Forwards Schedule for Completion of EOP Walkdowns,Aop Revs & Future EOP Revs to Incorporate Rev 1B of Erg,Per 900713 Response to Findings Noted in Insp Repts 50-334/90-80 & 50-412/90-80
ML20116B501
Person / Time
Site: Beaver Valley
Issue date: 10/22/1992
From: Sieber J
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9211020237
Download: ML20116B501 (3)


Text

4 Beaver va ey Power Station Shippingport. PA 15077-0004 (412) 393-5255 JOHN D SIEBER October 22, 1992 Vice Presideri Nuclear Group U.

S. Nuclear Regulatory Commission Attn:

Document Control Dcsk Washington, DC 20555

Subject:

Deaver Valley Power Station, Unit No. 1 and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 Combincd Inspection Report Nos. 50-334/90-80 and 50-412/90-00 The subject report documented f1rdings from an inspection of Emergency Operating Procedures (EOPs) at Beaver Valley Power Station.

By letter dated July 13,

1990, our response to the inspection report provided a

schedu?e for EOP satellite procedure walkdowns.

All walkdowns were to be completed by September 1, 1992.

However, approximately 25% of the walkdowns we;e not completed on the

~

spec.ified schedule.

Approximately one-half of the procedures that were required to be walked dowr.

were to be completed in conjunction with the Procedure Upgrade Project (PUP).

Delays in the completion of this project prevented some of these walkdowns from being completed on schedule.

Additional supp rt was necessary for other procedure related projects including station

blackout, outage support, and participation with industry working groups.

Presently, 75%

of the required procedure walkdownr have been complated.

The remaining procedure walkdowns will be completed by March 31, 1993.

Attachment 1

provides a

detailed schedule for completion of EOP walkdowns, Abnormal Operating Procedure (AOP) revisions, and future EOP revisions to incorporate Revisicn 1B of the Emergency Response Guidelines (ERG).

If there are any questions concerning this matter, please contact Charles O'Neill at (412) 393-4935.

Sincerely, a

f le q

f n;$$

bbhh31

' /L tbe /

I m on.

D.

Fieber 00

=

(

a

')

t, 2 *

-oy Attachment

,v S$

cc:

Mr.

L.

W.

Rossbach, Sr. Resident Inspector NO Mr.

T.

T.

Martin, NRC Region I Administrator Mr.

L.

H.

Bettenhausen, Chief Operations Branch, vy 0

Division of Reactor Safety

~g Mr.

A.

W.

De Agazio, Project Manager

&to Mr. M.

L.

Bowling-(VEPCO)

Mr.

L.

E, Briggs, NRC Region I, Senior Operations Engineer a

3 DUQUESNE LIGHT COMPANY j

Nuclear.-Group j

Beaver Valley Power Station Units 1 and 2=

~

}l' ATTACHMENT 1 4

EOP Walkdown Comoletion/ Comment Incorporation Schedule

'f l

1.

Emergency Operating Procedure (EOP) Satellite Procedures Sixty-nine (69) procedures require a walkdown 3

In order to. maintain the remainder of the upgrade project on

schedule, the EOP satellite procedures will be walked down i

by March 31, 1993 4-Any identified Jiscrepancies will

'be resolved (through procedure revision, Operating Manual Change Notice rOMCN) or 2

{

other resolution) by December 31, 1993 l

2.

Incorporation of Abnormal Operating Procedure (AOP)

Walkdown i

comments (both units) l Completion of Unit 2.AOP s - aowns by December 31, 1992 i

Review 9 pen Operc.i ing Mar.ual Deficiency Reports (OMDRs) i Review discrepancies generated-during walkdown of AOPs Draft changes te ACPs Perform appropriate validation Incorporate validation comments i

Perform verification 1

Obtain Onsite Safety Committee (OSC) concurrence I

l Obtain approval ~ by June-30, 1993 Above changea will be coordinated with training to' ensure issuance prior t.o due date_-(training must be-. completed prior to issuance) i-Issue revised procedures by September 30, 1993 3.

Incorporation of Emergency Response Guideline (ERG) Revision 1B (Unit 1)

Review ERG changes versus BV-1 EOPs 1.

Review open OMDRs l

Review -discrepancies generated during Ur.it I walkdown of EOP j

attachments

. ~.

~.... -. - - - -

=

.ATTACHME!1T 1 (Continuad) l t

b-l 3.

(Continued)

Draft-changes to

EOPs, EOP attachments, EOP background documents and EOP deviation sheets 4

Perform appropriate validation Incorporate validation comments P?rform verification L

Obtain OSC concurrence Obtain approval by March 31, 1994 i

Above changes will be coordinated with training to ensure issuance prior to due date (training muct be comple ted Eprior to issuance) i Issue

/ised procedures by June 30, 1994 i

4.

Incorporation of ERG Revision 1B (Unit 2)

Review ERG changes versus BV-2 EOPs Review open OMDRs 1

Review. discrepancies generated during Unit 2 walkdown of EOP attachments l

Draft changes to-EOPs, EOP. attachments, EOP background documents and EOP deviation sheets Perform appropriate validation i

Incorporate-validation comments j

Perform verification i

}

Obtain OSC concurrence i

Obtain approval by June 30, 1994 i

Above-changes will be. coordinated with training to ensure-issuance prior 1to due date (training must be completed prior-to issuance)

)

Issue revised procedures by. September 30, 1994.