ML20116J589
| ML20116J589 | |
| Person / Time | |
|---|---|
| Site: | Prairie Island |
| Issue date: | 08/09/1996 |
| From: | Wadley M NORTHERN STATES POWER CO. |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| Shared Package | |
| ML20116J590 | List: |
| References | |
| NUDOCS 9608130290 | |
| Download: ML20116J589 (2) | |
Text
l Northern States Power Company Prairie Island Nuclear Generating Plant 1717 Wakonade Dr. East Welch, Minnesota 55089 August 9,1996 U S Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Sinarn Generator Tube Sleeves Metallurgical Examination Results This letter is a follow-up to our May 3,1996 letter on the same subject. That letter submitted a proprietary report prepared by Combustion Engineering, CEN-628-P, Revision 01-P, " Verification of the Structural Integrity of the ABB CENO Steam Generator Welded Sleeve." By letter dated July 22,1996, you requested that we submit a non-proprietary version of this report. The non-proprietary version is attached to this letter.
In this letter we have made no new Nuclear Regulatory Commission commitments.
Please contact Jack Leveille (612-388-1121, Ext. 4662) if you have cay questions related to this letter.
Michael D Wadley g
Plant Manager g
Prairie Island Nuclear Generating Plant i
c: (see next page) e r, g 01 9608130290 960809 ADOCKOSOOg2 PDR P
USNRC NORTHERN STATES POWER COMPANY August 9,1996 Page 2 c:
Regional Administrator - Region Ill, NRC (w/o attachments)
Senior Resident inspector, NRC (w/o attachments)
NRR Project Manager, NRC J E Silberg (w/o attachments)
Attachments: CEN-628-NP,' Verification of the StructuralIntegrity of the ABB CENO j
Steam Generator Welded Sleeve," March 1966 i
METALRGI. DOC