THE COMMONWEALTH OF M ASSACHUSETTS h
DEPARTMENT OF THE ATTORNEY GENERAL JOHN W. Mc CORMACK ETATE OFFICE BUILDING ONE A5HWURTON PLACE. BOSTON 02105 raa w cie x. e sLLovvi cat gg7g.
.no.........
usNac W W 15 40:47 May 10, 1985 0FFIC OF SECRt4Ah v 00C Helen S.
Hoyt, Chairperson T g ERvlu.
Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Washington, DC 20555 Re:
Decket Nos. 50-443-OL, 50-444-OL l
Dear Judge Hoyt:
{
I note that the Board has requested from the Applicants a current construction status report.
For your information I enclose a copy of a decision of the Massachusetts Department of Public Utilities which concludes, at pages 48-49, that "...the earliest completion date which can reasonably be projected for Seabrook I on this record is August 1988 and...there is a substantial likeli-hood, based on both industry experience and the history of the Seabrook project, that an achievable completion date would be significantly later."
The detailed bases for these conclusions are set forth in the decision.
Thank you for considering this information as you review the Applicants' submission.
I
-Sincerely, j
N s
J Ann Shotwel Assistant Attorney General u Environmental Protection Division JAS/dd cc: