.. _ _ _

~

OPSEG Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Blusiness Unit SEP 0 51996 LR-N96276 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

SERVICE WATER SYSTEM OPERATIONAL PERFORMANCE INSPECTION FACILITY OPERATING LICENSE NPF-57 HOPE CREEK GENERATING STATION DOCKET NO. 50-354 On July 18, 1996, Public Service Electric and Gas Company (PSE&G) met with NRC personnel to discuss recent issues related to the Hope Creek Station Service Water System (SSWS) and Ultimate Heat l

Sink temperature limits.

At that meeting, PSE&G stated that a Service Water System Operational Performance Inspection (SWSOPI) would be performed at Hope Creek during the October-November, 1996, timeframe.

The purpose of this letter is to provide additional information relative to PSE&G's current plans for that inspection.

The Hope Creek SWSOPI will be jointly sponsored by Hope Creek Quality Assessment and Nuclear Engineering, utilizing NRC developed SWSOPI techniques.

Specifically, the SWSOPI will consist of a comprehensive audit of the SSWS and interfacing systems using selective sampling vertical-slice inspection i

i methods, including document reviews, walkdowns and personnel interviews to identify weaknesses or missing information in the operating or design basis documents.

The inspection will be performed in accordance with the guidance contained in NRC Temporary Instruction 2515/118, Service Water Systems Operational Performance Inspection, Revision 1, with emphasis on recently identified SSWS concerns and Hope Creek's response to Generic t

Letter 89-13.

(

The SWSOPI inspection team will consist of five inspectors with executive oversight provided by the Director of System Engineering.

The SWSOPI project manager will be the Manager of Hope Creek Quality Assessment and the team will be comprised of highly qualified and experienced SSWS inspectors.

A SWSOPI j

Response Team will also be formed to address insoection issues and ensure that the SWSOPI team receives adequate support during i

the inspection effort.

j

[/bi([b' 9609120067 960905 PDR ADOCK 05000354 G

Pm The nnens in y or hani m mon om i

l SEP 0 51996 o

l Document Control Desk LR-N96276 Detailed information concerning the experience and qualifications i

l of the SWSOPI team members is available for your review.

In l

addition, details from the SWSOPI inspection plan will also be provided at your request.

The current schedule for the SWSOPI is 1

October 14 to November 15, 1996.

A formal SWSOPI exit meeting is scheduled for November 22, 1996.

Should you require any addition details concerning the scope or schedule of the Hope Creek SWSOPI, please feel free to contact us.

l l

Sincerely,

. h ah i

D.

R.

Powell Manager -

Licensing and Regulation f

i C

Mr. H. Miller, Administrator - Region I U.

S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 l

l Mr.

D.

Jaffe, Licensing Project Manager - Hope Creek U.

S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 14E21 Rockville, MD 20852 Mr.

R.

Summers USNRC Senior Resident Inspector (X24)

Mr.

K.

Tosch, Manager IV Bureau of Huclear Engineering 33 Arctic Parkway

]

CN 415 Trenton, NJ 08625 i

2