Forwards Amend 60 to License DPR-21 & Safety Evaluation. Amend Provides Alternative to Currently Required Increase in App J,Type a Test Frequency Incurred After Failure of Two Successive Individual Leak Rate Tests
ML20127E372
Person / Time
Site: Millstone Dominion icon.png
Issue date: 01/11/1993
From: Andersen J
Office of Nuclear Reactor Regulation
To: Opeka J
CONNECTICUT YANKEE ATOMIC POWER CO., NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML20127E376 List:
References
TAC-M84727, NUDOCS 9301190270
Download: ML20127E372 (2)


Text

. . . . . .

,s ,-

January 11,-1993 Docket No. 50-245 DistributinDi- ~

- l

Docket' file Wanda Jones NRC & Local PDRs CGrimes Mr. John F. Opeka _

PD I-4 Plant JPulsipher Executive Vice President, Nuclear SVarga ACRS (10)

Connecticut Yankee Atomic Power Company JCalvo OPA

-Northeast Nuclear Energy Company SNorris OC/LFDCB-Post Office Box 270 JAndersen LTDoerflein, . RI Hartford, Connecticut 06141-0270 OGC ,

DHagan 1

Dear Mr. Opeka:

GHill (4)

SUBJECT:

ISSUANCE OF AMENDMENT (TAC NO. M84727)

The Commission has issued the enclosed Amendment No. 60 to Facility Operating I License No. DPR-21 for Millstone Nuclear Power Station, Unit 1, in response to I your application dated September 29, 1992, as supplemented November 6, 1992. 1 The amendment to Technical Specification (TS) Requirement 4.7.A.3.a.2 provides-an alternative to the currently required increase in Appendix J, Type A test frequency incurred after the failure of two successive Individual Leak Rate Tests. This only applies to the current condition of two consecutive Type A test failures (cycle 11 and cycle 13 refueling outages) vice a permanent change to the TS Surveillance Requirements. This TS change, along with Northeast Nuclear Energy Company's (NNECO's) exemption request dated November 4, 1992, will allow NNEC0 to return to the normal test schedule of three tests in 10-years. NNECO's exemption request was approved by Exemption _ dated January 11 , 1993. NNEC0's September 29, 1992, submittal also included a--

Bases change to'4.7.A.

A copy of the related Safety Evaluation is also enclosed'. The notice _of, issuance will be included in the Commission's biweekly Federal Reaister notice.

Sincerely, Original signed by James W. Andersen,-Acting Project. Manager

. Project Directorate I-4 9301190270 930111 -

Division of Reactor Projects - I/II DR ADOCK 0500 5 Office of Nuclear Reactor Regulation-p

Enclosures:

1. Amendment No. 60. to DPR-21 _.

.s

2. Safety Evaluation - {g ,

g;4 cc w/ enclosures: 140053 See next page ,,f OFFICE LA:PDI-4 PM:PDI-4 / DfPDI-4 OGC M WE ShN' JAndersenh JStol b EMo664 DATE M $ /92 FL /30/92 ~ /2 /30/92 / / v /f3 -/ /

OFFICIAL RECORD COPY Document Name: G:\ANDERSEN\84727.AMD

/

.I i

Mr. John F. Opeka Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit I cc:

Gerald Garfield, Esquire R. H. Katich, Director Day, Berry and Howard Nuclear Licensing Counselors at Law Northeast Utilities Service Company City Place Post Office Box 270 Hartford, Connecticut 06103-3499 Hartford, Connecticut 06141-0270 W. D. Romberg, Vice President D. O. Nordquist Nuclear, Operations Services Director of Quality Services Northeast Utilities Service Company Northeast Utilities Service Company Post Office Box 270 Post Office Box 270 Hartford, Connecticut 06141-0270 Hartford, Connecticut 06141-0270 2

Kevin McCarthy, Director Regional Administrator Radiation Control Unit Region I Department of Environmental Protection U.S. Nuclear Regulatory Commission State Office Building 475 Allendale Road Hartford, Connecticut 06106 King of Prussia, Pennsylvania 19406 Allan Johanson, Assistant Director First Selectmen Office of Policy and Management Town of Waterford Policy Development and Planning Division Hall of Records 80 Washington Street 200 Boston Post Road Hartford, Connecticut 06106 Waterford, Connecticut 06385 S. E. Scace, Nuclear Station Director P. D. Swetland, Resident Inspector Millstone Nuclear Power Station Millstone Nuclear Power Station Northeast Nuclear Energy Company c/o U.S. Nuclear Regulatory Commission Post Office Box 128 Post Office Box 513 Waterford, Connecticut 06385 Niantic, Connecticut 06357 -

H. F. Haynes, Nuclear Unit Director Millstone Unit No. 1 Northeast Nuclear Energy Company Post Office Box 128 Waterford, Connecticut 06385 Nicholas S. Reynolds Winston & Strawn 1400 L Street, NW Washington, DC 20005-3502