ML20128A012

From kanterella
Jump to navigation Jump to search
Forwards Perry Nuclear Power Plant Max Extended Operating Domain Analysis for NRC Approval.Fsar Will Be Revised to Include Mods to Plant Initial Test Program Upon Approval of Analysis.Analysis Will Be Included in Future FSAR Amend
ML20128A012
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 06/27/1985
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: Youngblood B
Office of Nuclear Reactor Regulation
Shared Package
ML20128A015 List:
References
NUDOCS 8507020542
Download: ML20128A012 (1)


Text

e 57 1-l

i<
~ c,l

~

c o

2.

8 e

c.

,i; P.O Box 5000 - CLEVELAND. OHlO 44101 - TELEPHONE (216) 622-9800 - lLLUMINATING BLDo. - 55 PUBLIC SQUARE Semng The Best Location in the Nation MURRAY R. EDELMAN VICE PRESIDENT NUCLE A R June 27, 1985 PY-CEI/NRR-0268 L lir. B. J. Youngblood, Chief Licensing Branch No. 1 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Startup Testing in the Maximum Extended Operating Domain (MEOD)

Dear Mr. Youngblood:

In order to take full advantage of the Perry Startup Test Program, we plan to perform tests in expanded areas of the power / flow operating map currently included in our FSAR. The expanded areas and the original map together are commonly referred to as the Maximum Extended Operating Domain (ME0D).

To justif y that it is safe to perform tests in the MEOD, we have completed a safety evaluation with analysis consistent with those in the FSAR. When the analysis has been approved by the staff, the FSAR will be revised to include modifications to the Initial Test Program. The analysis will be included in the FSAR in a future amendment.

If you have any questions, please call me.

Very truly yours, 6

Murray Edelman Vice President Nuclear Group MRE:njc cc: Jay Silberg, Esq.

John Stefano (2)

J. Grobe i

i\\

g7020542850627 A