Responds to IE Bulletin 75-04.Cable Spreading Room Penetrations Added to list.Non-flammable Covering Applied to Penetrations
ML20127J400
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 04/23/1975
From: Wachter L
NORTHERN STATES POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20127J404 List:
References
IEB-75-04, IEB-75-4, NUDOCS 9211190328
Download: ML20127J400 (1)


Text

.

s NSRm NORTHERN 8TATES POWEM COMPANY MIN N E A PO LI S, MIN N K eOTA 5 540t April 23,1975 Mr. J. G. Keppler Director - Region 111 Office of Inspection and Enforcement United States Nucicar Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Keppler:

MONTICELLO NUCLEAR GENERATING PLANT Docket No. 50-263 License No. DPR-22 The reviews and evaluation requested in items 1 through 3 of IE Bulletin 75-04 have been completed for the Monticello Nuclear Generating Plant.

In accordance with item 4 of the Bulletin, the results of these reviews and evaluation are hereby submitted.

Existing Administrative Directives governing installation and test procedures require identification of unusual mechanical, cicetrical, chemical, thermal, or other hazards associated with equipment and its environs.

Instructions and precautions necessary to control these hazards are required to be included fu the procedures. Existing Directives and instructions governing work authorizations require a second IcVel of review by technical and operating personnel prior to commencing work related to equipment, instruments, and systems which are designated on a " critical" list. Cabic spreading room penetrations have been added to this list.

Design of the floor and wall penetrations in the cabic spreading room requires the penetrations be covered with a non-flammable material.

Inveatigation revealed that penetrations which were scaled or rescaled subsequent to completion of original construction were scaled with a flame retardent material. A non-flammabic covering has been applied to these penetrations.

A task force has been designated to review the areas identified in IE Bulletin 7 5-04 A. Their review is expected to be completed by June 30, 1975.

Yours very truly,

$.tol&

L. f. Wachter Vice President - Power Production and System Operation ec: