January 8, 1993 Docket Hos. 50-313 and 50-368 Mr. Jerry W. Yelverton Vice President, Operations ANO Entergy Operations, Inc.
Route 3 Box 137G Russellville, Arkansas 72801
Dear Mr. Yelverton:
SUBJECT:
POST-ACCIDENT MEASUREMENT Of pil AT ARKANSAS NUCLEAR ONE, UNilS 1 AND 2 (TAC N05. M82201 AND M82202)
By "0CAN119101, Clarifies Ph Sampling Method & Chloride Grab Samples,As Suppl to Util .Util Currently Has Agreement W/B&W to Provide Offsite Analysis of Chloride & Ph [[Topic" contains a listed "[" character as part of the property label and has therefore been classified as invalid.s. Analyses Meet Reg Guide 1.97 & NUREG-0737,Item II.B.3|letter dated November 15, 1991]], Entergy Operations, Inc. (the licensee),
described their methodology for pH measurement in the post-accident grab sampics for Arkansas Nuclear One, Units 1 and 2.
In a arevious letter dated September 7, 1984, the licensee informed the NRC that tie measurement of pil in the post-accident grab samples will be performed offsite, llowever, no specific details were provided at that time, in the November 15, 1991, submittal, the licensee stated that Babcock and Wilcox will perform analyses of the post-accident grab samples and measure their pit.
The pH will be measured with a pli probe to an accuracy of 10.3 pil units for values in the range of 5 to 9, and 10.5 units for all other pil values.
The range over which measurements will be made is from pil 1 to 13.
We have reviewed the licensee's submittal and find that the methodology for pil measurement as proposed by the licensee meets the requirements specified in Regulatory Guide 1.97, Table 3. and the guidelines clarifying the post-accident sampling criteria, d scribed in NUREG-0737, item II.B.3.
We conclude, therefore, that the methodology is acceptable.
Sincerely, ORIGINAL S;GNED BY:
Roby B. Bevan, Project Manager Project Directorate IV-1 Division of Reactor Projects - lil/lV/V Office of Nuclear Reactor Regulation ORIGINAL SIGNED BY:
U Thomas W. Alexion, Project Manager Project Directorate IV $ b bon $O00013 Division of Reactor Projects - lil/lV/V P
PDR Office of Nuclear Reactor Regulation cc: See next page D111R11W1103:
1P*00'&LocalPDRs o
NRG PD4-1 Reading Docket File:
R. Bevan H. Virgilio J. Larkins P. Noonan PD4-1 Plant file
- 1. Alexion A.JA Beach 0GC ACRS (10) (P-315)
OfC-LA:PD40[h(
PMJQ4911 PM:PD4Nfki- 0:PD4*lk
)
'BeknYp' NAME PNoonan*
R k
TAlexion
!JLarkins DATE
/0/3//92
\\h/M/92 l / /hk f
/k /k I
(J j
OFFICIAL RECORD COPY Document Name: AR82201.1tr
l l
E[ge&s et og\\'o,
+
UNITED ST ATES r, yf,.r, NUCLE AR REGULATORY COMMISSION g
t W ASHINGTON, D. C, 205bb
\\'
,/
January 8, 1993 Doc *k*e*t Hos. 50-313 and 50-368 Mr. Jerry W. Yelverton Vice President, Operations AND Entergy Operations, Inc.
Route 3 Box 137G Russellville, Arkansas 72801 Dear Mr. Yelverton;
SUBJECT:
POST-ACCIDENT HEASUREMENT OF pH AT ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 (TAC NOS. H82201 AND M82202)
By "0CAN119101, Clarifies Ph Sampling Method & Chloride Grab Samples,As Suppl to Util .Util Currently Has Agreement W/B&W to Provide Offsite Analysis of Chloride & Ph [[Topic" contains a listed "[" character as part of the property label and has therefore been classified as invalid.s. Analyses Meet Reg Guide 1.97 & NUREG-0737,Item II.B.3|letter dated November 15, 1991]], Entergy Operations, Inc. (the licensee),
described their methodology for pH measurement in the post-accident grab samples for Arkansas Nuclear One, Units 1 and 2.
In a previous letter dated September 7,1984, the licensee informed the NRC that the measurement of pH in the post-accident grab samples will be performed offsite.
However, no specific details were provided at that time, in the November 15, 1991, submittal, the licensee stated that Rabcock and Wilcox will perform analyses of the post-accident grab samples and measure their pH.
lhe pH will be measured with a pH probe to an accuracy of 10.3 pH units for values in the range of 5 to 9, and 10.5 units for all other pH values. The range over which measurements will be made is from pH 1 to 13.
We have reviewed the licensee's submittal and find that the methodology for pH measurement as proposed by the licensee meets the requirements specified in Regulatory Guide 1.97, Table 3, and the guidelines clarifying the post-accident sampling criteria, described in NUREG-0737, item II.B.3.
W.e conclude, therefore, that the methodology is acceptable.
Sincerely,
/
ear Roby Bevan, Project Manager Project Directorate IV-1 Division of Reactor Projects - Ill/lV/V Office of Nucle r Reactor Regulation
})RS W
Thomas W. Alexion, Proj ct Manager Project Directorate IV-1 Division of Reactor Projects - Ill/IV/V Office of Nuclear Reactor Regulation cc:
See next page l
A Mr. Jerry W. Yelverton Entergy Operations, Inc.
Arkansas Nuclear One, Units 1 & 2 cc:
Mr. Donald C. Hintz, President Mr. John R. McGaha and Chief Operating Officer Vice President, Operations Support Entergy Operations, Inc.
Entergy Operations, Inc.
P. 0. Box 31995 P. O. Box 31995 Jackson, Mississippi 39286 Jackson, Mississippi 39286 Mr. Robert B. McGehee Mr. R. A. fenech Wise, Carter, Child & Caraway General Manager, Plant Operations P. O. Box 651 Entergy Operations, Inc.
Jackson, Mississippi 39205 Route 3 Box 137G Russellville, Arkansas 72801 Mr. Charles B. Brinkman, Manager Washington Nuclear Operations Mr. Nicholas S. Reynolds ABB Combustion Engineering Nuclear Power Winston & Strawn 12300 Twinbrook Parkway, Suite 330 1400 L Street, N.W.
Rockville, Maryland 20852 Washington, D.C.
20005-3502 Mr. James J. Fisicaro Mr. Robert B. Borsum Director, Licensing Licensing Representative Entergy Operations, Inc.
B&W Nuclear Technologies Route 3, Box 137G 1700 Rockville Pike, Suite 525 Russellville, Arkansas 72801 Rockville, Maryland 20852 Admiral Kinnaird R. McKee, USN (Ret)
Senior Resident Inspector 214 South Morris Street U.S. Nuclear Regulatory Commission Oxford, Maryland 21654 1 Nuclear Plant Road Russellville, Arkansas 72801 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 Honorable Joe W. Phillips County Judge of Pope County Pope County Courthouse Russellville, Arkansas 72801 Ms. Greta Dicus, Director Division of Radiation Control and Emergency Management Arkansas Department of Health 4815 West Markham Street Little Rock, Arkansas 72205-3867
,.,.,..-