F-

.t*

ver Valley Power Station Shippingport. PA 15077-0004 l

SUSHIL C.JAIN (412) 393-5512 DMalon V6ce Prealdent Fax (412) 643-8069 Nuclear Services Nuclear Power Division U. S. Nuclear Regulatory Comnussion August 15, 1996 Attention: Document Control Desk Washington, DC 20555-0001

Subject:

Beaver Valley Power Station, Unit No.1 I Docket No. 50-334, License No. DPR-66 Cycle 12 Startup Test Report Enclosed is a copy of the Cycle 12 Startup Test Report provided in accordance with Technical Specification 6.9.1.3 Item (2). This report summarizes the applicable physics testing performed to verify the adequacy of the Cycle 12 reload core design. The results of each test performed indicate that the measured parameters are within the specified ,

acceptance criteria.  !

Sincerely, 1

Sushil C. Jain l

l c: Mr. L. W. Rossbach, Sr. Resident Inspector

! Mr. H. J. Miller, NRC Region I Administrator 1 Mr. D. S. Brinkman, Sr. Project Manager fEDG ' ,

O'~iOO23 ottivERiNG GUAtITY 9608270151 960815 PDR ADOCK 05000334 ENERGV p PDR

,