Responds to IE Bulletin 83-03 Re Check Valve Failures in Raw Water Cooling Sys of Diesel Generators.Check Valves Radiographed During Fifth Refueling Outage.Repairs Made to Valves Which Did Not Fully Close When Flow Cut Off
ML20116G339
Person / Time
Site: Salem  PSEG icon.png
Issue date: 04/15/1985
From: Liden E
Public Service Enterprise Group
To: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-83-03, IEB-83-3, NUDOCS 8505010452
Download: ML20116G339 (1)


Text

O PSEG Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038 Nuclear Department April 15, 1985 t

Dr. Thomas E. Murley, Regional Administrator Region 1 U. S.. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406

Dear Dr. Murley:

'IE BULLETIN 83-03 CHECK VALVE FAILURES IN RAW WATER COOLING SYSTEMS OF DIESEL GENERATORS SALEM GENERATING STATION

-UNIT NOS. 1 AND 2 As committed in our response dated June 7, 1983, the applicable Unit 1 Check valves were radiographed during the fifth refueling outage.

It was determined that two of the valves did not fully close when flow was cut off.

Work orders were initiated and repairs were made to the affected valves.

This information was reviewed by the NRC Resident Inspector during the course of Combined Inspection 50-272/84-19 and 50-311/84-19 and found to be acceptable.

The above information completes the PSE&G response to IE Bulletin 83-03.

Should you have any questions regarding this information, please do not hesitate to contact us.

Sincerely, s

E. A. Liden Manager - Nuclear fl Licensing and Regulation f()"

C Mr. Donald C.

Fischer Licensing Project Manager Senior Resident Inspector g 50go g $$o The Energy People 2