 270 Hartford, Connecticut 06141-0270 Hartford, Connecticut. 06141-0270 Kevin McCarthy, Director Regional Administrator Radiation Control Unit Region 1 Department of Environmental Protection U.S. Nuclear Regulatnry Commission State Office Building 475 Allendale Road Hartford, Connecticut 06106 King of Prussia, Pennsylvania 19406 Allan Johanson, Assistant Director First Selectmen Office of Policy and Management Town of Waterford Policy Development & Planning Division Hall of Records 80 Washington Street 200 Boston Post Rohd Hartford, Connecticut 06106 Waterford, Connecticut 06385 S. E. Scace, Nuclear Station Director P. D. Swetland, Resident inspector Millstone Nuclear Power Station Millstone Nuclear Power Station Northeast Nuclear Energy Company c/o U.S. Nuclear Regulatory Commission Post Office Box 128 Posi Office Box 513 Waterford, Connecticut 063M Niantic, Connecticut 06357 C. H. Clement, Nuclear Unit Director M. R. Scully, Executive Director Millstone Unit No. 3 Connecticut Municipal Electric Northeast Nuclear Energy Company Energy Cooperative Post Office Box 128 30 Stott Avenue Waterford, Connecticut 06385 Norwich, Connecticut 00360 Burlington Electric Department David W. Graham c/o Robert E. Fletcher, Esq. Fuel Supply Planning Manager 271 South Union Street Massachusetts Municipal Wholesale Burlington, Vermont 05402 Electric Company Post Office Box 426 Ludlow, Massachusetts 01056 1

i i

2-  ;

)

Mr. John F. Opeka Haddam Neck Plant & Hillstone Nuclear Northeast Nuclear Energy Company Power Station, Unit Nos. 2 & 3 cc:

l Charles Brinkman, Manager Board of Selectmen i Washington Nuclear Operations Town Office Building i ABB Combustion Engineering Haddam, Connecticut 06438 Nuclear Power 12300 Twinbrook Pkwy., Suite 330 Resident Inspector Rockville, Maryland 20852 Haddam Neck Plant l c/o U.S. Nuclear Regulatory Commission J. P. Stetz, Nuclear Station Director 361 Injun Hollow Road Haddam Neck Plant East Hampton, Connecticut 06424-3099 Connecticut Yankee Atomic Power Company 362 Injun Hollow Road Nicholas S. Reynolds East Hampton, Connecticut 06424-3099 Winston & Strawn 1400 L Street, NW G. H. vouchard, Nuclear Unit Director Washington, DC 20005-3502 '

Haddam Neck Plant Connecticut Yankee Atomic Power Company 362 Injun Hollow Road East Hampton, Connecticut 06424-3099

+

- m.,. ,, -4 -- .-