Forwards Evaluation of 850225 Revised Emergency Plan.Plan Meets Requirements of 10CFR50 App E,Reg Guide 2.6 & ANSI/ANS-15.16-1982 & Acceptable.Implementation Should Begin Immediately W/Full Implementation within 120 Days
ML20128B494
Person / Time
Site: Idaho State University
Issue date: 05/21/1985
From: Thomas C
Office of Nuclear Reactor Regulation
To: Kegel C
IDAHO STATE UNIV., POCATELLO, ID
Shared Package
ML20128B499 List:
References
RTR-REGGD-02.006, RTR-REGGD-2.006 NUDOCS 8505240552
Download: ML20128B494 (3)


Text

. - . _ .

May 21,1985 Docket No. 50-284 Dr. Charles H. Kegel

-Academic Vice President Idaho State University -

Pocatello, Idaho 83201

Dear Dr. Kegel:

SUBJECT:

ACCEPTANCE OF EMERGENCY PLAN The staff of the U. S. Nuclear Regulatory Commission (NRC) has completed its review and evaluation of the revised emergency plan for the Idaho 25, 1985 State University in compliance reactor with 10 CFRfacility)that 50.54(q andyou(r).submitted

. The planon was February reviewed against the requirement: of Appendix E to 10 CFR Part 50, the guidance criteria set forth in Revision 1 to Regulatory Guide 2.6 and ANSI /ANS-15.16-1982, " Emergency Planning for Research Reactors."

Based on its review, and as discussed in the enclosed evaluation, the staff concludes that the emergency plan for the Idaho State University reactor facility meets both the requirements of the regulations and the guidelines provided to you and is, therefore, acceptable. We request that you begin to implement your approved emergency plan immediately, with full implementation to be accomplished within 120 days of the date of this letter. Furthermore, you are requested to inform us by letter of the date on which complete implementation is achieved.

If you have any questions, please contact Angela Chu our Project Manager for your facility, at (301) 492-9798.

Sincerely Original signed by Cecil 0. Thomas, Chief Standardization and Special Projects Branch Division of Licensing, NRR As stated cc: See next page DISTRIBUTION

<5ecket: m e @ Region IV SSPB Reading PAnderson 8505240552 850521 AChu PDR ADOCK 05000284 HBerkow F PDR CThomas DMatthews, I&E e :tm w 05/Al/85 05G /85 05/:% /85 05g//85

p nn v #p -

UNITED STATES

-5

'g'. o I

NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 2f,555 j

% /y May 21, 1985 I

Docket No. 50-284 i Dr. Charles H. Kegel Academic Vice. President  :

Idaho State University j Pocatello, Idaho 83201 j

Dear Dr. Kegel:

SUBJECT:

ACCEPTANCE OF EMERGENCY PLAN The staff of the U. S. Nuclear Regulatory Commission (NRC) has completed its review and evaluation of the revised emergency plan for the Idaho 25, 1985 State University in compliance withreactor 10 CFRfacility)that 50.54(q and youfr).submitted The plan on wasFebruary reviewed against the requirements of Appendix E to 10 CFR Part 50, the guidance  !

criteria set forth in Revision 1 to Regulatory Guide 2.6 and ANSI /ANS-15.16-1982, " Emergency Planning for Research Reactors."

Based on its review, and as discussed in the enclosed evaluation, the staff concludes that the emergency plan for the Idaho State University reactor facility meets both the requirements of the regulations and the guidelines provided to you and is, therefore, acceptable. We request that you begin to implement your approved emergency plan immediately, with full implementation to be accomplished within 120 days of the date of this letter. Furthermore, you are requested to inform us by letter of the date on which complete implementation is achieved.

If you have any questions, please contact Angela Chu our Project Manager for your facility, at (301) 492-9798.  ;

Sincerely NA0 W ::wM Cecil 0. Thomas, Chief l Standardization and Special Projects Branch Division of Licensing, NRR (

Enclosure:

As stated cc: See next page

, [

i i

Idaho State University 50-284 Attorney General-

~

State House Rofse, Idaho. 83720

. State Plannino and Comunity '

Affairs Agency

. State of Idaho Boise, Idaho -83720 t

t

'8 .

c

, . i f

l I

C I