Forwards Insp Rept 50-346/92-17 on 921027-1215.Violations Noted,But Not Cited
ML20127A597
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 12/31/1992
From: Lanksbury R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Shelton D
CENTERIOR ENERGY, TOLEDO EDISON CO.
Shared Package
ML20127A601 List:
References
NUDOCS 9301120013
Download: ML20127A597 (2)


See also: IR 05000346/1992017

Text

__ - _ _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

, y- GCb

p og um n o s w ts

4 , h, NUCLEAH HIGUL ATORY cOMMisslON

. ; Q, REGloN lli

'  ;.  :- j res noostvtu aomo

% g cow tt us. nuwoes sour

%...../

DEC 311992

Docket lio. 50-346

Centerior Service Company

A1Til: Mr. Donald Shelton

Vice President

Nuclear - Davis-Besse

c/o Toledo Edison Company

300 Madison Avenue

Toledo, OH 43652 --

Dear Mr. Shelton:

This refers to the inspection conducted by Messrs. S. Stasek and R. K. Walton

of this office on October 27 through DecemLer 15, 1992. The inspection

included a review of authorized activities for your Davis-Besse Nuclear Power

Station. At the conclusion of the inspection, the findings were discussed

with those members of your staff identified in the enclosed report.

Areas examined during the inspection are identified in the report. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observation of

activities in progress.

During this inspection, certain of your activities appeared to be in violation

of NRC requirements. However, as described in the enclosed inspection report,

you identified these violations. Therefore, the violations will not be

subject to enforcement action because your efforts in identifying and -

correcting the violations meet the criteria specified in Section VII.B of the

" General Statement of Policy and Procedures for NRC Enforcement Actions,"

(Enforcement Policy,10 CFR Part 2, Appendix C (1992).

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter and the enclosed inspection report will be placed in the NRC

Public Document Room.

We will gladly discuss any questions you have concerning this inspection.

Sincerely.

-

4

[.- y

R. D. Lanksbury, Chief

Reactor Projects Section 3B

Enclosure: Inspection Report

No. 50-346/92017(DRP)

See Attached Distribution

9301120013 921231 $ l

PDR ADOCK 05000346 g\

G PDR

_

_ . . . . - . . . - . - .. - -. . - _ , - . - . ~ . _ . . . . - . . . . . -. . . - . . - . - . -

i

, .

DEC 311992 .

.

Centerior Service Company 2

.

cc w/ enclosure:

L. Storz, Plant Manager

DCD/DCD (RIDS) >

OC/LfDCB

Resident inspector, Rill

James R. Williams, State of Ohio

Robert E. Owen, Ohio

Department of Health

A. Grandjean, State of Ohio,

Public Utilities Commission

,