Forwards Insp Rept 50-461/92-19 on 921201-03.No Violations Noted.One Exercise Weakness Noted
ML20126E904
Person / Time
Site: Clinton Constellation icon.png
Issue date: 12/18/1992
From: Pederson C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Jamila Perry
ILLINOIS POWER CO.
Shared Package
ML20126E909 List:
References
NUDOCS 9212300039
Download: ML20126E904 (3)


See also: IR 05000461/1992019

Text

-

3p t, 0

.

.

, .

DEC 181932

Docket No. 50-461

Illinois Power Company

ATTN: J. S. Perry

Vice President

Clinton Power Station

Mail Code V-275

P. O. Box 678

Clinton, IL 61727

Dear Mr. Perry:

SUBJECT: ROVIINE EMERGENCY PREPARE 0 NESS EXERCISE INSPECTION AT THE CLIN 10N

POWER STATION

This refers to the inspection conducted by Mr. C. Cox and others of this

affice on December 1-3, 1992. The inspection included a review of activities.

authorized at the Clinton Power Station. At the conclusion of the inspection,

the findings were discussed with those members of your staff identified in the

enclosed inspection. report.

Areas examined during the inspection are identified in the enclosed report.

Within these arets, the inspection consisted of a selective examination of

procedures and representative records, interviews with personnel, and

observations of activities in progress.

No violations of NRC requirements were identified during the course of this

inspection. However, one' exercise weakness was identified which will require

corrective action. This weakness is summarized in the Appendix to this

letter,

in accordance with 10 CFR Part 2.790 of the Commission's regulations, a copy

of this letter and the enclosed inspection report will be placed in the NRC

Public Document Room. "

i

9212300039 921218- '

ADOCK 05000461+

PDR

G PDR. A' @' 3 l

4

l

- - _.,

, ., _ _ _ _ _ ._ _.. _ _ . . _ . _ . _ _ _ _ _ _ _ _ _ . _ _ - -

t

.  !

4

Illinois Power Company 2 ,

We will gladly discuss any questions you have concerning this inspection.  !

Sincerely, ,

'Orliinal sttned by J. yl. lAccormick-Barter" l

Cynthia D. Pederson, Chief -

Reactor Support Programs Branch .

Enclosures:

1. Appendix, Exercise Weakness

2. Inspection Report

No. 50-461/92019(DRSS) .

- cc w/ enclosure:

J._ Cook, Manager, Clinton Power Station

F. Spangenberg III, Manager- ,

Licensing and Safety

DCD/DCB (RIDS)

OC/LFDCB -

Resident Inspector, RIII

LPM,NRR

J. McCaffrey, Chief, Public

Utilities Division

Patricia O'Brien, Governor's

Office of Consumer Services

S. 2nbcl, Esquire, Schiff, Hardin,

& Waite

K. K. Berry, licensing Services Manager

General. Electric Company

Chairman, DeWitt County Board

Illinois Department of

Nuclear Safety

Robert Newmann, Office of Public

Counsel, State of Illinois Center

Perry SRI

D. Bement, FEMA, Region V

. lfd

RIII- RIII Rlli Ri!I

Co dg H$ e ick-Barger PNersIf

12//r/92 (MJ j qjff93

,

L

FPEND]f

[XERCISLW_LAKN[SS

lhe initial protective action racommendations were not issued to the off-site

agencies in a timely manner. The notification forms to the state indicated

that the off-site agencies did not receive any protective action

recommendations from the utility until 25 minutes after the Emergency Manager

had declared the General Emergency. (Item No. 416/92019-02)(Section 5d)