Forwards Change to QA Program Description for PSAR Section 17.Changes Do Not Reduce Commitments in Previous Program Description
ML20127L792
Person / Time
Site: Beaver Valley
Issue date: 06/04/1985
From: Carey J
DUQUESNE LIGHT CO.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
2NRC-5-085, 2NRC-5-85, NUDOCS 8506280137
Download: ML20127L792 (3)


Text

'

se cd L/H/W e

s

%s 2NRC-5-085 N $ o!s'- seo Nuclear Construction Division Telecopy (412) 787-2629 Robinson Plaza, Building 2. Suite 210 Pittsburgh, PA 15205 Jttne 4,1985 United States Nuclear Regulatory Commission Region 1 631 Park Avenue King of Prussia, PA 19406 ATTENTION:

Mr. Richard W. Starostecki Division of Project and Resident Programs

SUBJECT:

Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 10CFR50.55(f) PSAR QA Programs Gentlemen:

Please find attached the change made to the Quality Assurance Program description (Section 17, BVPS-2 PSAR).

In accordance with 10CFR50.55( f),

these changes have been evaluated and do not reduce the commitments in the program description previously accepted by the NRC.

DUQUESNE LIGHT COMPANY lbd By

/

J.

arey Vice resident JS/wjs Attachment ec:

Mr. B. K. Singh, Project Manager (w/a)

Mr. G. Walton, NRC Resident Inspector (w/a)

INPO Records Center (w/a)

NRC Document Control Desk (w/a) o) h JBg62gggj8%g2 Q

'\\

A L

r, DUQUESNE LIGHT CCMPANY f

NUCLEAR GROUP Quality Assurance Unit Evaluation - 10CFR50.55(f)

Subject:

BVPS-2 PSAR, Section 17 s

1.1 Pages Affer.ted by the Change 17.1-5, 17.1-7, 17.1-9, 17.1-10, 17.1-11 1.2 Identification of the Change The Vice President - Nuclear Group has assumed total responsibility for the Beaver Valley No.

2 Unit.

This responsibility includes the supervision and control of Stone and Webster and all other contractors and consultants, as well as all phases of the start-up operations.

11e responsibilities of the positions of Vice President - Nuclear Construction and Vice President General Services have been reassigned.

The newly created position entitled Vice President of Special Nuclear Projects will report directly to the Vice President Nuclear Group.

Figure 17.1-1A, attached, has been revised to reflect the current titles and reporting assignments.

1.3 Reason for the Change t

Engineering and construction work of Beaver Valley Unit No. 2 is nearing completion, and there is increasing activity in the area of turnover of plant systems and subsystems from construction to operations.

l l

1.4 Basis for concluding that the revised program incorporating this change l

continues to satisfy the criteria of 10CFR50, Appendix B and the Safety j

Analysis Report Quality Assurance Program description commitments previously accepted by the NRC.

The administrative changes made still provide for the organizational freedom necessary for the QA Program to operate in accordance with the l

requirements of 10CFR50, Appendix B.

Prepared By:

d h.

Date:

5-N - BS Approved By:

./bi wh Date:

h/ 4 TT L

v.

Chairman of the Board and President i

t Executive Vice President I

l Power Supply Administrative Nuclear Group Group Vice President Services Group i

j Vice President Vice President Vice President of i

Special Nuclear Projects

?

I I

I I

I I

Nuclecr Engineering Nuclear Operations Nuclear Services Quality Assurance General Services Materials and C::nstruction General Manager General Manager Manager General Manager Management General Manaaer Manager 1

I i

Legend Lines of Responsibility Figure 17.1-1A

.Duquesne Light Company I

Lines of Comunication Organization for Quality Assurance Beaver Valley Power Station - Unit 2

---~~~~~~-

Preliminary Safety Analysis Report