Forwards SE Accepting 920921 Response to Suppl 1 to GL 87-02 Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-46.
Date released: 05/21/2020 Download: ML20128A652


Safety Evaluation Accepting Licensee 920921 120-day Response to Suppl 1 to GL 87-02 Re in-structure Response Spectra
ML20128A730
Person / Time
Site: Prairie Island Xcel Energy icon.png
Issue date: 11/30/1992
From:
Office of Nuclear Reactor Regulation
To:
References
Download: ML20128A730 (2)
Safety Evaluation Accepting Licensee 920921 120-day Response to Suppl 1 to GL 87-02 as Commitment to Entire GIP-2, Including Both SQUG Commitments & Implementation Guidance. In-structure Response Spectra Addressed in Separate SE
ML20128A717
Person / Time
Site: Prairie Island Xcel Energy icon.png
Issue date: 11/30/1992
From:
Office of Nuclear Reactor Regulation
To:
References
Download: ML20128A717 (3)
Forwards SE Accepting 920921 Response to Suppl 1 to GL 87-02 Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Usi A-46.
ML20128A650
Person / Time
Site: Prairie Island Xcel Energy icon.png
Issue date: 11/30/1992
From: Gamberoni M
Office of Nuclear Reactor Regulation
To: PARKER T M
NORTHERN STATES POWER CO.
References
REF-GTECI-A-46, REF-GTECI-SC, TASK-A-46, TASK-OR
Download: ML20128A650 (3)