ML20119B072
| ML20119B072 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 05/08/2020 |
| From: | Blake Purnell Plant Licensing Branch III |
| To: | Bezilla M Energy Harbor Nuclear Corp |
| Purnell B | |
| Shared Package | |
| ML20119B079 | List: |
| References | |
| EPID L-2020-LLE-0026, EPID L-2020-LLE-0027, EPID L-2020-LLE-0028, EPID L-2020-LLE-0029, EPID L-2020-LLE-0030, EPID L-2020-LLE-0031, EPID L-2020-LLE-0032 | |
| Download: ML20119B072 (4) | |
Text
May 8, 2020 Mr. Mark B. Bezilla Site Vice President Energy Harbor Nuclear Corp.
Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO. 1 - REQUEST FOR TEMPORARY EXEMPTION FROM CERTAIN REQUIREMENTS OF 10 CFR PART 73, APPENDIX B, GENERAL CRITERIA FOR SECURITY PERSONNEL [COVID-19] (EPIDS L-2020-LLE-0026 THROUGH L-2020-LLE-0032)
Dear Mr. Bezilla:
The U.S. Nuclear Regulatory Commission has approved the enclosed temporary exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR), Part 73, Appendix B,Section VI, Nuclear Power Reactor Training and Qualification Plan for Personnel Performing Security Program Duties, for the Davis-Besse Nuclear Power Station, Unit No. 1.
This action is in response to your application dated April 23, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20114E221), as supplemented by letter dated May 6, 2020 (ADAMS Accession No. ML20128J218), that requested a temporary exemption from the periodic requalification requirements for security personnel in paragraphs B.5.(a), C.3.(l)(1), D.1.(b)(3), D.2.(a), E.1.(c), E.1.(f), and F.5.(a) of 10 CFR 73, Appendix B, Section VI.
A copy of the exemption is enclosed. This exemption expires 90 days after the end of the Coronavirus Disease 2019 (COVID-19) public health emergency, or December 31, 2020, whichever occurs first. The exemption will be forwarded to the Office of the Federal Register for publication.
If you have any questions, please contact me at 301-415-1380 or via e-mail at Blake.Purnell@nrc.gov.
Sincerely,
/RA/
Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
Exemption cc: Listserv
ENCLOSURE EXEMPTION
PKG: ML20119B076 LTR: ML20119B072 EXEMPT: ML20119B068 FRN: ML20119B070
- via e-mail OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA*
NSIR/DPCP/RSB/BC*
NAME BPurnell SRohrer ABowers (w/comments)*
DATE 05/07/2020 04/29/2020 05/07/2020 OFFICE OGC - NLO*
NRR/DORL/LPL3/BC*
NRR/DORL/D*
NAME MWoods (w/comments)
NSalgado CErlanger*
DATE 05/08/2020 05/08/2020 05/08/2020 OFFICE NRR/DORL/LPL3/PM NAME BPurnell DATE 05/08/2020