_ _ _ _ _. - __
Cgmmtnwealth Edistn
.d__-
1400 Opus Place Downers Grove, filinois 60515 e
DeceN' e
, 1992 Dr. Thomas E. Murley, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regula'ory Commission c
Washington, D.C.
20555 Attn: Document Control Desk
Subject:
Quad Cities-Station Units 1--and 2 i
Hithdrawal of Application for Amendment to facility l
Operating Licenses'DPR-29 and DPR-30, Appendix A, Technical Specifications NRC Docket Nos. 50-254 and 50-265~
Reference:
(a)' Letter from J. Schrage (CECO) to-T.E. Murley (NRC),
l dated November 20,- 1991.
In the Reference (a) letter, Commonwealth Edison-.(CECO) proposed to-amend l
Section 3/4.1 of Appendix A, Technical Specifications ~to Facility.-Operating Licenses DPR-29 and DPR-30.
The proposed change involved a rewrite of the R9ctor Protection System section of the Technical Specifications and was j
submitted as part of an overall Technical Specifica 'on Upgrade Progam (TSUP).-
l The purpose of this letter is,to? inform your staff of CECO's plan-to
~
l formally. withdraw the proposed amendments for Quad' Cities Station.
New L
amendment requests, combined with identical Dresden Station amendment rep asts, are'being submitted as part of a Technical Specification Upgrade; Program at both Quad ~ Cities and Dresden Stations.
t-I 9212140051 9212041 -
. \\a l.
PDR ADDCK 05000254 1
e en
' ZNLD/1342/21 L
Dr.'T.E. Murley December 4, 1992 The new amendment requests will be patterned after the original Quad Cities submittal, but will more closely follow the guidelines presented in NUREG-0123, Revision 4.
In addition, the proposed amendments will make the Quad Cities and Dresden Technical Specifications identical within equipment and design limitations.
Please direct any questions you may have regarding thii matter to this office.
Sincerely, 4'
ete L. Piet Nuclear Licensing Administrator JLS/BCH/cah cc:
A.B. Davis - Regional Administrator, RIII C.P. Patel - Project Manager, NRR T. Taylor - Senior Resident Inspector, Quad Cities Office of Nuclear Facility Safety - IDNS l
t i