Notice of Violation from Insp on 850429-0503
ML20126H405
Person / Time
Site: Waterford Entergy icon.png
Issue date: 06/13/1985
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20126H390 List:
References
50-382-85-17, NUDOCS 8506180334
Download: ML20126H405 (1)


See also: IR 05000429/2005003

Text

.

.

APPENDIX A

NOTICE OF VIOLATION

Louisiana Power and Light Company Docket: 50-382

'Waterford Steam Electric Station, Unit 3 License: NPF-38

Based on the results of an NRC inspection conducted during the period of

April 29-May 3, 1985, and in accordance with the NRC Enforcement Policy (10 CFR

Part 2, Appendix C), 49 FR 8583, dated March 8, 1984, the following violation

was identified:

Failure to 'istablish Sampling Procedure

Technical Specification 6.8.1.a requires that " written procedures shall be

established, implemented, and maintained covering the activities

. . . recommended in Appendix A of Regulatory Guide 1.33, Revision 2,

February 1978. . . ." Paragraph 7 of Appendix A addresses gaseous

effluent sampling procedures. Chemistry department procedure CE-3-305,

" Sampling of Ventilation and Gaseous Waste Management Systems for

Radioactive Effluents," describes the procedure for sampling of waste gas

decay tanks.

Contrary to the above, on April 30, 1985, the NRC inspector observed

sampling of waste gas decay tank "B" which was collected from the pressure

indicator gauge associated with that waste gas decay tank, without the use

of an approved procedure, using a method not described in

procedure CE-3-305.

This is a Severity Level V Violation. (Supplement I) (382/8517-02)

Pursuant to the provisions of 10 CFR 2.210, Louisiana Power and Light Company

is hereby required to submit to this office, within 30 days of tre date of this

Notice, a written statement or explanation in reply, including: (1) the

corrective steps which have been taken and the results achieved; (2) corrective

steps which will be taken to avoid further violations; and (3) the date when

full compliance will be achieved. Consideration may be given to extending your

response time for good cause shown.

Dated: JUN 13 7985