Withdraws 841101 Request for Mod of NRC 840302 Order Re Installation of Noble Gas Steam Effluent Monitor,Per NUREG-0737,Item II.F.1.1.Installation Completed During Next Outage of Sufficient Duration Following 841231
ML20117N114
Person / Time
Site: Calvert Cliffs  
Issue date: 05/09/1985
From: Poindexter C
BALTIMORE GAS & ELECTRIC CO.
To: John Miller
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.F.1, TASK-TM NUDOCS 8505170389
Download: ML20117N114 (1)


Text

BALTIM ORE GAS AND ELECTRIC CHARLES CENTER P.O. BOX 1475 BALTIMORE, MARYLAND 21203 ARTHUR E. LUNDVALL. JR.

vice pacs otw SUPPLY Director of Nuclear Reactor Regulation Attention: Mr. 3. R. Miller, Chief Operating Reactors Branch #3 Division of Licensing U.S. Nuclear Regulatory Commission Washington,' D.C. 20555

Subject:

Calvert Cliffs Nuclear Power Plant Units Nos.1 & 2; Dockets Nos. 50-317 and 50-318 NUREG-0737 Item II.F.I.1, Noble Gas Steam Effluent Monitor Gentlemen:

Baltimore Gus and Electric Company hereby withdraws its November 1,1984 request for modification of NRC Order dated March 2,1984, pertaining to the schedule for installation of the noble gas steam effluent monitor. As discussed with your staff on December 21,1984, installation of the subject instrumentation has been determined to be outage-related in that certain supporting work activities inside the main steam penetration room are required. Consequently, installation will be completed during the next scheduled outage of sufficient duration following December 31,1984, in accordance with the subject NRC order.

The work activities to be accomplished inside the main steam penetration room include:

(1) removal of the detector from the existing shield assembly and placement in a calibration test stand (to be set up in the room), (2) calibration and testing, and (3) replacement of the detector in the shield assembly. Also, the detector will be modified slightly by the addition of a low-power radiation source which will serve to provide a minimum continuous control room indication to facilitate periodic verification of system operability.

If you should have any questions, please do not hesitate to contact us.

Very truly yours, b

AEL/BSM/vf C. H. Poindexter cc: D. A. Brune, Esq.

for A. E. Lundvall, Jr.

G. F. Trowbridge, Esq.

Vice President-Supply Mr. D. H. Jaffe, NRC Mr. T. Foley, NRC 8505170389 850509 hDR ADOCK 05000317